Site photo U # 1 and U # 2
|
Site photo
|
Boiler U # 1 - readiness for Steam Blowing i/p.
|
Boiler U # 2
|
chimney - U # 2 5th segment ern i/p.
|
|
Eco duct erection in progress.
|
U # 1 Bottom Ash Hopper structures erection in progress
|
U#1 Mill D shuttering for deck casting in progress
|
U#1 PA Duct erection in progress
|
TP/TRs Erection in progress
|
U#1 Bottom ash hopper erection in progress
|
U#1 RHS Tripper floor sheeting in progress
|
Boiler U # 1 - Economizer ducts erection in progress
|
Boiler U # 1 - Mill D Casting completed
|
U # 1 Bottom Ash Hopper structures erection in progress
|
FSH 40 Coils Erection started after modification
|
CHP Galleries Erected
|
Boiler U # 1 Pressure parts
|
Auxiliary Boiler
|
Boiler U # 1
|
AUXILIARY BOILER STR ERECTION UNDER PROGRESS
|
CHIMNEY INTERNAL PLATFORM ERECTION UNDER PROGRESS
|
Unit-2 FD Fan B Deck civil work in progress.
|
CAC Foundation and Pedestals are made
|
Unit-2 ESP Control room Civil work in progress.
|
Unit-1 RHS Mills backfilling in progress.
|
Unit-1 Duct Pre-Assembly in progress
|
Unit-1 RHS Bunker Shell pre-assembly in progress
|
Chimney
|
Unit-2 erection of 3rd tier in progres
|
Unit-1 PA and FD Fans ready for erection
|
Unit-1 PA and FD Fans ready for erection
|
Unit-1 Rotary equipment Pr-assembly started.
|
Unit- 1Boiler- Erection of 4th tier in progress.
|
Unit-2 Boiler - Erection of 3rd tier columns in progress.
|
Unit-2 ID Fan A Deck reinforcement work in progress.
|
Unit-2 ESP area
|
Unit-1FD Fan support foundation civil work
|
Unit-1 Boiler 4th tier columns erection in progress
|
Unit-1 Fans handling structure and ESP erection in progress
|
Chimney height 64.4 Meter
|
Unit-2 Boiler- 3rd Tier erection in progress
|
Unit-2 PA & FD fans foundation civil work in progress.
|
Unit-2 ESP- Pass D inlet funnel erection is in progress
|
Unit-1 Fans handling structures erection in progress.
|
Aux Boiler footings and pedestals casting in progress
|
Unit-2 Boiler- 3rd tier erection in progress.
|
Unit-2 Boiler 3rd tier erection in progress
|
Unit-1 Boiler erection of 4th tier started
|
Chimney height 57.2 m
|
Unit-1 Boiler 4th Tier Erection in progress.
|
Unit-2 Boiler 2nd tier erection in progress
|
Unit-2 ESP
|
Unit-1 ESP
|
Chimney height achieved 44m
|
Chimney height Achieved 43 meter
|
Unit-1 Fans handling structures erection is in progress.
|
HCSD Silo Raft Casted
|
Unit-2 Boiler area
|
Unit-2 ESP area
|
Unit-2 FD and PA Fans area
|
PA Fan 1A - Deck reinforcement and shuttering under progress
|
Chimney shell casting under progress
|
Unit-1 Boiler 2nd Tier erection under progress
|
Unit-2 Boiler erection in progress
|
Unit-2 Boiler area
|
Ash Water Pump house area
|
Unit-1 ESP backfilling completed with earthmat
|
Unit-1 Boiler 2nd tier erection in progress
|
PA Fan-1A Reinforcement Work For Deck Cast
|
Unit-2 Boiler 2nd tier column erection
|
Unit-1 ID fan-A Deck Cast completed
|
Chimney
|
TP43B Foundation Civil Work
|
Chimney Shell Concreting Started
|
Chimney Shell Concreting
|
Ducts Support Foundations Civil Work & Backfilling
|
Unit-1 ESP
|
Unit-2 Boiler Columns erection
|
Unit #1 ID fan deck cast
|
U#1 PA fan civil work
|
U#1 ESP erection
|
U#1 ESP control room backfilling completed
|
Chimney
|
U#2 Boiler
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|