Director(Thermal) APPDCL During the synchronisation
|
Unit Synchronization
|
Air receiver tank LHS placed on foundation
|
Status of HFO & LDO Tanks
|
Seal Air Fan foundation is in progress
|
Aerial view of Cooling tower
|
Aerial view of ESP
|
Pent House Sheeting in progress
|
Oil flushing is in progress for MDBFP
|
Status of CCR
|
Aerial view of Switch Yard
|
@ Feeder floor RHS
|
Staus of Mills foundations on LHS
|
Acid cleaning arrangements in progress
|
Aerial view of Boiler
|
Wall Blowers alignment in progress
|
Insulation erection is in progress
|
SCAPH RHS erection is in progress
|
Hot SA Duct LHS erection is in progress
|
Cold SA common duct erection is in progress
|
TDBFP Exhaust line is in progress
|
Line chamber erected below Generator
|
HP Turbine view
|
IVCV welding completed
|
Temp. piping detergent flushing
|
HP Heaters & BFD pipe line insulation completed
|
Dearator & FST
|
Dearator & FST
|
Critical piping in CD Bay
|
Piping works @ HFO Tank
|
ESP inlet duct insulation hooks welding in progres
|
Status of ducts in lhs
|
BCW Pump dummy fixing in progress
|
FD Fan motor trail run in presence of CE
|
Bottom Ash Hopper
|
Flue gas duct above APH LHS
|
HOT SA LHS
|
SA SCAPH RHS
|
ESP Outlet area flooring work in progress
|
Fin welding in progress
|
Fin welding in progress
|
Piping @ PHE
|
Boiler pressure parts ATT was completed successful
|
LP Rotor 2 was placed for final boxup
|
Flue gas duct
|
ID Fan (RHS) outlet duct progress
|
Wall Blowers alignment in progress
|
FD Fan RHS Discharge Duct
|
Bottom Ash Hoppers
|
Flue gas duct at Pass c made dummy for Light up
|
All panels placed in CCR room
|
Critical piping @ 17m floor
|
SG DMCW Pump A motor trail run commenced
|
LHS Bunker columns erection under progress
|
LP inner casing cleaning under progress
|
Condenser front view
|
CD Bay Pipe & Cable tray structure
|
FD & PA Fan (RHS) Insulation under progress
|
Boiler view from esp inlet
|
SA duct status
|
Bottom Ash Hoppers
|
Mills Lube oil skids placed on foundations
|
Station Transformer charged successfully
|
Boiler Front view
|
ACW pumps
|
ERM & CRM Motors trial run in progress
|
CD Bay
|
Bunker RHS
|
SA Duct status
|
BAH status
|
Critical Piping @ B row
|
ESP C & D pass Flue gas duct
|
Flash Tank Vent Pipe erection
|
CST
|
Control panels in CCR
|
UAT ready for charging
|
ST ready for charging
|
11kv & 3.3kv switchgear panels testing completed
|
DMCW Motors ready for trial run
|
Vaccum pumps A & B placed on position
|
Condenser 1 Titanium welding in progress
|
Condenser 1 FRE coating completed
|
CEP pumps ready for trial run
|
TDBFP A alignment in progress
|
MDBFP Oil piping in progress
|
Turbine & Generator lube oil piping
|
ESV - HPCV servo motors erection completed
|
Dearator & CD Bay status
|
Pent house structure
|
Scanner fans
|
LDO & Atomizing station in progress
|
APH (LHS) erection is in progress
|
FLUE GAS DUCT FROM APH TO ESP INLET (PASS C & D)
|
ESP FUNNELS INSULATION SHEETING IS IN PRORESS
|
LPT 1 PREPARATION OF TOP HALVES FOR ASSEMBLY
|
GENERATOR PW PIPING IS IN PROGRESS
|
Cooling Tower status
|
Condensor Tube cutting
|
ESP Top
|
Eco Flue gas duct
|
Cooling Water Pump House
|
ESV
|
TG Areial view
|
SPBD status
|
SPBD status
|
Lube oil line erection is in progress
|
CST
|
Cooling Water Pump House
|
Cooling Tower status
|
Panels in CCR
|
Aerial view of Turbine
|
esp inlet flue gas duct
|
ESP Pass D side casing insulation under progress
|
DMCW pumps erection in progress
|
Critical Piping erection in CD Bay
|
MDBFP C
|
status of aph hoppers (RHS)
|
Eco Flue gas duct
|
esp inlet flue gas duct
|
Status of APH (RHS) Outlet Flue gas duct
|
Pre assembly Flue gas duct is in progress
|
Aerial view of ESP
|
11kv panel charged
|
MDBFP C
|
Aux. Transformers
|
Blowdown Header
|
Station Transformer
|
Shifting C&I panels to CCR
|
Flue gas duct (rhs)
|
FOPH status
|
LHS Permanent lift sheeting
|
Areial view of Turbine
|
Areial view of Turbine
|
Condensor 2 tube insertion
|
Eco Flue gas duct
|
Mills (RHS)
|
PA fan discharge duct (rhs)
|
1st pass bottom ring header
|
SPBD bus duct
|
Control Room
|
APH on RHS
|
esp inlet flue gas duct
|
esp inlet flue gas duct
|
ESP side casing insulation
|
CD Bay structure erection in progress
|
ID Fan (RHS) erection status
|
Cooling Tower status
|
Start up system
|
FD Fan (RHS) Discharge duct is in progress
|
ATT is in progress in ESP Pass D
|
Dewatering at ESP rear side
|
Water logging due to rains
|
Water logging due to rains
|
Water logging due to rains
|
Stator dragging to actual location
|
Stacking of Transformer oil drums
|
Pre assembly of spiral waterwall panels (LHS)
|
Pressure Parts – Inside furnace
|
1st pass spiral wall (LHS) Fitup in progress
|
Backpass LTRH Lower Most Coils erection in progress
|
Status of Secondary Air Duct (LHS)
|
Status of Secondary Air Duct(RHS)
|
PA & FD Fans RHS Erection under progress
|
ESP Outlet Duct & Supporting Structure Erection
|
Air Tightness test in progress in ESP Pass C
|
Condenser Rear water chambers in position
|
2nd pedestal placed on foundation
|
Condensor B status
|
Condensor A status
|
Pre assembly of Portal crane Girder at TG floor
|
Portal Crane erection at ground level
|
Cooling Water Pump House
|
Status of APH(RHS)
|
View of Furnace cavity
|
ESP Outlet Duct erection in progress
|
Boiler 2nd pass roof erection in progress
|
Status of Condenser
|
Portal Crane erection at TG floor
|
Portal Crane erection at ground level
|
ESP Pass C & D view
|
Boiler 1st pass view
|
Boiler Furnace view
|
Boiler inside furnace
|
Boiler front view
|
Boiler 1st pass above roof
|
Boiler 2nd pass above roof
|
Boiler Front view
|
Boiler LHS view
|
Condenser(RHS)
|
Condenser(LHS)
|
CE Rapping mechanism in progress
|
Cooling Water Pump House
|
PA Fan (RHS)
|
Stator Unloading is in progress
|
Pressure Parts status
|
FUEL OIL TANKS STATUS
|
PA FAN (RHS)
|
Screen & Hanger tubes erection is in progress
|
Unloading of Generator Stator is in progress
|
Concrete floor made ready for unloading stator
|
Cooling Water Pipe Line
|
ESP Pass B & C Outlet Side Box up is in progres
|
Boiler area
|
Boiler Front View
|
All Inlet Funnels erection was completed
|
Pre-assembly of Furnace screen & hanger tubes
|
Power House Building
|
Spare GT unloaded on foundation
|
Status of Bunker & its structure on RHS
|
Final Funnel pre assembly is in progress
|
Status of Mills (RHS)
|
Status of Cooling water pipe line from TG end
|
EOT Crane in TG hall
|
Assembly of furnace rear screen & hanger tubes
|
Portal crane 1 consignment on the way to plant
|
Stator inside plant premises
|
BP Screen tubes pre assembly with inter panels
|
BP Screen tubes pre assembly with inter panels
|
Lower Hoppers erection is in progress in ESP pass C
|
Hoppers boxing up is in progress in ESP C Pass
|
PA & FD Fans (RHS) erection is in progress
|
Boiler Top view
|
ESP REAR SIDE DUCT STRUCTURE FOUNDATIONS IN PROGRE
|
ESP B PASS PENT HOUSE STRUCTURE ERECTION IN PROGRE
|
POWER HOUSE BULDING STATUS
|
FINISH SH FRONT ASSY (S-39) ERECTION IN PROGRESS
|
BP UPPER (RHS) PANELS WITH S11 HEADER ERECTION IS IN PROGRES
|
Erection of Eco Handling structure with 800MT cran
|
Chimney area
|
Mill Seperator erection is in progress
|
RH Coil Erection is in progress
|
ESP area
|
Boiler area
|
Mill A
|
ESP area - All outlet funnels erected
|
Boiler area
|
|
|
|
|
|
|
|
|
|
|