KAKATIYA 600 MW


Seal Air Fans Erection/In progress

PA Fan B Motor Erection/In progress

FD Fan B Motor Erection/In progress

Station Transformer work/Under progress

IPBD and GT work/Under progress

BOF to ESP duct work/Under progress

Preparation for Acid Cleaning of Boiler/Under progress

ID Fan with Inlet and Outlet Duct/

Electro Static Precipitator/

Boiler Bottom Ash Hopper/

GT ERECTION WORKS UNDER PROGRESS/

MILLS WORKS UNDER PROGRESS/

BOILER LIGHT UP ON 31.05.2015/

Station Transformer placed on respective foundation/

SPBD erection under progress for ST,UAT

WORKS UNDER PROGRESS AT TFBFP- B AREA/

INSULATION ERECTION WORKS UNDER PROGRESS ESP TO ID TO CHIMNEY ( NORTH SIDE)/

RHS MILLS WORKS UNDER PROGRESS/

BOF to ESP Duct Erection U/p in left side/

IV CONTROL VALVE PIPING WORKS UNDER PROGRESS/

GENERATOR TRANSFORMER PLACEMENT UNDER PROGRESS. /

WORKS UNDER PROGRESS AT TFBFP- B AREA./

INSULATION ERECTION WORKS. ESP TO ID TO CHIMNEY ( NORTH SIDE)/

RHS MILLS WORKS UNDER PROGRESS./

FUEL OIL PUMP HOUSE (FOPH) TO BOILER PIPING ERECTION WORKS UNDER PROGRESS/

BUS DUCT ERECTION FROM STAGE-I/In Progress

CRITICAL PIPING WORKS BELOW 8.5m EL./In Progress

TDBFP LUB OIL COOLER PIPING WORKS/In Progress

OIL CANAL WORKS/ In progress

RE JOINTS FIT UP ( OUTLET LINE)/In Progress

IVCV VALVES/In Progress

FD Fan to APH/In Progress

ESP outlet to ID Fan/ In progress

ESP Pass D insulation Work/In Progress

Plant View/

RHS MILLS ALONG WITH LOS AND ASSOCIATED COAL PIPING WORKS/In Progress

Boiler/In Progress

RHS Mills/In Progress

PA, FD and ID Fan/In Progress

Condenser Area/In Progress

Turbine Area/In Progress

Bottom Furnace Area/Customer Front not available

0 Mtr Foundations

Power House Floors/Customer Front not available

BOF to ESP Duct/Customer Front not available

ESP to ID duct/Customer Front not available

GT

Cooling Tower/Customer Scope

Switch Yard/Customer Scope

CW Piping/Customer Scope

DG Compressor Area/Customer Scope