Home   

KHURJA TG PKG


ST-1

CWPH

RWPH

ST-1

Reactor transformer

GT-2,UT-2, ST-2 foundations

Lube oil room columns

Lube oil room

Pipe -rack

ST-1

site photos

Service building

PHB

PHB

Misc tanks

AC duct in CCR

Unit-2

TG-1

TG-1 17 Mtr

CPU bulding

Generator Rotor-1

SERVICE BUILDING FOUNDATION CASTING

TG u#1 STATUS

CST TANK 1&2 REINFORCEMENT AND EXCAVATION

TG dECK COLUMN U#2 REINFORCEMENT

CPU EXCAVATION

CCR STRUCTURE

RWPH REINFORCEMENT WORK

STRUCTURE ERECTION STATUS AB BAY U#1

CWPH EXCAVATION

CCR STRUCTURE ERECTION

TG#2 STRUCTURE WORK

UT#2B TRANSFORMER YARD CIVIL WORK

CST TANK 1 & 2 REINFORCEMENT AND EXCAVATION WORK

SERVICE BUILDING CIVIL WORK

TRANSFORMER YARD U#2 CIVIL WORK UNDER PROGRESS

TRANSFORMER YARD U#1 CIVIL WORK UNDER PROGRESS

TG DECK COLUMN U#2 REINFORCEMENT

PHB #1 STRUCTURE ERECTION BETWEEN ROW A TO B

PHB #2 B ROW STRUCTURE ERECTION

SERVICE BUILDIGNG CIVIL WORK

CCR STRUCTURE ERECTION

CCR Structure erection under progress

PHB U#1 Structure erection work under progress

Structure erection work PHB#1

TG#2 Reinforcement work

service building footing and pedestal work

CST Tank U#2 reinforcement work

GT foundation Unit-2

PHB 31 AB BAY GROD 11 TO 14 STRUCTURE ERECTION

ST2 FOOTING RCC

CST TANK 2 REINFORCEMENT WORK

PHB #2 STRUCTUREE RECTION & TGCOLUMN REINFORCEMENT

PHB #1 STRUCTURE ERECTION AB BAY

CCR STRUCTURE ERECTION

SERVICE BUILDING FOOTING RCC

TG DECK COLUMN U#2 REINFORCEMENT WORK

CCR STRUCTURE ERECTION ROW F GRID 15,

STRUCTURE ERECTION AB BAY GRID11

UT-2B REINFORCEMENT WORK UNDER PROGRESS

CST-2 PCC

ccr structure work status

UT 2A raft reinforcement work

structure erection AB bay grid 5

tg deck u#2 columns reinforcement work.

service building excavation work

reinforcemnet work in TG deck column U#2

Structure erection in Ab bay Unit-1

structure erection in AB bay Unit-1

Structure erection in CCR

reinforcement work in TG Deck U#2 column

roof girder TG u#1 erection

tg deck u#1 curing

ccr structure erection

BC bay TG-1 structure erection

TG deck U#1 concreting started

TG Deck u#1 shuttering work

Sand Backfilling in AB bay between Grid 20-24

TDBFP 2A Column RCC work

TG Deck U#1 Shuttering and reinforcement placement

TG#1 deck work hampered due to heavy rainfall

TG#2 work hampered due to rainfall

Plinth Beam concreting TG#2

TG DECK U#1 Reinforcement placement

TG Deck U#1 Reinforcement laying work under progress

TG#2 MDBFP Casting completed

TG Deck Unit-1 reinforcement work under progress

TG Deck Unit-2 reinforcement work under progress

Unit-2 MDBFP foundation shuttering work under progress

TG deck u#1 reinforcement work

erection of structure in CCR

TG Deck U #1 Reinforcement and stagging work

TG#2 MDBFP shuttering work

TG#1 GT Transformer Rail Wall shuttering

TG deck1 Reinforcement work under progress

TG#2 pedestal shuttering work under progress

TG Deck U #1 Reinforcement work under progress

TG#2 MDBFP Reinforcement work under progress

pcc work at U#2 TDBFP A

MDBFP U#2 reinforcemnt placement

TG#2 Pedestal PCAd19 and Deck column reinforcement

Unit-1 UT tray excavation work

TG#1 deck reinforcement work

TG#2 Deck Column reinforcement work in progress.

TG#2 Reinforcement placing for MDBFP raft

U#2 TG Deck column Shuttering and reinforce

TG Deck U #1 Reinforcement and staging work

GT 1A Wall Reinforcement work

Pedestal Shuttering work

TG#2 Column A7 & A8 Shuttering work

TG-1 deck bottom shuttering work under progress

TG-1 deck reinforcement work under progress

Reinforcement and shuttering work in TG-2 column

GT 1A U-1 Raft casting completed

Reinforcement and shuttering work in Tg-1 UT found

TG-1 Deck shuttering and reinforcement work

TG-2 PCAA18 pedestal reinforcement work

TG-2 PAa19 First lift pedestal casting completed

TG#1 B Row structure erection under progress

TG#2 Pedestal Casting of PCAc18 Shuttering Work

TG U-1 ,Staging and shuttering work

Bolt tightening BC bay TG-1

PCB20/21 pedestal casting reinforcement work

Excavation work in RWPH is under progress

GT-1B raft casting completed

CCR structure erection start

CCR structure erection start

TG Deck U-1 Reinforcement work under progress

TG-1 Transformer Yard GT-B Foundation Reinforcement

Column Reinforcement work at TG-2 Deck columns

MDBFP Unit-2 PCC work completed

UT 1A raft reinforcement work

TG#1 staging work for TG deck casting

Unit-2 Transformer Excavation work

Unit-2 Pedestal Reinforcement work

Unit-2 Pedestal Work

Unit-2 TG Column work

Unit-2 Pile cap civil work

CCR Civil foundation work completed

AB & BC Bay TG-1 Deck

BC- Bay structure work

AB Bay Structure work

ST-1 Foundation RCC work

TG-1 Structure and column work

Transformer Yard Pile cap work

TG-1 Deck stagging

TG-1 Deck reinforcement bending and curing work

Unit-1 site photograph