29.04.24 Unit#7 Block # 3&4 Duct foundations
|
29.04.24 LST Tank
|
25.04.24 33KV switchgear
|
22.03.2024 Gypsum Dewatering
|
20.04.2024 Chimney #5 Grade Slab
|
06.04.2024 Road Works between Absorber# Stage#1 an
|
04.04.2024 Stage#1 Absorber (2)
|
04.04.2024 Intermediate Silo
|
02.04.2024 33KV Switchgear building first floor ca
|
02.04.2024 33KV Switchgear Building
|
27.03.2024 Absorber Stage#1 Erection start puja (
|
22.03.2024 FGD Control Room Building First Floor B
|
22.03.2024 Gypsum Dewatering building- Belt filter
|
18.03.2024 Wett ball mill 2
|
15.03.2024 Unit#4 Booster Fan-B
|
15.03.2024 Unit#4 Booster Fan-B
|
15.03.2024 Unit#4 Booster Fan-B (2)
|
12.03.2024 Truck Tippler Grade Slab casting
|
08.03.2024 Limestone Weigh bridge
|
08.03.2024 GYPSUM DEWATERING BELT WASH TANK
|
08.03.2024 TT WEIGH BRIDGE
|
07.03.2024 Unit#7 Block#3
|
07.03.2024 Switchgear Room
|
07.03.2024 Switchgear Room (2)
|
07.03.2024 Booster Fan-4b
|
05.03.2024 GYPSUM DEWATERING BELT WASHING TANK
|
03.03.2024 Limestone Weigh Bridge
|
01.03.2024 Absorber Stage#1 Second Stage Casting
|
06.02.2024 Duct Erection Unit#5 Block#3
|
06.02.2024 FGD cr (2)
|
07.02.2024 Unit#5 Block#5 Duct Structure Erection
|
04.02.2024 Spool Duct Erection in Unit#5 Completed
|
16.01.2024 cKE WASH & BELT WASH
|
07.02.2024 Unit#7 Chimney Beam Erection started
|
07.02.2024 Unit#7 Chimney Beam Erection started (2
|
07.02.2024 Unit#7 Absorber Second Stage Casting af
|
30.12.2023 Unit#6 Chimney
|
29.01.2024 33Kv Swgr
|
20.01.2024 FGD Control Room
|
04.01.2024 Stage#1 RC Pump and Oxidation blower ar
|
04.01.2024 Stage#1 Booster Fan Raft Casting works
|
04.01.2024 Stage#1 Booster Fan and Elevator founda
|
04.01.2024 Stage#1 Booster Fan and Duct Foundation
|
04.01.2024 Intermediate Silo
|
04.01.2024 Gypsum dewatering building- plinth beam
|
04.01.2024 FGD control Room (2)
|
02.1.2024 Unit#5 Absorber and booster Fan
|
02.01.2024 TT area Overview
|
02.01.2024 Gypsum shed plinth beam shuttering work
|
02.01.2024 Ball Mill area
|
23.11.2023 Unit#7 Chimney area
|
23.11.2023 Unit#4 Chimney
|
23.11.2023 FGD control Room
|
22.11.2023 Silo Fabrication
|
22.11.2023 ECW & ACW Pump House
|
22.11.2023 Crusher House Erection works
|
21.11.2023 Unit#7 Absorber & Chimney
|
21.11.2023 Unit#6 Chimney
|
21.11.2023 Unit#5 Block#5
|
21.11.2023 Unit#5 Blcok#4
|
21.11.2023 Unit#4 Block#7
|
21.11.2023 Stage#1 Block#3 Duct Erection work.
|
21.11.2023 Stage #1 Block#3 Duct erection works
|
21.11.2023 LHP & GHP area
|
21.11.2023 Gypshum Dewatering area
|
21.11.2023 ECW & ACW pump House
|
21.11.2023 Crusher House & Silo area
|
08.11.2023 Unit#4 Block#7 (2)
|
07.11.2023 Tank Area
|
02.11.2023 HOP NTPC KOrba Welcomed by AGM & CM Kor
|
02.11.2023 HOP KOrba Welcomed by GM & PD Korba FGD
|
01.11.2023Site Status Review by NTPC Director Proj
|
01.11.2023 NTPC Director( Designate) Wecomed by GM
|
01.11.2023 NTPC Director( Designate) Wecomed by AG
|
01.11.2023 NTPC Director Project( Designate ) Site
|
01.11.2023 NTPC Director ( Designate) review of Ko
|
31.10.2023 Unit#5 Block#1
|
29.10.2023 Stage#1 Chimney Shell Casting Completed
|
29.10.2023 Stage#1 Chimeny Shell casting completed
|
29.10.2023 Stage#1 Chimeny Shell casting completed
|
21.10.2023 Truck Tippler Area
|
21.10.2023 IM Silo
|
21.10.2023 Gypsum Shed Area
|
20.10.2023 Crusher House Area
|
20.10.2023 Ball Mill area2
|
20.10.2023 Ball Mill area
|
19.10.2023 Crusher House Area Night View
|
19.10.2023 Crusher House Area Evening View
|
17.10.2023 Unit#5 Absorber & Elevator
|
17.10.2023 FGD control Room
|
17.10.2023 FGD control Room (2)
|
17.10.2023 FGD control room
|
13.10.2023 Unit#5 Chimney Beam Erection Puja works
|
13.10.2023 Unit#5 Chimney Beam Erection Puja works
|
13.10.2023 Unit#5 Chimney Beam Erection Puja works
|
13.10.2023 Unit#5 Chimney Beam Erection Puja works
|
13.10.2023 Unit#5 Chimney Beam Erection Puja works
|
13.10.2023 Unit#5 Chimney Beam Erection Puja works
|
10.10.2023 Elevator Unit#6
|
10.10.2023 Elevator Unit#5
|
10.10.23 FGD CONTROL ROOM
|
07.10.2023 Ball Mill Building Area
|
30.09.2023 Unit#6 Block#3 Duct foundations
|
30.09.2023 Unit#5 Block#4 Duct Location
|
30.09.2023 Unit#5 Block#4 duct foundations
|
30.09.2023 Unit#5 Block#4 duct foundations (2)
|
30.09.2023 Unit#5 Block#4 duct foundation
|
30.09.2023 Unit#5 Absorber area
|
30.09.23 MISC TANK AREa
|
30.09.23 FGD CONTROL ROOM
|
30.09.23 Crusher house LHP GHP AREA
|
30.09.23 Crusher house LHP GHP AREA
|
30.09.23 CRUSHER HOUSE AREA
|
20.09.2023 Unit#6 Chimney area
|
20.09.2023 Unit#6 Block#6 Duct Foundations
|
20.09.2023 Unit#5 Blcok#6 area Duct
|
20.09.2023 Unit#5 Blcok#5 Duct Foundations
|
20.09.2023 Unit#4 Abdorber Area and Duct Foundatio
|
20.09.2023 Unit#4 Abdorber Area and Duct Foundatio
|
20.09.2023 Stage#1 RC Pumps Foundations
|
20.09.2023 Stage#1 RC Pump Foundations
|
20.09.2023 Stage#1 Chimney
|
20.09.2023 FGD control room status
|
20.09.2023 Elevator Unit#6-1
|
20.09.2023 Elevator Unit#6
|
20.09.2023 Booster Fan Unit#7A&B
|
14.09.2023U#6 B#2
|
14.09.2023 UNIT#6 BLOCK#2
|
09.09.2023 Unit4 Block#7
|
09.09.2023 Unit#4 Block#6
|
09.09.2023 Unit#4 Block#5
|
09.09.2023 Unit#1 Block#4
|
09.09.2023 U#4 Block#5
|
09.09.2023 U#4 Blcok#6
|
28.08.2023 Unit#5 Block#3 Str Erection start
|
28.08.2023 Unit#5 Block#3 Duct Str Erection start
|
28.08.2023 Unit#5 Block#3 Duct Str Erection start
|
28.08.2023 unit#5 Block#3 Duct Str Erection start
|
28.08.2023 Unit#5 Block#3 Duct Str erection start
|
28.08.2023 Unit#5 Block#3 Duct Erection start
|
28.08.2023 Unit#5 Block#3 Duct Erection start (2)
|
28.08.2023 Unit#5 Blcok#3 Duct Str Erection start
|
22.08.2023 TT AREA CORBELL
|
22.08.2023 SILO AREA
|
22.08.2023 RC Unit#4
|
22.08.2023 LTP-1 & TT AREA
|
22.08.2023 GYPSUM SHED
|
22.08.2023 GYPSUM DEWATERING BUILDING
|
22.08.2023 GYPSUM DEWATERING AREA 2
|
22.08.2023 FGD Control room
|
22.08.2023 CRUSHER HOUSE AREA
|
22.08.2023 BALL MILL BUILDING AREA
|
21.08.2023 Unit#5 Block#6 Duct foundations
|
21.08.2023 Unit#4 Header Column Near Absorber and
|
21.08.2023 Stage#1 Block#4 Duct foundation Near Bo
|
21.08.2023 Stage#1 Block#4 Duct foundation Near Bo
|
21.08.2023 Stage#1 Block#3 Inside Central Store.
|
21.08.2023 Stage#1 Block#3 Central Store duct foun
|
21.08.2023 Stage#1 Block#3 Central Store Duct
|
09.08.2023 Primary Hydro cyclone tank
|
09.08.2023 Gypsum Dewatering Building
|
09.08.2023 Gypsum Dewatering Building
|
08.08.2023 Unit#1 Chimney 175Meter
|
07.08.2023 Unit#7 Chimney 31Meter
|
07.08.2023 Unit#7 Chimney 31Meter (2)
|
07.08.2023 Unit#5 Chimney 131Meter
|
07.08.2023 Unit#1 Chimney 173 Meter
|
09.08.2023 TT LTP-1 AREA COLUMN
|
09.08.2023 TT AREA COREBELL
|
09.08.2023 TT area Core bell
|
09.08.2023 LIMESTONE WB
|
09.08.2023 LIMESTONE WEIGH BRIDGE
|
09.08.2023 LIME STONE WEIGH BRIDGE
|
09.08.2023 Elevator #6
|
09.08.2023 Duct Unit#5 Block#5
|
09.08.2023 Duct Unit#5 Block#5 (3)
|
09.08.2023 Duct Unit#5 Block#5 (2)
|
09.08.2023 Duct Unit#1 Block#4
|
09.08.2023 Duct Unit#1 Block#4 (3)
|
09.08.2023 Duct Unit#1 Block#4 (2)
|
09.08.2023 Duct Unit#1 Block#3
|
09.08.2023 Duct Unit#1 Block#3 (3)
|
09.08.2023 Duct Unit#1 Block#3 (2)
|
09.08.2023 Duct Stage#1 Block#2
|
09.08.2023 Duct Stage#1 Block#2 (3)
|
09.08.2023 Duct Stage#1 Block#2 (2)
|
09.08.2023 Booster Unit#7B
|
09.08.2023 Booster Unit#7 A
|
09.08.2023 Booster Unit#5A
|
09.08.2023 BOOSTER FAN UNIT#6A&B
|
09.08.2023 BOOSTER FAN UNIT#6 A&B
|
09.08.2023 ACW-ECW Pump House
|
08.08.2023Limestone slurry Tank A
|
08.08.2023 Limestone slurry Tank B
|
08.08.2023 FGD Control Room
|
08.08.2023 FGD CONTROL ROOM
|
08.08.2023 FGD CONTROL ROOM (3)
|
08.08.2023 FGD control room (2)
|
31.07.2023 Unit#5 Blcok#5 Duct Footings Pic-1
|
31.07.2023 Stage#1 Block#3&4 Duct Footings Pic-4
|
31.07.2023 Stage#1 Block#3&4 Duct Footings Pic-3
|
31.07.2023 Stage#1 Block#3&4 Duct Footings Pic-2
|
31.07.2023 Stage#1 Block#3&4 Duct Footings Pic-1
|
31.07.2023 BUF#7A & &B Deck Slab
|
31.07.2023 BUF#5A Deck Slab
|
20.07.2023 Tank Works
|
20.07.23 Waste water tank
|
20.07.23 Secondary hydro cyclone tank
|
20.07.23 Process water tank
|
20.07.23 Filtrate water tank
|
20.07.23 FGD control room
|
20.07.23 FGD CONTROL ROOM (2)
|
20.07.23 Absorber unit#123
|
20.07.23 Absorber unit#7
|
20.07.23 Absorber 5
|
20.07.23 Absorber #7
|
20.07.23 Absorber unit#4
|
20.07.23 Absorber #6
|
20.07.23 Absorber #5
|
19.07.2023 Unit#7 Chimney
|
19.07.2023 Unit#6 Chimney
|
19.07.2023 Unit#5 Block#3 Duct
|
19.07.2023 Unit#4 Chimney
|
19.07.2023 Unit#1,2,3 Chimney 147Meter
|
19.07.23 Absorber #6
|
18.07.2023 Unit#5 Chimney 93.3Meter
|
18.07.23 Silo area
|
18.07.23 Crusher house
|
18.07.23 Ball mill area
|
15.07.2023 TT area Top
|
15.07.2023 TT area roof top
|
13.07.23 CHIMNEY(Unit#1) 142 METER
|
11.07.23 Unit #05 Chimney 90M shell
|
13.07.23 Chimney U# 07 13.5 meter
|
13.07.23 Intermediate Silo
|
13.07.23 Intermediate Silo (2)
|
13.07.23 Gypsum dewatering Building
|
13.07.23 Crusher House
|
13.07.23 Crusher House (2)
|
02.07.2023 Intermediate Silo and Ball mill area
|
02.07.23 Intermediate Silo and Ball mill
|
30.06.23 Unit#7 Absorber and BUF
|
30.06.23 Unit#6 Elevator
|
30.06.23 Unit#6 Absorber
|
30.06.23 Process Water Tanks
|
30.06.23 Intermediate Silo
|
30.06.23 Crusher house
|
29.06.2023 TT AREA
|
29.06.2023 TT AREA
|
29.06.2023 LBC-1AB
|
29.06.23 Stage#1 Chimney
|
26.06.23 FGD CONTROL ROOM
|
24.06.23 Unit#5 Chimney Shell Wall curing
|
24.06.23 Unit #05 Chimney curing work is progress
|
24.06.23 Stage#01 chimney shell curing work going
|
24.06.23 Crusher house area Concrete Start pooja
|
23.06.23 Unit#5 shell curing work in progress..
|
23.06.23 Stage #1 Chimney shell curing work in pr
|
23.06.23 TT AREA
|
23.06.23 Stage#1 Chimeny shell curing work in prog
|
12.06.2023 Elevator unit#7
|
12.06.2023 Elevator Unit#6
|
12.06.2023 Elevator Unit#5
|
12.06.2023 Elevator Unit#4
|
12.06.2023 Elevator stage-1
|
12.06.2023 BUF#7 and Absorber#7
|
12.06.2023 Ball Mill area & Intermediate Silo
|
12.06.2023 Absorber#5
|
12.06.2023 Absorber #6
|
12.06.23 FGD control room area
|
12.06.23 FGD CONTROL ROOM AND CHIMNEY-4
|
12.06.23 Crusher house area
|
12.06.23 Chimney-7 and Absorber #7
|
12.06.23 Chimney-6
|
12.06.23 Chimney-5 63.8 Meter
|
12.06.23 Chimney stage-01 108Meter
|
12.06.23 ACW ECW AREA
|
01.06.23 Unit#6 Chimney
|
03.06.23 Unit-7 Oxidation Blower-B and rest of Abs
|
03.06.23 Unit-7 Booster fan and deck slab nearby j
|
03.06.23 Unit-7 Booster fan and deck slab nearby j
|
03.06.23 Unit-6 area
|
03.06.23 Unit-5 Booster fan and block-6 duct area
|
03.06.23 Unit-5 absorber and RC pump area
|
03.06.23 Unit-1,2&3 Chimney
|
03.06.23 Silo area
|
03.06.23 Gypsum shed
|
03.06.23 Gypsum dewatering building (2)
|
03.06.23 Crusher house area (2)
|
03.06.23 Ball- mill area
|
01.06.24 FGD CR
|
01.06.23 Stage#1 CHIMNEY
|
01.06.23 RC#4
|
01.06.23 RC #7
|
01.06.23 Chimney-7
|
01.06.23 Chimney-5
|
01.06.23 BUF#7
|
01.06.23 BUF STAGE#1
|
01.06.23 BUF STAGE#1
|
01.06.23 Absorber #4
|
16.05.23 Excavation in process U#5 block#3
|
19.05.23 FGD control room plinth beam work started
|
17.05.23 FGD control room (4)
|
17.05.23 FGD CONTROL ROOM (3)
|
17.05.23 FGD CONTROL ROOM (2)
|
17.05.23 FGD control room
|
14.05.23 Unit #05 Chimney wall curing work
|
15.05.23 Chimney
|
15.05.23 RC pump #7 (2)
|
15.05.23 RC pump #7
|
13.05.2023 Absorber Unit#7
|
13.05.2023 Unit#5 Block #3 Duct Pre assembly
|
13.05.2023 Chimney Stage#1 area
|
13.05.2023 Chimney #4 area
|
13.05.2023 Central Store Area
|
13.05.2023 BUF #7 Area Road
|
13.05.2023 Absorber #7 Area
|
09.05.2023 09.05.23 Unit #06 pile cap 5th segments
|
12.05.2023 Stage#1 Chimney
|
11.05.2023 Stage#1 Chimney
|
09.05.23 Chimney Unit-1, Rcc Shell Curing work in
|
06.05.23 Chimney-7 absorber 7 booster fan 7
|
06.05.23 Chimney-5
|
06.05.23 Booster fan 5A
|
06.05.23 RC PUMP 7
|
06.05.23 Elevator 5
|
06.05.23 Elevator 7
|
06.05.2023 Absorber #6
|
06.05.23 Absorber 5
|
06.05.23 Chimney unit-07
|
06.05.2023 Chimney #6
|
06.05.23 Chimney unit-5
|
06.05.23 Chimney unit-4
|
06.05.23 Chimney unit 1,2&3
|
13.04.23 Chimney-7
|
12.04.23 Chimney #6
|
13.04.23 Unit #06 chimney pile cap 3rd segments
|
12.04.23 Chimney #4
|
13.04.2023 Chimney Stage#1, Chimney #4 and Chimney
|
14.04.2023 Chimney Stage#1 50Meter (2)
|
14.04.2023 Chimneys Stage#1 50Meter Achieved
|
14.04.2023 Chimney Stage#1 50Meter
|
13.04.23 FGD CONTROL ROOM AREA
|
13.04.23 ACW ECW PUMP HOUSE
|
30.03.23 Chimney Stage#1
|
29.03.2023 Stage#1 Chimney (2)
|
29.03.2023 Stage#1 Chimney
|
29.03.2023 Stage#1 Chimney
|
29.03.2023 Stage#1 Chimney
|
29.03.2023 Satge#1 Chimney
|
25.03.2023 Chimney #5
|
30.03.23 Chimney #7
|
30.03.23 Chimney #7
|
30.03.23 Chimney #6
|
28.03.2023 Crusher House
|
29.03.2023 Flue can Fabrication
|
29.03.2023 Flue can fabrication yard
|
29.03.2023 Flue can Fabrication yard (2)
|
29.03.2023 Flue can Fabrication
|
29.03.2023 Flue can fabrication
|
29.03.23 U#5 Block#3
|
28.03.2023 Duct Unit#5 Block#3
|
05.04.2023 Chimney#4 (2)
|
05.04.2023 Chimney#4
|
30.03.23 Absorber #5 (3)
|
30.03.23 Absorber #5 (2)
|
30.03.23 Absorber #5
|
30.03.23 Absorber #6
|
30.03.23 Absorber #6 (3)
|
30.03.23 Absorber #6 (2)
|
30.03.23 Booster Fan#7 (3)
|
30.03.23 Absorber #6
|
30.03.23 Booster Fan#7 (3)
|
30.03.23 Booster Fan#7 (2)
|
30.03.23 Booster Fan#7
|
30.03.23 ELEVATOR #7
|
30.03.23 ELEVATOR #7 (2)
|
30.03.23 Absorber #7
|
30.03.23 Absorber #4
|
30.03.23 RC pump #4
|
30.03.23 Chimney Stage #1 absorber
|
29.03.2023 Stage#1 Absorber and BUF
|
05.04.23 Process Water Tank
|
30.03.23 Process water tanks (2)
|
30.03.23 Process water tanks
|
05.04.23 Gypsum Dewatering
|
05.04.23 Gypsum Shed
|
05.04.23 Ball Mill area
|
28.03.2023 Ball Mill Area
|
31.03.2023 BOOSTER FAN#5
|
30.03.23 Booster Fan#5
|
31.03.2023 NTPC GM FGD Visit at Korba Site
|
31.03.2023 NTPC ED PM FGD Visit
|
31.03.2023 Chimney#4 Shell casting start occasion
|
31.03.23 Chimney #4 Shell casting start puja
|
UNit#4 Chimney
|
23.03.2023 Unit#7 RC Pump and Header Column
|
23.03.2023 Unit#5 Booster Fan #5A
|
23.03.2023 Unit#7 Block#3 Duct Foundation
|
23.03.2023 Unit #7 Block#4 Duct Foundation
|
23.03.2023 Unit #5 RC Pump and Header Column
|
23.03.2023 Stage#1 Booster Fan#A
|
22.03.23 Unit #06 pile cap 1st segment concreting
|
22.03.23 U#6 Chimney Raft Casting first Segment
|
22.03.23 U#6 Chimney Raft Casted First Segments
|
21.03.2023 U#6 Chimney Raft Casting Puja By NTPC G
|
21.03.2023 Gethering During Puja of U#6 Raft Casti
|
21.03.23 Unit#6 Chimney Raft Casting Puja by NTPC
|
21.03.23 Unit#6 Chimney Raft Casting Puja by NTPC
|
21.03.23 Unit#6 Chimney Raft Casting Puja by BHEL
|
21.03.23 Unit#6 Chimney Raft Casting Puja by BHEL
|
21.03.23 U#6 Chimney Raft Casting start Puja by NT
|
21.03.23 Raft Casting First Segment
|
20.03.23 Unit #06 chimney pile cap 1st segment shu
|
16.03.23 Chimney #7
|
16.03.23 Chimney #7 and Stage#1 Chimney
|
16.03.23 Chimney #7
|
16.03.23 Chimney#7 and absorber #7
|
15.03.23 FGD control room (2)
|
15.03.23 FGD CONTROL ROOM
|
15.03.23 Chimney #4 (2)
|
15.03.23 Chimney #4
|
16.03.23 Booster#7
|
16.03.23 Chimney #7 and Absorber#7
|
16.03.23 Absorber #7
|
16.03.23 Absorber #6
|
16.03.23 Chimney #6
|
16.03.23 Chimney #6
|
11.03.23 TPV4 pile head done
|
11.03.23 Unit#5 Absorber and RC pump
|
13.03.23 Unit#6 Absorber
|
14.03.23 Unit #06 chimney pile cap 1st segment Top
|
13.03.23 Unit#6 Chimney (2)
|
13.03.23 Unit#6 Chimney
|
15.03.23 Unit #04 chimney Slip for trusses erectio
|
14.03.23 Unit #04 chimney Slip for 04 nos. trusses
|
11.03.23 Unit #04 chimney Slip for erection bottom
|
11.03.23 Unit #04 chimney Slip for erection bottom
|
11.03.23 unit#4 Chimney (2)
|
11.03.23 unit#4 Chimney
|
13.03.2023 TANK FABRICATION START PUJA BY SAMAY EN
|
13.03.2023 TANK START PUJA BY NTPC OFFICIAL
|
13.03.2023 TANK FABRICATION START PUJA BY NTPC OFF
|
13.03.2023 TANK FABRICATION START PUJA BY NTPC OFF
|
13.03.2023 TANK FABRICATION START PUJA BY CM SITE
|
13.03.2023 TANK FABRICATION START PUJA BY CM SITE
|
13.03.2023 TANK FABRICATION START PUJA BY BHEL OFF
|
13.03.2023 TANK FABRICATION START PUJA BY BHEL OFF
|
13.03.2023 PUJA BY NTPC OFFICIAL
|
13.03.2023 POOJA BY NTPC GM FGD
|
13.03.2023 POOJA BY NTPC GM FGD (2)
|
13.03.2023 Curing work is going on at Unit #1,2
|
27.02.2023 Vertical Load Test Ch#6 (2)
|
27.02.2023 Vertical Load Test Ch#6 (3)
|
27.02.2023 Vertical Load Test Ch#6 (4)
|
27.02.2023 Vertical Load Test Ch#6
|
11.03.23 Chimney 6 block unloading completed
|
04.03.2023 Waste water Tank
|
04.03.2023 Crusher House status
|
28.01.23 Crusher House Excavation started
|
24.02.2023 Unit#7 Chimney Shell casting start geth
|
24.02.2023 UNit#7 Chimney Shell casting Pooja by G
|
24.02.2023 Unit#7 Chimney Shell casting Pooja by C
|
24.02.2023 Unit#7 Chimney Gethering of Workmens du
|
24.02.2023 Unit#7 Chimney Slipform Assembly Shell
|
24.02.2023 U#7 Chimney Shell Casting Slipform asse
|
24.02.23 Unit#7 Chimney Slipform assembly for Shel
|
24.02.23 Pooja Unit#7 Chimney Shell casting start
|
24.02.23 Pooja Unit#7 Chimney Shell casting start
|
15.02.2023 Stage#1 Chimney
|
15.02.23 Stage#1 Chimney
|
17.02.23 Chimney-5 (2)
|
17.02.23 Chimney #5
|
17.02.23 Chimney-5 (2)
|
17.02.23 Chimney-5
|
17.02.23 BUF#6
|
17.02.23 BUF#6 (2)
|
17.02.23 Chimney #7
|
17.02.23 Chimney #4
|
11.02.23 Block placing started in chimney#6
|
15.02.23 RC Pump#7
|
15.02.2023 FGD Control Room
|
11.02.2023 FGD Control Room
|
15.02.23 Absorber Unit-1 Chipping of Shear key in
|
15.02.23 Absorber Unit-4 Abs Cleaning in progress
|
17.02.23 unit#5 absorber Column Erection
|
17.02.2023 Absorber #5 First Column Erection start
|
15.02.23 Unit#4 Chimney
|
15.02.23 Absorber #7 First column erection
|
10.02.2023 Site Visit of GM(I) Sir Near Chimney #5
|
10.02.2023 Site review by GM(I) Sir at BHEL office
|
10.02.2023 Sapling plantation by GM & PD Korba Si
|
10.02.2023 Sapling Plantation by GM(I) sir at BHE
|
10.02.2023- Sapling plantation by CM site
|
10.02.2023 Review by GM(I) Sir the work of MBPL-
|
10.02.2023 Group Photographs during GM(I) Visit
|
10.02.2023 GM(I) Sir Welcomed by GM & PD Korba sit
|
10.02.2023 GM(I) sir Welcomed by AGM& CM Korba sit
|
10.02.2023 GM(I) Sir Welcome Poster at BHEL office
|
10.02.2023 GM(I) Sir Visit on Unit#5 Duct pilling
|
10.02.2023 GM(I) Sir Site visit
|
10.02.2023 GM(I) Sir BHEL Office Visit
|
10.02.2023 GM(I) Meet with HOP NTPC Korba
|
10.02.2023 GM(I) Address to Site Employee
|
11.02.2023 Chimney Stage-I, status
|
11.02.2023 FGD Control Room Status
|
11.02.23 Block placing started in chimney#6
|
12.02.23 Chimney (Unit#05) update (RCC shell casti
|
08.02.23 Chimney unit-05
|
06.02.23 Chimney Unit-5, Curing in Progress
|
04.02.2023 Photographs during Shell casting start
|
04.02.2023 Photographs during shell casting start
|
04.02.2023 Group Photographs during Unit#5 Chimney
|
04.02.2023 Chimney-5 shell casting started
|
04.02.2023 Chimney-5 Shell casting started
|
04.02.2023 Chimney #5 Shell casting start puja
|
04.02.2023 Chimney #5 Shell casting start Puja (2)
|
04.02.23 Unit #05 chimney shell wall concreting 23
|
04.02.23 Group Photographs Unit#5 Chimney Shell ca
|
04.02.23 Chimney-5 shell casting started
|
04.02.23 Pooja conducted and Pre job briefing to
|
03.02.2023 Pooja performed by GM-FGD NTPC Abs#7
|
03.02.2023 Pooja Performed By CM site Absorber #7
|
03.02.2023 Group Photographs Absorber #7 Erection
|
03.02.2023 Absorber #7 Erection work Pooja Perform
|
03.02.2023 Absorber #7 Erection Group Photographs
|
03.02.2023 Absorber #7 Erection Pooja performed b
|
28.01.23 TT AREA OUTSIDE COREBELL
|
28.01.2023 TT AREA CORE BELL
|
28.01.2023 TT AREA
|
28.01.2023 TT AREA
|
28.01.23 Crusher House Excavation started
|
28.01.23 Ball Mill Area Excavation completed
|
28.01.23 Gypsum Shed area Compection under Progres
|
28.01.23 Gypsum Dewatering Area Excavation started
|
30.01.2023 Stage-I Chimney Shell Casting
|
29.01.2023 Stage-I Chimney Shell Casting
|
29.01.2023 Stage-I Chimney Shell Casting (2)
|
27.01.23 Stage-I Chimney Shell Casting
|
27.01.23 Chimney stage-01 Date 27.01.2023 shell Co
|
27.01.2023 Group Photographs during Puja for Shell
|
27.01.2023 Stage-I Chimney Shell casting arrangeme
|
27.01.23 Stage-I Chimney Shell casting arrangement
|
27.01.23 Stage-I Chimney Shell casting arrangement
|
27.01.23 Pooja Performed by GM& PD BHEL KORBA FGD
|
27.01.23 Pooja Performed by GM& PD BHEL KORBA FGD
|
27.01.23 Pooja Performed by Executive Director NT
|
27.01.23 Pooja Performed by Executive Director NT
|
Korba Site-Group Photographs
|
Korba Site-Group Photographs..
|
Korba Site-Flag Hoisting by GM&PD Sir
|
Korba Site- Speech By GM& PD sir
|
Korba Site- Message to Site employees by GM& PD si
|
Korba Site- Marching for Flag Hoisting
|
Korba Site- Flag Hoisting by GM& PD sir..
|
REVIEW OF SITE PROGRESS AT FGD AREA STG-I CHIMNEY
|
REVIEW OF SITE PROGRESS AT FGD AREA STG-I CHIMNEY
|
REVIEW OF SITE PROGRESS AT FGD AREA STG-I CHIMNEY
|
GROUP PHOTOGRAPH
|
NTPC DIRECTOR( OPN) & NTPC RED WR-II Welcome poste
|
NTPC RED WR-II Welcomed by CM Korba site
|
Interaction of NTPC Director Opn with Construction
|
NTPC DIRECTOR OPN Welcomed by CM Korba site
|
Interaction of NTPC Director Opn with Project Dire
|
NTPC DIRECTOR Welcomed by Project Director Korba
|
16.01.2023 ACW -ECW PUMP HOUSE
|
16.01.23 UNIT#7 BLOCK-3 DUCT FOUNDATION EXCAVATION
|
16.01.23 STAGE-I BLOCK-3 DUCT FOUNDATION STATUS
|
16.01.23 STAGE-1 BLOCK-3 PILE FOUNDATION
|
16.01.23 STAGE#1 BLOCK-4 DUCT FOUNDATION
|
16.01.23 RC PUMP & OB SHED UNIT#4 STATUS
|
16.01.23 RC PUMP & OB SHED U#7
|
16.01.23 RC Pump #7 location
|
16.01.23 RC Pump #4 Location
|
16.01.23 PROCESS WATER TANK B STATUS
|
16.01.23 LIMESTONE SLURRY TANK B STATUS
|
16.01.23 LIMESTONE SLURRY TANK # A
|
16.01.23 FGD CONTROL ROOM STATUS
|
16.01.23 FGD CONTROL ROOM STATUS FOOTINGS
|
16.01.23 FGD CONTROL ROOM STATUS (2)
|
16.01.23 BUF#6A BOOSTER FAN
|
16.01.23 Absorber#6 & RC Pump #6 Location status
|
16.01.23 ABSORBER STAGE-1
|
16.01.23 ABSORBER STAGE-1 STATUS
|
16.01.23 ABSORBER STAGE-1 RENFORCEMENT LAYING
|
16.01.23 33KV Switchgear Location
|
24.12.22 ACW PUMP HOUSE BACKFILLING
|
24.12.22 ABSORBER#1,2,3 STATUS
|
24.12.22 TRUCK TIPPLER AREA OVERVIEW
|
14.12.22 TRUCK TIPPLER AREA INSIDE BACKFILLING
|
14.12.22 TRUCK TIPPLER AREA INSIDE BACK FILLLING
|
14.12.22 TRUCK TIPPLER AREA BACK FILLING
|
14.12.22 TRUCK TIPPLER AREA INSIDE
|
14.12.22 Truck Tippler AREA
|
24.12.22 LBC 1AB STATUS
|
28.12.22 CHIMNEY#6 STATUSS
|
28.12.22 CHIMNEY #6 STATUS
|
24.12.22 CHIMNEY#6 Status
|
28.12.22 CHIMNEY#4 STATUS
|
28.12.2022 CHIMNEY #4 STATUS
|
24.12.22 CHIMNEY#4 STATUS
|
24.12.22 CHIMNEY#4 STATUS
|
30.12.22 ABSORBER#7 STATUS
|
28.12.22 ABSORBER#7 SATSUS
|
24.12.22 ABSORBER#7 STATUS
|
30.12.22 RC PUMP #7 STATUS
|
31.12.22 CHIMNEY#7 STATUS
|
28.12.22 CH#7 STATUS
|
24.12.22 CH#7 STATUS
|
02.01.23 FGD CR STATUS
|
30.12.22 FGD CR STATUS
|
28.12.22 FGD CR STATUS
|
24.12.22 FGD CR STATUS
|
02.01.23 LIMESTONE SLURRY TANK B
|
02.01.23 LIMESTONE SLURRY TANK A
|
28.12.22 LIMESTONE SLURRY TANK A
|
28.12.22 LIMESTONE SLURRY TANK B
|
13.12.2022 Booster Fan Unit 7B pilecap casting com
|
14.12.22 BUF#6
|
24.12.22 Absorber # 5 status
|
24.12.2022,0650 Chimney unit-07 segment-06 Concret
|
20.12.2022,0715 Chimney unit-07 segment-02 Concret
|
14.12.2022 Chimney unit-07 Pile cap segment 03 cas
|
13.12.2022 Chimney unit-07 Pile cap segment 03 cas
|
13.12.2022 Booster Fan Unit 7B pilecap casting com
|
09.12.2022 Unit #06 chimney Raft Excavation purpos
|
09.12.2022 Unit #06 Excavation work has been start
|
06.12.22 Unit #07 balance five segments bottom bot
|
02.12.2022 Unit #07 chimney Raft 1st segment concr
|
02.12.2022 Unit #07 chimney Raft 1st segment concr
|
01.12.22 Unit #07 chimney Raft 1st segment concret
|
01.12.2022 Unit#7 First Raft Casting Pooja
|
29.11.2022 Unit#6 absorber 665-745 cum completed
|
29.11.2022 Unit#6 absorber 641-745 cum completed
|
29.11.2022 Unit#6 absorber 493 745 cum completed
|
28.11.2022 Absorber Unit#6 120- 745 cum casting co
|
28.11.2022 Absorber Unit 6 PC1 Pilecap casting sta
|
28.11.2022 Absorber unit-6 raft concrete pouring s
|
25.11.22 Chimney #4 Status
|
25.11.22 Unit #07 1st segments top jali & shell wa
|
24.11.2022 U#7 Chimney status
|
22.11.2022 Unit#7 Chimney load test (2)
|
18.11.22 Loading completed in chimney 7.datum fixi
|
12.11.22 Block placing started in unit7 chimney Lo
|
11.11.2022 Unit#7 Chimney Reinforment laying start
|
26.11.2022 ch#5
|
26.11.2022 ALL SIX SEGMENT CASTING COMPLETED
|
26.11.22 Unit #05 final two segments out of 0606 s
|
25.11.22 12 00Hrs Unit #05 chimney Raft final two
|
25.11.22 Unit #5 Chimney Raft segments #01 & 04 fi
|
25.11.22 Chimney unit-05 pile cap segment 01& 03 c
|
24.11.2022 Chimney #5
|
24.11.2022 Unit#5 Chimney
|
17.11.2022 Pile Chipping work started
|
10.11.22 Control room pcc in process
|
12.11.22 Block placing started in unit7 chimney
|
11.11.2022 Unit#7 Chimney Reinforment laying start
|
11.11.2022 Unit#7 Chimney Reinforment laying start
|
15.11.2022 Chimney stage-01 Segment-06 Concrete C
|
15.11.2022 Chimney stage-01 Segment-06 Concrete C
|
14.11.2022 Chimney stage-01 Segment-06 Concrete st
|
21.10.22 UNIT 5 BLOCK 3 PILING START NO. 24
|
22.10.2022 Absorber unit4 casting successfully com
|
21.10.2022 Absorber Unit 4 pilecap casting started
|
20.10.2022 Unit#6 chimney Pile Ni P20 drilling UP
|
04.11.2022 Unit#7 Booster Fan Area Pile chippling
|
04.11.2022 BALL MILL AREA
|
04.11.2022 TT AREA
|
04.11.2022 TT Area Retaining wall
|
04.11.2022 TT AREA RETAINING WALL
|
20.10.2022 Truck tippler reataining wall concrete
|
18.10.22 TT Area
|
18.10.2022 Truck Tippler Retaining Wall casting co
|
18.10.22 Chimney satge-01, Segment-2 casting stare
|
11.11.2022 Unit#7 Chimney Reinforment laying start
|
21.10.22 Chimney Unit 7 Pile chipping completed,
|
21.10.22 Chimney stage-01 Pile cap as on
|
19.10.22 Stage-1 Segment-2( Third Segment)
|
19.10.22 Segment-2( Third Sement)
|
11.10.22 Segment-5(Second Segment)
|
12.10.22 Concreting completed 664cum segment-05(Se
|
Date 11.10.2022 Chimney Segment-5(Second Segment)
|
Stage-I Chimney Safety First -Pep Talk before star
|
Stage-I Chimney Raft Cating Pooja by NTPC BHEL Off
|
Stage-I Chimney Raft Casting start Pooja by NTPC-B
|
Stage-I Chimney Gethering at Raft Casting Location
|
Stage-I Chimney Gathering at Location
|
Stage-I Chimeny Raft Casting started by Boom Place
|
Unit#4 Chimney Raft Casting Pep Talk
|
Unit#4 Chimney Raft Casting Group Photo
|
Unit#4Chimney Raft Casting Pooja by CM site
|
Unit#4 Chimney Raft Casting Pooja by PD BHEL Korba
|
Unit#4 Chimney Raft casting Pooja by NTPC GM FGD
|
UNit#4 Chimney Raft Casting Pooja by HOP NTPC
|
Unit#4 Chimney Raft Casting
|
Unit#5 Chimney
|
Truck Tippler
|
Unit#5 Booster Fan
|
Unit#5 Absorber
|
Unit#4 Chimney
|
Unit#5 Chimney
|
Stage-I Chimney
|
LTP-1 Area
|
Process Water Tank-B
|
Process Water Tank -A
|
Gypsum Shed Area
|
FGD Control Room area
|
Unit#5 Booster Fan
|
ACW/ECW AREA
|
Unit#7 Absorber
|
WASTE WATER & FILTRATE WATER TANK
|
TRUCK TIPPLER AREA
|
TRUCK TIPPLER
|
PROCESS WATER TANK-B
|
PROCESS WATER TANK-A
|
LTP-1( LIME STONE TERMINAL POINT-01)
|
GYPSUM STORAGE SHED
|
ACW/ ECW PUMP HOUSE
|
Booster Fan Unit#5
|
Absorber Unit#5
|
12.08.22 U#7 Absorber Reinforcement laying Status
|
Unit#5 Booster Fan Reinforcement work status
|
Unit#5 Chimney Raft Status
|
Unit#5 Chimney Raft status on 13.07.2022
|
Unit#5 Chimney Raft Casting 3 segment out of 6done
|
Unit#5 Absorber Raft Casting
|
Absorber Unit#5 Raft casting Started on 02.07.2022
|
Test Pile TPV-5 Compression Load test Start
|
Test Pile TPV-5 Compression Load test
|
Unit#5 Absorber
|
Unit#4 Chimney
|
Unit#1I2I3 Chimney
|
Test Pile TPV-5 Loading work start
|
TPV-5 TEST PILES WORKS
|
Welcome of GM(I) at Korba FGD site
|
UNIT#5 CHIMNEY WORK STATUS
|
Meeting of GM(I) With HOP Korba
|
GROUP PHOTOGRAPH ON 18.05.2022 WITH GM(I)
|
ACW/ ECW WORK STATUS , WORK PENDING DUE TO BOLTS
|
ABSORBER UNIT#5 PCC
|
Test Pilling Work status Review by NTPC officials
|
M/s NAVRUP INDIA Pilling work start
|
Gypsum Shed rea Footing Progress
|
Gypsum Shed area Footing Work Status
|
Gypsum Shed area Work Progress Photographs
|
ACW/ECW Area Work Progress Photographs
|
Gypsum Shed Area Work Progress Photograps
|
TT area Photograph Pic-2
|
TT area Photographs
|
Excavation in Gypsum Storage Shed
|
Excavation in Gypsum Storage Shed
|
Excavation in Gypsum Storage Shed
|
Weigh bridge installation in progress
|
U#2 RHS FGD Bypass Damper placed in position
|
U#2 RHS FGD Bypass Damper erection under progress
|
U#2 RHS existing duct removal for damper erection
|
Chimney Unit-5 Job pilling
|
MBPL Batching plant
|
1st Batching plant BJCL for job pile package
|
BJCL Batching plant -1 area
|
U#2 Existing duct RHS cutting in progress
|
Truck tippler raft is under progress
|
Truck tippler raft is under progress
|
Chimney-5 piling work in progress
|
Chimney-5 piling work in progress
|
Damper Erection done in Unit#2 LHS side
|