Seal Air Fans Erection/In progress
|
PA Fan B Motor Erection/In progress
|
FD Fan B Motor Erection/In progress
|
Station Transformer work/Under progress
|
IPBD and GT work/Under progress
|
BOF to ESP duct work/Under progress
|
Preparation for Acid Cleaning of Boiler/Under progress
|
ID Fan with Inlet and Outlet Duct/
|
Electro Static Precipitator/
|
Boiler Bottom Ash Hopper/
|
GT ERECTION WORKS UNDER PROGRESS/
|
MILLS WORKS UNDER PROGRESS/
|
BOILER LIGHT UP ON 31.05.2015/
|
Station Transformer placed on respective foundation/
|
SPBD erection under progress for ST,UAT
|
WORKS UNDER PROGRESS AT TFBFP- B AREA/
|
INSULATION ERECTION WORKS UNDER PROGRESS ESP TO ID TO CHIMNEY ( NORTH SIDE)/
|
RHS MILLS WORKS UNDER PROGRESS/
|
BOF to ESP Duct Erection U/p in left side/
|
IV CONTROL VALVE PIPING WORKS UNDER PROGRESS/
|
GENERATOR TRANSFORMER PLACEMENT UNDER PROGRESS. /
|
WORKS UNDER PROGRESS AT TFBFP- B AREA./
|
INSULATION ERECTION WORKS. ESP TO ID TO CHIMNEY ( NORTH SIDE)/
|
RHS MILLS WORKS UNDER PROGRESS./
|
FUEL OIL PUMP HOUSE (FOPH) TO BOILER PIPING ERECTION WORKS UNDER PROGRESS/
|
BUS DUCT ERECTION FROM STAGE-I/In Progress
|
CRITICAL PIPING WORKS BELOW 8.5m EL./In Progress
|
TDBFP LUB OIL COOLER PIPING WORKS/In Progress
|
OIL CANAL WORKS/ In progress
|
RE JOINTS FIT UP ( OUTLET LINE)/In Progress
|
IVCV VALVES/In Progress
|
FD Fan to APH/In Progress
|
ESP outlet to ID Fan/ In progress
|
ESP Pass D insulation Work/In Progress
|
Plant View/
|
RHS MILLS ALONG WITH LOS AND ASSOCIATED COAL PIPING WORKS/In Progress
|
Boiler/In Progress
|
RHS Mills/In Progress
|
PA, FD and ID Fan/In Progress
|
Condenser Area/In Progress
|
Turbine Area/In Progress
|
Bottom Furnace Area/Customer Front not available
|
0 Mtr Foundations
|
Power House Floors/Customer Front not available
|
BOF to ESP Duct/Customer Front not available
|
ESP to ID duct/Customer Front not available
|
GT
|
Cooling Tower/Customer Scope
|
Switch Yard/Customer Scope
|
CW Piping/Customer Scope
|
DG Compressor Area/Customer Scope
|