RHS feeder floor
|
Boiler RHS area
|
ID fans area
|
ESP area
|
Boiler RHS area
|
Boiler RHS area
|
ESP area
|
ESP area
|
LHS feeder floor
|
LHS mills and feeders
|
PA duct area
|
Boiler RHS area
|
Fans area
|
Boiler RHS area
|
ESP area
|
Boiler RHS area
|
Boiler RHS area
|
Boiler RHS area
|
Boiler RHS area
|
Boiler RHS area
|
Boiler RHS area
|
RHS Structure erection Mills area
|
Boiler RHS area
|
RHS Fans area
|
PA tempering duct insulation works
|
PA duct area erection
|
Boiler RHS area
|
hot PA duct erection
|
hot PA duct erection
|
ESP ALI installation works
|
Mill maintenance platform works
|
TDBFP-B Insulation
|
TDBFP-B Insulation
|
TDBFP-A Insulation
|
TDBFP-A Insulation
|
RHS beam erection
|
RHS beam erection
|
RHS beam erection
|
ESP I/L gate received at site
|
TDBFP-B bearing boxup
|
TDBFP-B TSI sensor mounting
|
TDBFP-B TSI sensor calibration
|
LHS feeder floor- feeder erection
|
PA duct area
|
PA duct area
|
Feeder floor LHS
|
Team BHEL Vijayawada
|
Team BHEL Vijayawada
|
Team BHEL Vijayawada
|
Team BHEL with ED/PSSR post Synchronization
|
First synchronization at 00:09hrs
|
Coconut breaking by ED/PSSR
|
ED/PSSR felicitating MD/APGENCO
|
Project Director felicitating ED/PSSR
|
Project Director felicitating ED/PSSR
|
Coconut breaking by CE/APGENCO
|
Coconut breaking by CE/APGENCO
|
Coconut breaking by GM/ TSX
|
Coconut breaking by Project Director/Vijayawada
|
Coconut breaking by Director/ Technical, APGENCO
|
TDBFP B
|
TDBFP A
|
MDBFP
|
TG Hall
|
Corner 2 erection works u/p @54 mts elevation.
|
Erection of Cladding at 55 mts for permanent lift under progres.
|
BOF to ESP duct support structure erection u/p in RHS of Boiler.
|
Turbine insulation works completed.
|
Delta run alignment of IPBD u/p.
|
DCS panels beIng powered on by officials.
|
DMCW for excitor & Hydrogen cooler works u/p.
|
LPBP erection works u/p.
|
Drive Turbine of TDBFP - B erected on foundation.
|
Generator Base plate grouting completed.
|
Erection of HV bushing GT- R phase u/p.
|
Erection of LV bushing GT- R phase u/p.
|
PA Fan lube oil lines chemical cleaning u/p.
|
LPBP valve insulation under progress.
|
ESP HVR Trnf oil BDV sample collection and testing u/p.
|
LP-2 Thermo couple routing completed.
|
CRH NRV insulation completed.
|
IV and IP turbine insualtion completed.
|
HP Turbine and ESV insulation completed.
|
Mill A PGB oil filling in progress.
|
Extraction of HP heater 2 completed.
|
Exiciter Placed in position.
|
Work stations powered @CCR.
|
IPBD erection u/p @ 8.5 Mts in TG floor.
|
Insulation works commenced for Deareator & FST.
|
Status of RHS Mills.
|
BFD Hydro test successfully completed internally.
|
BFD Hydro test touched 400 Kg per Sq.cm.
|
ID Fan A Motor trial run successfully completed.
|
Deaerator Hydro test successfully completed.
|
LP 2 thermo couples fixing completed.
|
240V UPS battory both banks commissioned.
|
GT- B phase A frame erection commenced.
|
FD Fan A alignment works u/p
|
TDBFP booster pump erection works u/p.
|
RHS Mills fdns status. Mill A PGB sole plate alignment works u/p
|
LP By Pass piping works under progress.
|
MOT room & Oil module erection status.
|
Status of MDBFP.
|
Piping works u/p in CD Bay.
|
BFD to ECO preparation for hydro test u/p.
|
16 MVA UAT -02 Charged.
|
Generator Rotor insertion successfully completed..
|
Generator Rotor insertion under progress.
|
Soot blower panels erection u/p in boiler MCC.
|
16 MVA UAT -01 Charged.
|
16 MVA UAT -01 Charged.
|
Steam Blowing of PRDS line done.
|
ID Fan A bumped and readings found ok.
|
ESP to Chimney and ID Fan B status
|
ESP Control Room to ESP cabling under progress
|
ESP Control room status
|
FOPH status
|
BOF to ESP erection status
|
Bottom Ash Hopper erection status (BOP Scope)
|
Boiler RHS Mills status
|
Boiler First pass insulation status
|
ESP penthouse roof status
|
Boiler Penhouse roof insulation status
|
C&I Status at Boiler Penthouse
|
LHS Bunkers erection status (BOP Scope)
|
Coal Pipe erection status
|
CD Bay cable rack erection status (BOP Scope)
|
CD Bay Cable racks erection status (BOP Scope)
|
Main Control Room status
|
TG Deck status
|
Primary Water Piping for Generator Stator
|
TDBFP-B Deck casting status (BOP Scope)
|
De Super Heaters erection status
|
Oil Canal Status
|
MOT Room status
|
MDBFP allignment under progress
|
IPBD Duct Status
|
Seal Oil Valve Rack grouting under progress
|
LP Heaters 1A/2A & 1B/2B erection status
|
HP Heaters 6B & 7B erection status
|
HP Heaters 6A & 7A erection status
|
DMCW pumps and PHEs erection status
|
Hot Well make up pumps piping status
|
10 to 11 grid piping erection status at 8.5 Mtrs
|
Flash Tank A and related piping status
|
Boiler CC pump erection status
|
CD Bay PCP erection status
|
CD Bay Piping erection status
|
Boiler LHS view
|
BOF to ESP LHS side status
|
ESP to Chimney LHS duct insulation status
|
ID Fan to Chimney Duct insulation status
|
SEL relay testing in 3.3 KV 8CA board u/p.
|
Floor tile works u/p in Main Control Room.
|
IPBD erection u/p.
|
MDBFP alignment works u/p.
|
JT 25 works under progress by BOP agency.
|
SGDMCW system ready for BLU.
|
View of Boiler (North side).
|
Turbine floor.
|
MDBFP erection works u/p.
|
Overall view of the Plant.
|
Piping works between CD Bay .
|
BOF to ESP duct ready for ATT.
|
View of Boiler (South side).
|
ESP to ID duct insulation works u/p.
|
FD and PA Motor rainhood erection u/p.
|
FD Fan cable laying works under progress.
|
Flash tank B lifting under progress
|
Flash tank structure erection u/p by BOP agency.
|
Both the condensers boxed up
|
MOT room structure erection u/p by BOP agency.
|
ESP D Pass erection with RIO panels completed. C Pass u/p.
|
GT 1C to Spare GT concreting yet to be done by Custoner.
|
Approach road for Station Transformer to be made by civil agency
|
Road to be made aval.for movement of materials inside the BLR
|
MTM along with tray work at at vertical wall @ pent hoise of BLR
|
SH/RH spray LIE shifting to Boiler @60 M el. Works u/p.
|
ID to Chiemney (LHS) Duct kerosene test u/p.
|
Bottom Ash hopper erection status by BOP agency
|
Fan Foundation status on RHS of the Boiler .
|
Mills B,C& D foundation status .
|
ESP Pass B Inlet Funnel insulation works u/p.
|
Insulation works u/p between ESP O/L to ID Fan I/L Duct.
|
Piping erection stopped due to slush in CD bayC
|
Hydra getting stuck up in Boiler area due to slush
|
Boiler materials feeding sopped due to slush road
|
Front water boxes of both condensers erected.
|
Control room status due to heavy rain.
|
Last portal crane girder loaded on trailer to send the same to E
|
Condenser 1 final box up under progress.
|
Preparation for rear water box of condenser 1 under progress.
|
GT 1A: clearance given to civil for 10 Aux. Peduatals casting.
|
Condensor1: platform removed after completing erection on front
|
3/12 trailer consists of portal crane parts diverted to Ennore.
|
ACP D Pass CT testing completed. PT testing u/p.
|
Storage Yard 2 filled up with ash water. Dewatering u/p.
|
Bottom Ash hopper works under progress by BOP agency.
|
Coal Piping Erection works under progress in Corners 1,2,3 &4.
|
Boiler lift sheeting works under progress on RHS .
|
Duct connection b/w chimney and ID duct on RHS u/p by BGR.
|
Balance pent house sheeting works under progress in ESP Pass D.
|
ESP cable laying works started.
|
IA & PA Air compressors erection under progress by BOP Agency.
|
Mills E,F,G&H hoists erected.
|
ALT- A Testing under progress.
|
TG&SGDMCW pumps erection completed.Piping works under progress.
|
Steam cooled spacer works under progress in boiler.
|
Cable tray and cabling required for running of SG-DMCW.
|
First EC panel erected in ESP control room .
|
MDBFP fdns h/o on 15.07.19 and erection works started today.
|
Civil works u/p for Mills B,C,D
|
Portal crane dismantling works under progress
|
Oil purification unit fdns u/p for TDBFP
|
TDBFP A Lub oil fdns under progress
|
Condensor 2 water box fixed
|
Hopper tray work held up for want of floor in ESP Pass A
|
Flask Tank B not lifted due non avl. of strructure
|
Operator Desk & LVS room not yet ready
|
Feeder Panels erection u/p in Unit Control Room
|
Insulation of PRDS Line u/p.
|
Portal Crane Dismantling works u/p.
|
Drip pump fdns yet to be h/o by APGENCO
|
Mill A Casted & Checking U/p.B,C&D civil works u/p
|
BOF to ESP -C&D pass duct clearance not available
|
FD-B and PA-B fan foundation status
|
Coal Pipe erection in progress
|
Bottom ash hopper erection by BOP agency in progress.
|
Spare GT to be shifted .Need Rails by civil agency
|
Rail fixing U/p.Reqd for GT(spare) & UT shifting
|
GT-B Auxillary foundations not ready
|
Fire wall between GT-1A >-1B is not ready
|
GT-1A Auxillary fdns not ready for erection
|
RHS BOF to ESP duct foundn works not yet started
|
FD Fan -B foundation not ready for erection
|
PA Fan-B foundation not ready for erection
|
8.5mtr floor structure & grating reqd for IPBD
|
Beam not erected for support of IPBD by BOP agency
|
MOT room civil & structure works not yet started
|
TDBFP-B foundation civil foundation under progress
|
TDBFP-A foundation civil works not yet started
|
MDBFP foundations not yet handed over for erection
|
Main control room false ceiling reqd
|
Boiler MCC room panels not erected by BOP agency.
|
Cable Tray between Switchgear to ID fan not done
|
Cable Tray between Switchgear to ID fan not done
|
Boiler front pass insulation status
|
ESP Insulation status
|
ESP Insulation status
|
Transformer Yards status
|
PR-08 status
|
MCC Status
|
SPBD and IPBD duct status
|
UAT status
|
TG Floor status
|
Condenser 1 boxed up
|
Deaerator status
|
17 Mtrs floor TG status
|
PRDS header ready for steam blowing
|
CEP discharge works status
|
DMCW pumps status
|
PHEs and piping status
|
Zero Mtrs piping status
|
CD Bay piping status
|
17 Mtrs floor heaters piping status
|
ESP Penthouse status
|
ID Fan A Status
|
ID Fan B Status
|
FOPH Status
|
ESP and ESP Control room status
|
LHS Mills Status
|
Coal Pipes and Burners erection status
|
RHS mills foundation status
|
Boiler Penhouse
|
Boiler Front view
|
Boiler LHS View
|
BOILER RHS VIEW
|
ESP to Chimney ducting status LHS view
|
BOF to ESP duct and ESP insulation LHS view
|
Boiler LHS view
|
CPU erection status
|
IPBD Ducts status
|
Station transformer and SPBD duct status
|
Generator stator erection status
|
HP module and IP module status
|
HP Heaters 6A, 6B, 8A & 8B piping status
|
LP Heater 1A & 1B status
|
HP Heaters 6A & 7A piping status
|
Bottom Ash Hopper foundations status
|
LHS Bunkers status
|
deareator Status
|
PR-04 and CW pipeline status
|
RHS mills foundation status
|
ESP Pent house status
|
Boiler insulation status
|
CD Bay structure status
|
Air Pre Heaters status
|
ESP Status
|
BOF to ESP duct status
|
ESP & ESP control room status
|
Generator Stator Erectedon 29.04.2019
|
CEP Canister Erection in progress
|
CEP Canister Erection in progress
|
IP Turbine Top casing placement
|
IP Rotor Placement
|
IP Rotor Lifting
|
Transformer Yard works in progress
|
IP Turbine Inner casing works in progress
|
Condenser Dome wall placement
|
Condenser Works
|
Condenser and Flash Tank in AB Bay
|
CD Bay status
|
ESP Status
|
LHS Mill Bunker Structure status
|
Burner Panel fit up and welding under progress
|
Control Room Status
|
First Pass progress
|
Bottom Ring Header assembly
|
Boiler RHS status
|
Boiler LHS Status
|
ID fan B Side works
|
ID Fan A Side Duct erection status
|
Right side Spiral panel erection under progress
|
ID to Chimney duct erection under progress
|
Stator unloading at site
|
Stator unloading in presence of Chief Engineer(Construction & TI)/APGENCO
|
FD Fan-A silencer erected
|
Stator reached site
|
ESP overview
|
Condenser erection under progress
|
Boiler
|
Stator reached near to site, 2km away from site
|
Turbine erection start 03 Oct 2018
|
ESP outlet to Chimney flange ducting under progress
|
ESP C pass ATT succesfully completed
|
Ducting
|
Ducts between APH & PA, FD under progress
|
Transformers foundations
|
Risers fit up under progress
|
SOFA ducts erection under progress
|
Left side upper spiral panel pre-assembly Under progress
|
Front side upper spiral wall panel erected
|
Right side upper spiral wall panel preassemby under progress
|
Water box and water chamber erection under progres
|
Condenser side walls fit up under progress
|
Encased CW pipe rear end positioned for erection
|
Condenser 1 & 2 bottom plates
|
ESP and Boiler overview
|
TG Deck
|
Transformer yard
|
Condenser bottom plate & hot well
|
ESP Outlet to ID ducting under progress
|
ESP
|
Mills LHS
|
FD & PA fan LHS
|
ID Fans erection under progress
|
Hot PA ducting erection progress
|
SH Furnace roof tubes Erection under progress
|
Pendant coil erection under progress
|
Economizer tubes erection under progress
|
Furnace front spiral panel erection under progress
|
Boiler
|
Boiler Vent Completed
|
ID fan duct fabrication in progress
|
Condenser Erection in progress
|
3.5 mtr BC bay flooring completed
|
EOT crane movement is available upto 5th Grid only
|
Condenser-1 & 2 sidewall casting completed
|
Transition panel work in progress
|
Mill Rolls unloading at site
|
ATT successfully completed in ESP pass D
|
Flash Tank Pipe Welding in progress
|
CW Pipe
|
Condenser Foundation under Progress
|
Condenser Foundation under Progress
|
Road condition from Switchyard to Boiler & ESP
|
Air Tightness Test Started for ESP
|
Status of roads at site due to rain
|
Condenser Foundation under progress
|
ESP- D Pass readiness is under progress
|
Duct support Structures & ID fan
|
ESP to ID ducting
|
ESP area
|
FD & PA Fan area
|
Mills area
|
APH area
|
Boiler
|
Panels pre-assembly under progress
|
Pressure parts erection Under Progress
|
Boiler overview
|
Mills LHS side
|
Boiler overview
|
APH LHS side
|
4 nos GTs unloaded at site
|
TG Deck (Customer scope)
|
EOT crane erection Under progress.(Customer scope)
|
Bunker & Power house structure(Customer scope)
|
Cooling tower (customer scope)
|
Chimney(Customer scope)
|
ESP outlet funnel gate erection under progress
|
ESP to ID fan Ducts erection under progress
|
ESP Overview
|
ID fan -A erection under progress
|
Mills E, F,G & H erection under progress
|
LTRH coils Pre assy Under progress
|
2nd Pass front panel pre assembly under progress
|
Duct and burner erection Under progress
|
Cold Primary & secondary air ducts erection Under progress.
|
LHS APH,FD fan & PA fan erection under progress
|
Reheater coils erection under progress
|
Pressure parts erection under progress
|
APH and Hot Sec air ducts erection under progress
|
Boiler view from ESP side
|
ESP overview from RHS inlet side
|
ESP overview from LHS outlet side
|
ESP to ID Fan duct erection under progress
|
PA Fan LHS erection under progress
|
Mills LHS erection under progress
|
ID Fan-A erection under progress
|
Boiler overview from back side
|
Boiler overview from RHS
|
Boiler overview from LHS
|
Boiler overview from front side
|
Boiler area
|
Site Overview
|
Boiler area
|
Inside Boiler area (Panels erection under progres)
|
Vijayawada site view
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|