JITPL DERANG UNIT 2


CEPs/Alignment completed, ready for motor trial run

Drain Cooler

Seal Oil System/Ready for flushing

Vacuum Pump /Erection completed

LPBP Skid/Placed in position

MOT Room/Lube Oil Flushing in progress

TDBFP-A/Lube Oil Flushing readiness in progress.

ERECTION OF PRIMARY WATER UNIT/completed

ERECTION OF MDBFP OIL COOLERS AND PW COOLERS/completed

SEAL STEAM PIPING WELDING WORK/IN PROGRESS

LPBP Valve Platform at 8.50 mtr./NOT AVAILABLE

PLATFORM (at 8.5 mtr) FOR WATER INJECTION SYSTEM/NOT AVAILABLE

IV INLET PIPE WELDING/IN PROGRESS

Generator /Ready for final Alignment and coupling with LP

IP-Inlet Assembly/Erection completed, Preparation for welding in progress

WELDING OF LP-1

GS Condenser/Preparation for CW Side hydro test in progress

TS Condenser/COLTCS work in progress

Overall View/Erection in Progress

Boiler

Boiler RHS and LHS/In Progress

Boiler to ESP Duct Foundation/In Progress

TG Floor/In Progress

FD Fan B

Transformer Yard/In Progress