ST-1
|
CWPH
|
RWPH
|
ST-1
|
Reactor transformer
|
GT-2,UT-2, ST-2 foundations
|
Lube oil room columns
|
Lube oil room
|
Pipe -rack
|
ST-1
|
site photos
|
Service building
|
PHB
|
PHB
|
Misc tanks
|
AC duct in CCR
|
Unit-2
|
TG-1
|
TG-1 17 Mtr
|
CPU bulding
|
Generator Rotor-1
|
SERVICE BUILDING FOUNDATION CASTING
|
TG u#1 STATUS
|
CST TANK 1&2 REINFORCEMENT AND EXCAVATION
|
TG dECK COLUMN U#2 REINFORCEMENT
|
CPU EXCAVATION
|
CCR STRUCTURE
|
RWPH REINFORCEMENT WORK
|
STRUCTURE ERECTION STATUS AB BAY U#1
|
CWPH EXCAVATION
|
CCR STRUCTURE ERECTION
|
TG#2 STRUCTURE WORK
|
UT#2B TRANSFORMER YARD CIVIL WORK
|
CST TANK 1 & 2 REINFORCEMENT AND EXCAVATION WORK
|
SERVICE BUILDING CIVIL WORK
|
TRANSFORMER YARD U#2 CIVIL WORK UNDER PROGRESS
|
TRANSFORMER YARD U#1 CIVIL WORK UNDER PROGRESS
|
TG DECK COLUMN U#2 REINFORCEMENT
|
PHB #1 STRUCTURE ERECTION BETWEEN ROW A TO B
|
PHB #2 B ROW STRUCTURE ERECTION
|
SERVICE BUILDIGNG CIVIL WORK
|
CCR STRUCTURE ERECTION
|
CCR Structure erection under progress
|
PHB U#1 Structure erection work under progress
|
Structure erection work PHB#1
|
TG#2 Reinforcement work
|
service building footing and pedestal work
|
CST Tank U#2 reinforcement work
|
GT foundation Unit-2
|
PHB 31 AB BAY GROD 11 TO 14 STRUCTURE ERECTION
|
ST2 FOOTING RCC
|
CST TANK 2 REINFORCEMENT WORK
|
PHB #2 STRUCTUREE RECTION & TGCOLUMN REINFORCEMENT
|
PHB #1 STRUCTURE ERECTION AB BAY
|
CCR STRUCTURE ERECTION
|
SERVICE BUILDING FOOTING RCC
|
TG DECK COLUMN U#2 REINFORCEMENT WORK
|
CCR STRUCTURE ERECTION ROW F GRID 15,
|
STRUCTURE ERECTION AB BAY GRID11
|
UT-2B REINFORCEMENT WORK UNDER PROGRESS
|
CST-2 PCC
|
ccr structure work status
|
UT 2A raft reinforcement work
|
structure erection AB bay grid 5
|
tg deck u#2 columns reinforcement work.
|
service building excavation work
|
reinforcemnet work in TG deck column U#2
|
Structure erection in Ab bay Unit-1
|
structure erection in AB bay Unit-1
|
Structure erection in CCR
|
reinforcement work in TG Deck U#2 column
|
roof girder TG u#1 erection
|
tg deck u#1 curing
|
ccr structure erection
|
BC bay TG-1 structure erection
|
TG deck U#1 concreting started
|
TG Deck u#1 shuttering work
|
Sand Backfilling in AB bay between Grid 20-24
|
TDBFP 2A Column RCC work
|
TG Deck U#1 Shuttering and reinforcement placement
|
TG#1 deck work hampered due to heavy rainfall
|
TG#2 work hampered due to rainfall
|
Plinth Beam concreting TG#2
|
TG DECK U#1 Reinforcement placement
|
TG Deck U#1 Reinforcement laying work under progress
|
TG#2 MDBFP Casting completed
|
TG Deck Unit-1 reinforcement work under progress
|
TG Deck Unit-2 reinforcement work under progress
|
Unit-2 MDBFP foundation shuttering work under progress
|
TG deck u#1 reinforcement work
|
erection of structure in CCR
|
TG Deck U #1 Reinforcement and stagging work
|
TG#2 MDBFP shuttering work
|
TG#1 GT Transformer Rail Wall shuttering
|
TG deck1 Reinforcement work under progress
|
TG#2 pedestal shuttering work under progress
|
TG Deck U #1 Reinforcement work under progress
|
TG#2 MDBFP Reinforcement work under progress
|
pcc work at U#2 TDBFP A
|
MDBFP U#2 reinforcemnt placement
|
TG#2 Pedestal PCAd19 and Deck column reinforcement
|
Unit-1 UT tray excavation work
|
TG#1 deck reinforcement work
|
TG#2 Deck Column reinforcement work in progress.
|
TG#2 Reinforcement placing for MDBFP raft
|
U#2 TG Deck column Shuttering and reinforce
|
TG Deck U #1 Reinforcement and staging work
|
GT 1A Wall Reinforcement work
|
Pedestal Shuttering work
|
TG#2 Column A7 & A8 Shuttering work
|
TG-1 deck bottom shuttering work under progress
|
TG-1 deck reinforcement work under progress
|
Reinforcement and shuttering work in TG-2 column
|
GT 1A U-1 Raft casting completed
|
Reinforcement and shuttering work in Tg-1 UT found
|
TG-1 Deck shuttering and reinforcement work
|
TG-2 PCAA18 pedestal reinforcement work
|
TG-2 PAa19 First lift pedestal casting completed
|
TG#1 B Row structure erection under progress
|
TG#2 Pedestal Casting of PCAc18 Shuttering Work
|
TG U-1 ,Staging and shuttering work
|
Bolt tightening BC bay TG-1
|
PCB20/21 pedestal casting reinforcement work
|
Excavation work in RWPH is under progress
|
GT-1B raft casting completed
|
CCR structure erection start
|
CCR structure erection start
|
TG Deck U-1 Reinforcement work under progress
|
TG-1 Transformer Yard GT-B Foundation Reinforcement
|
Column Reinforcement work at TG-2 Deck columns
|
MDBFP Unit-2 PCC work completed
|
UT 1A raft reinforcement work
|
TG#1 staging work for TG deck casting
|
Unit-2 Transformer Excavation work
|
Unit-2 Pedestal Reinforcement work
|
Unit-2 Pedestal Work
|
Unit-2 TG Column work
|
Unit-2 Pile cap civil work
|
CCR Civil foundation work completed
|
AB & BC Bay TG-1 Deck
|
BC- Bay structure work
|
AB Bay Structure work
|
ST-1 Foundation RCC work
|
TG-1 Structure and column work
|
Transformer Yard Pile cap work
|
TG-1 Deck stagging
|
TG-1 Deck reinforcement bending and curing work
|
Unit-1 site photograph
|