Home   

KAHALGAON FGD (4X210+3X500 MW)


U#5 chimney

U#7 Chimney 3rd Segment

Ball Mill Equipment Foundation

Unit#5 Absorber: Top Slab in Curing

Switch Gear Building Unit#6

Unit#6 Absorber

Unit#6 Chimney Pile Chipping in progress

U#7 Absorber: Work in progress

UNIT#7 Chimney: Shuttering work for 04th Segment

U#3&4 Absorber & Booster Fan Area

Wt Ball Mill Equipment Foundation casting

U#7 Chimney - 3rd Segment Casting completed

U# 5Chimney Slip Form Work in progress

U#3&4 Booster Fan: Piling in Progress

U#6 Chimney pile chipping under progress

U#7 chimney ready for pile cap casting

U#7 Absorber pile cap casting completed

U#1 and 2 Absorber Raft Casting Completed

U#5 Chimney-3rd Segment Raft Casting Started today

U#5 Absorber Raft Completed

Process Water Tank concreting in progress

U#1&2 Absorber PIT under porgress

U#5 Chimney- 1st Segment Raft completed

U#7 Chimney

U#5 Absorber

U# 5Chimney

U# 5Chimney

Chimney U#7 reinforecement work under progress

U#6 Booster fan raft casting completed

Chimney #5 1st raft casting completed

U#5 Chimney: R/F binding under progress

U#6 Chimney Excavation under progress

U#5 Booster Fan raft concreting completed

PIT in U#5 Absorber under Progress

Control Room Building-II Pile cap casting

Process Water Tank (B) Lift Wall Casting

U#5 Chimney: R/F binding under progress

U#5: Booster Fan (B) Raft Casting (248 cum)

Control Room Building Casting-II

Gypsum Shed Pile Cap casting

U#6 Absorber: Piling Head Chipping in Progress

U#3*4 Absorber: Clearance of hindrance

U#3&4 Chimney-Clearance of Hindrance in Left Area

U#7 Chimney Pile Head Chipping cleaning

U#5 Chimney R/F Laying in progress

Unit#3&4 Booster Fan are under development by NTPC

Unit#3&4 Area under development by NTPC

Crusher House Chipping in process

Booster Fan#5 Chipping process

PCC of Chimney#5

RCC work of Unloader Unit

RCC work of Pump House(SWDW)

Excavation of Chimney#7 in process

Excavation of Chimney#7 completed

Chimney#5 under progress

Truck Unloader R/F Binding

Construction Power under progress

FGD Control Stage-1: Foundation Breaking by NTPC

Chimney# Excavation under progress

Piling of Chimney#3&4 Started on 13.07.22

Absorber#1&2 Piling Work

Crusher House Piling Work Under Progress

Truck Unloader Unit Work Progress

Truck Unloader Unit Area Excavation Started

Debris under progress for Front of Absorber #3&4

Hindrances to Fronts for Unit#3&4 Booster Fan

Safety Talk by BHEL Safety

Safety Talk by GM/PD at Site

Tree plantation on World Environment Day

Chimney 1&2 Job Piling Progress

Unit 1&2 Chimney Job Piling

Gypsum Shed Job Piling

Unit 7 Job Piling under Progress

Unit 7 Chimney Job Piling

Unit 5 Job Piling under Progress

Unit 5 Chimney Job Piling

Unit#1&2 Chimney Piling Under Progress

Test Pile Stage I commenced

Test Pile Stage I commenced

Trial mix testing

Kahalgaon site office renovation

Test Piling Commencement at site on 24 01 22

Test Piling Commencement

Forest cleaning in FGD Area of Unit-5

Forest cleaning of FGD area of Unit-7

Forest cleaning of FGD area of Unit-7

Forest cleaning of FGD area of Unit-6

Forest cleaning of FGD area of Unit-6

Forest cleaning of Unit-5 area

Site Office Renovation work under progress.

batching Plant Installation under progress