Home   

KRISHNAPATNAM SDSTPS STAGE-II (1X800MW)


Director(Thermal) APPDCL During the synchronisation

Unit Synchronization

Air receiver tank LHS placed on foundation

Status of HFO & LDO Tanks

Seal Air Fan foundation is in progress

Aerial view of Cooling tower

Aerial view of ESP

Pent House Sheeting in progress

Oil flushing is in progress for MDBFP

Status of CCR

Aerial view of Switch Yard

@ Feeder floor RHS

Staus of Mills foundations on LHS

Acid cleaning arrangements in progress

Aerial view of Boiler

Wall Blowers alignment in progress

Insulation erection is in progress

SCAPH RHS erection is in progress

Hot SA Duct LHS erection is in progress

Cold SA common duct erection is in progress

TDBFP Exhaust line is in progress

Line chamber erected below Generator

HP Turbine view

IVCV welding completed

Temp. piping detergent flushing

HP Heaters & BFD pipe line insulation completed

Dearator & FST

Dearator & FST

Critical piping in CD Bay

Piping works @ HFO Tank

ESP inlet duct insulation hooks welding in progres

Status of ducts in lhs

BCW Pump dummy fixing in progress

FD Fan motor trail run in presence of CE

Bottom Ash Hopper

Flue gas duct above APH LHS

HOT SA LHS

SA SCAPH RHS

ESP Outlet area flooring work in progress

Fin welding in progress

Fin welding in progress

Piping @ PHE

Boiler pressure parts ATT was completed successful

LP Rotor 2 was placed for final boxup

Flue gas duct

ID Fan (RHS) outlet duct progress

Wall Blowers alignment in progress

FD Fan RHS Discharge Duct

Bottom Ash Hoppers

Flue gas duct at Pass c made dummy for Light up

All panels placed in CCR room

Critical piping @ 17m floor

SG DMCW Pump A motor trail run commenced

LHS Bunker columns erection under progress

LP inner casing cleaning under progress

Condenser front view

CD Bay Pipe & Cable tray structure

FD & PA Fan (RHS) Insulation under progress

Boiler view from esp inlet

SA duct status

Bottom Ash Hoppers

Mills Lube oil skids placed on foundations

Station Transformer charged successfully

Boiler Front view

ACW pumps

ERM & CRM Motors trial run in progress

CD Bay

Bunker RHS

SA Duct status

BAH status

Critical Piping @ B row

ESP C & D pass Flue gas duct

Flash Tank Vent Pipe erection

CST

Control panels in CCR

UAT ready for charging

ST ready for charging

11kv & 3.3kv switchgear panels testing completed

DMCW Motors ready for trial run

Vaccum pumps A & B placed on position

Condenser 1 Titanium welding in progress

Condenser 1 FRE coating completed

CEP pumps ready for trial run

TDBFP A alignment in progress

MDBFP Oil piping in progress

Turbine & Generator lube oil piping

ESV - HPCV servo motors erection completed

Dearator & CD Bay status

Pent house structure

Scanner fans

LDO & Atomizing station in progress

APH (LHS) erection is in progress

FLUE GAS DUCT FROM APH TO ESP INLET (PASS C & D)

ESP FUNNELS INSULATION SHEETING IS IN PRORESS

LPT 1 PREPARATION OF TOP HALVES FOR ASSEMBLY

GENERATOR PW PIPING IS IN PROGRESS

Cooling Tower status

Condensor Tube cutting

ESP Top

Eco Flue gas duct

Cooling Water Pump House

ESV

TG Areial view

SPBD status

SPBD status

Lube oil line erection is in progress

CST

Cooling Water Pump House

Cooling Tower status

Panels in CCR

Aerial view of Turbine

esp inlet flue gas duct

ESP Pass D side casing insulation under progress

DMCW pumps erection in progress

Critical Piping erection in CD Bay

MDBFP C

status of aph hoppers (RHS)

Eco Flue gas duct

esp inlet flue gas duct

Status of APH (RHS) Outlet Flue gas duct

Pre assembly Flue gas duct is in progress

Aerial view of ESP

11kv panel charged

MDBFP C

Aux. Transformers

Blowdown Header

Station Transformer

Shifting C&I panels to CCR

Flue gas duct (rhs)

FOPH status

LHS Permanent lift sheeting

Areial view of Turbine

Areial view of Turbine

Condensor 2 tube insertion

Eco Flue gas duct

Mills (RHS)

PA fan discharge duct (rhs)

1st pass bottom ring header

SPBD bus duct

Control Room

APH on RHS

esp inlet flue gas duct

esp inlet flue gas duct

ESP side casing insulation

CD Bay structure erection in progress

ID Fan (RHS) erection status

Cooling Tower status

Start up system

FD Fan (RHS) Discharge duct is in progress

ATT is in progress in ESP Pass D

Dewatering at ESP rear side

Water logging due to rains

Water logging due to rains

Water logging due to rains

Stator dragging to actual location

Stacking of Transformer oil drums

Pre assembly of spiral waterwall panels (LHS)

Pressure Parts – Inside furnace

1st pass spiral wall (LHS) Fitup in progress

Backpass LTRH Lower Most Coils erection in progress

Status of Secondary Air Duct (LHS)

Status of Secondary Air Duct(RHS)

PA & FD Fans RHS Erection under progress

ESP Outlet Duct & Supporting Structure Erection

Air Tightness test in progress in ESP Pass C

Condenser Rear water chambers in position

2nd pedestal placed on foundation

Condensor B status

Condensor A status

Pre assembly of Portal crane Girder at TG floor

Portal Crane erection at ground level

Cooling Water Pump House

Status of APH(RHS)

View of Furnace cavity

ESP Outlet Duct erection in progress

Boiler 2nd pass roof erection in progress

Status of Condenser

Portal Crane erection at TG floor

Portal Crane erection at ground level

ESP Pass C & D view

Boiler 1st pass view

Boiler Furnace view

Boiler inside furnace

Boiler front view

Boiler 1st pass above roof

Boiler 2nd pass above roof

Boiler Front view

Boiler LHS view

Condenser(RHS)

Condenser(LHS)

CE Rapping mechanism in progress

Cooling Water Pump House

PA Fan (RHS)

Stator Unloading is in progress

Pressure Parts status

FUEL OIL TANKS STATUS

PA FAN (RHS)

Screen & Hanger tubes erection is in progress

Unloading of Generator Stator is in progress

Concrete floor made ready for unloading stator

Cooling Water Pipe Line

ESP Pass B & C Outlet Side Box up is in progres

Boiler area

Boiler Front View

All Inlet Funnels erection was completed

Pre-assembly of Furnace screen & hanger tubes

Power House Building

Spare GT unloaded on foundation

Status of Bunker & its structure on RHS

Final Funnel pre assembly is in progress

Status of Mills (RHS)

Status of Cooling water pipe line from TG end

EOT Crane in TG hall

Assembly of furnace rear screen & hanger tubes

Portal crane 1 consignment on the way to plant

Stator inside plant premises

BP Screen tubes pre assembly with inter panels

BP Screen tubes pre assembly with inter panels

Lower Hoppers erection is in progress in ESP pass C

Hoppers boxing up is in progress in ESP C Pass

PA & FD Fans (RHS) erection is in progress

Boiler Top view

ESP REAR SIDE DUCT STRUCTURE FOUNDATIONS IN PROGRE

ESP B PASS PENT HOUSE STRUCTURE ERECTION IN PROGRE

POWER HOUSE BULDING STATUS

FINISH SH FRONT ASSY (S-39) ERECTION IN PROGRESS

BP UPPER (RHS) PANELS WITH S11 HEADER ERECTION IS IN PROGRES

Erection of Eco Handling structure with 800MT cran

Chimney area

Mill Seperator erection is in progress

RH Coil Erection is in progress

ESP area

Boiler area

Mill A

ESP area - All outlet funnels erected

Boiler area