Vac pumps unit 4
|
Unit 5 MVHV cable vault
|
Unit 4 LT cable vault 8.5m
|
Unit 4 debris filter
|
Unit 3 LT switchgear
|
U3&4.. Battery room... 17m slab and 8.5AR tiling b
|
U3&4 HT switchgear
|
Tf yard 4
|
Power house 1&2
|
Fire water tanks
|
Foam Pump house
|
Fire water PH
|
FGD Inlet & Outlet duct opening _ Material not avb
|
FGD #1 duct pedestals curing
|
FGD #1 duct foundations excavation
|
Esp CR 5
|
Esp cr 4 cable vault
|
Esp control room 5
|
DM plant
|
CST PH stage 2 and CST tank 5
|
Condenser tubes insertion unit 4
|
Compressor bldg stg 2
|
Clarified water PH
|
Chimneys and ESP 5
|
Chimney 1
|
Boiler 5 RHS and TP 35
|
Water system area
|
Overall BTG view
|
Plant from rear side
|
TP 11 & 31
|
Switchyard
|
Pipe rack 12
|
Power house 2
|
Fly ash silos
|
Fire water tanks
|
ESP control room 3
|
ESP 5
|
ESP 4
|
ESP 3
|
DM Plant tanks
|
CST tanks area
|
CPU regeneration bldg
|
CHP Stock pile
|
CHP Galleries
|
Chimney 1
|
CCR 2
|
Boiler 5
|
Boiler 5 LHS
|
Boiler 4
|
Boiler 4
|
Boiler 3
|
Boiler & Power house 3
|
Boiler 3
|
Boiler 5 RHS
|
NDCT 1(Right) & 2 (Left)
|
Pre Treatment plant channels
|
PT Chemical house
|
PT Clarifier 1
|
DM Plant Acid unloading tanks
|
Fuel oil tanks
|
NDCT 3
|
BOP Switchgear 2
|
ACW Pumps stage 1
|
TG rotor insertion
|
TG 1
|
Fuel oil pump house
|
FO Tanks
|
PT Plant
|
PT Clarifier
|
DM Clarifier
|
DM Clarifier 1
|
Overall
|
DM Plant
|
Chimney - Flue can with Borosilicate glass
|
Chimney 1 Borosilicate application
|
Vacuum pump house
|
Vph 1&2
|
Unit3 ESP TO ID FAN
|
Transformer yard 2
|
TG 2
|
Stage 2 transfer points
|
Stage 2 compressors
|
Stage 1 RHS
|
Service building stage 1(TSGENCo)
|
Primary water skid 2
|
PR2 PR3
|
PR1 PR7
|
Ndct 2
|
NDCT 2 Upper tie beam shuttering
|
Ndct 1
|
HPH 7a b
|
Hph 6a b
|
FOPH
|
Foam system
|
Fire water tanks
|
Fire water pump house
|
Esp cr3 (2)
|
Esp cr 3
|
Esp 3
|
Esp 2
|
Esp 1
|
DM Transfer PH
|
CWPH stage1
|
CST pUmp house stage 2
|
CST PH STAGE1
|
CPU Regen building
|
CPU 2
|
Condenser #2
|
CHP MCC 5
|
Chimney 2 Unit 3 Flue can ground assembly
|
Chimney 1 Flue can #2 primer application completed
|
Chimney 1 access winch
|
CER wall tiling
|
CCR OWS room with ducts
|
BOP Switchgear 1
|
Boiler 3 SCR Platforms
|
Boiler 2 RHS
|
Boiler 3
|
Boiler 2
|
Boiler 2 RHS
|
Boiler to ESP Duct #2
|
Boiler 2
|
Boiler 1
|
BCN 9AB
|
Aux boiler
|
Aux boiler MCC
|
AHP pipe rack
|
FGD Primary hydrocuclone feed storage tank B excav
|
FGD Duct Footing chiselling
|
FGD Duct #2 pedestals Civil works
|
Chimney 2 Flue can works #3
|
NDCT 5 racker columns
|
NDCT 3
|
Chimney 1 Flue can liner grinding works
|
Boiler 2 RHS
|
IPBD Alluminium welding test
|
UPS Battery charging
|
FOPH MCC
|
DM Plant Stream 1
|
Dm plant bulk acid storage tanks
|
DM Cascade aerator and clarifier 6 and 7
|
Clarifier 3,4,5
|
Clarifier 1 and 2, cascade aerator
|
Chimney 2 unit 3 flue can assy
|
RWPH pump floor
|
RWPH gates
|
RWPH battery room
|
PR 11 trestle erection
|
NDCT 5
|
NDCT 4
|
Clarified Water PH Pump floor
|
Clarified Water tank
|
Chimney 2 and 3
|
NDCT 5 Grillage columns
|
NDCT 5 Racker columns
|
SCR LHS Hopper Boiler 4
|
Chimney 2 unit 3 flue can assembly
|
Raw water pump house Stage 2 Pipe connections
|
5 units
|
TG 1
|
Ash slurry PH 1
|
CWPH NDCT Stage 1
|
SSF Stage 1
|
CWTP Stage 1
|
CPU Vessels Unit 1
|
Bottom ash hopper #2
|
Boiler 2
|
ESP 1 Rear ducting
|
ESP 1 front
|
ESP 2 rear ducting
|
ESP 2 front
|
Fuel oil tanks
|
Fire water tanks
|
DM vessels
|
DM tanks
|
DM plant Bulk acid storage tank
|
DM Plant
|
Boiler 1
|
Boiler 1
|
Switchyard
|
PT Clarifier
|
PT Plant Distribution pedestals
|
DM Aerator
|
PR 13
|
PR 2
|
PR 1
|
NDCT 1
|
MOT #2
|
LDO 2
|
LDO 1
|
ID duct unit 2
|
HFO 2
|
HFO 1
|
FOPH
|
ESP to ID Fan #1
|
ESP Control room 2
|
ESP 2
|
ESP 1
|
CW PH STage 1
|
CPU Vessels Unit 1
|
Chimney 1
|
CCR 1(Outside)
|
CCR 1 _Panel room
|
Boiler 1 RHS
|
Boiler 1 LHS
|
BCN 11ab
|
Ash slurry PH Stage 2
|
Station transformer 1
|
Boiler 1 RHS
|
NDCT 2
|
CHP conveyor galleries
|
Boiler 2
|
NDCT 3 & 4
|
Power block 3 LHS
|
PT Plant view
|
Boiler floor
|
Deaerator unit 2
|
AHP Silos
|
Boiler 2 insulation works
|
Coal piping unit 2
|
BOP Switchgear 1
|
Primary Water skid unit 2
|
Switchyard
|
TG 2
|
Transformer yard 2
|
CPU service vessels 2
|
HT switchgear 2
|
Bottom ash hopper 2
|
TP37
|
TP36
|
TP35
|
TP34
|
TP33
|
TP32
|
TP31
|
TP14
|
TP11
|
side stream filtration stage1
|
NDCT2
|
NDCT1
|
CWPH1
|
Boiler 1 to 5
|
PT storage tank
|
PT pump house
|
PR3
|
PR2
|
FOPH
|
Fire water tanks
|
ESP control room 3
|
CPU
|
Clarifier
|
CHP
|
ESP5
|
ESP4
|
ESP3
|
Boiler5 LHS
|
Boiler3 LHS
|
Boiler2 LHS
|
Boiler4 LHS
|
BCN9 & PR2
|
DM plant
|
DM tanks
|
Unit1 ESP TO CHIMNEY1 DUCT
|
Transformer yard1
|
SSF STAGE1
|
Ndct2
|
Ndct1
|
Esp2 to chimney duct
|
Esp control room3
|
Esp control room1
|
Cwph1
|
Chimney1 Fluecan can
|
BOP SWGR1
|
Boiler2 RHS
|
Boiler 1 LHS
|
BCN 10ab erection
|
BCN 9ab
|
Switchyard
|
Stage2
|
Stage1
|
Raw water pump house
|
Raw water MCC
|
Raw water MCC & Pump house
|
NDCT 4
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2 (1)
|
NDCT 1
|
Fuel oil PH
|
FO tanks
|
DM PLANT
|
CWPH STAGE1
|
Clarified water PH
|
Chemical house
|
PT Sludge sump
|
PT Clarifiers
|
PR 4
|
PR 3
|
NDCT 5 basin
|
NDCT 5 basin & Pedestals
|
NDCT 2 Grillage columns
|
NDCT 1 ring beam
|
Fire water tanks
|
Fire water pump house
|
DM tanks
|
DM Plant UFT tanks
|
DM Clarifiers & aerator
|
CPU Building
|
BCN and Chimney 1
|
NDCT2
|
NDCT1
|
Raw water pump house
|
Raw water pump house
|
Raw water reservoir
|
Raw water pump house
|
NDCT4
|
NDCT stage 1
|
FOPH
|
ESP5
|
ESP4
|
ESP3
|
ESP1
|
DM plant
|
DM Clarifiers
|
Clarified water pump house
|
Chemical house
|
Boiler5
|
Boiler4 LHS
|
Boiler3 RHS
|
Boiler3 LHS
|
Boiler2 RHS
|
Boiler1 LHS
|
Auxiliary Boiler
|
CPU Building
|
DM Plant
|
FOPH
|
DM Plant
|
Clarified Water Pump House
|
CCR-1
|
Aerator-1
|
NDCT-4
|
Raw Water Pump House
|
Unit#2 PHE
|
CHP Crusher & MCC
|
Aux Blr Dearator Chimney
|
Auxiliary boiler
|
NDCT#2
|
NDCT#1
|
ESP Control Room #3
|
ESP U#3
|
BCN 9AB
|
CCR Building #1
|
U#2 ID Fan to Chimney Duct
|
U#1 PA and FD Fan Foundations
|
VPH #1 and #2
|
ID Fan to Chimney Duct U#1
|
Flue Can Assembly U#1
|
ESP Control Room #1
|
ESP Unit-1
|
Boiler U#1, LHS
|
CWPH #1
|
Transformer Yard #1
|
DG Building #1
|
Station Transformer
|
Transformer Yard #2
|
Powerhouse #1 & #2
|
ESP U#2
|
ESP Control Room #2
|
Boiler#2 RHS
|
Powerhouse, CCR#2
|
Boiler#4 LHS
|
Vacuum Pump House #3
|
Vacuum Pump House #4
|
U#4 APH-2
|
ESP#4 CCR
|
ESP#5
|
Powerhouse, CCR#3
|
Boiler#5
|
Switchyard earthpit boring
|
Switchyard AC Kiosk fdn
|
TP 7 stool fixing
|
Clarifier 1 drain casting
|
PT Clarifier 2
|
PT Clarifier 2 Bridge erection
|
NDCT 2 grillage columns
|
NDCT 2 Ring beam 3rd lift
|
ACW line Unit 2 encasing
|
ACW line Unit 2
|
NDCT 5 Grillage column
|
NDCT 5 Basin floor preparation
|
NDCT 5 Basin floor
|
Boiler 4 DHT
|
NDCT 3 Racker column reinformcement work
|
NDCT 3 Racker columns work
|
NDCT 3 Grillage columns
|
NDCT 3 Racker columns works
|
NDCT 2 Ring beam 18th segment
|
Pipe rack 4 foundations
|
Pipe rack 5
|
NDCT 5 partition wall
|
NDCT 5 basin floor
|
NDCT 5 grillage columns
|
NDCT 3 Racker columns(2)
|
NDCT 3 pedestals
|
NDCT 3 Grillage structure
|
NDCT 2 Ring beam casting
|
NDCT 2 Racker columns
|
NDCT 2 Precast beam castings
|
NDCT 1 Ring beam
|
FOPH building(arrangement for FO by road handling)
|
FD PA fan fdns 1B
|
FD PA 2B
|
ESP 3 rear side
|
DM Transfer PH
|
DM tanks
|
CPU regeneration bldg
|
Boiler 1
|
BCN 8AB
|
UNIT2 FD & PA FAN FOUNDATIONS
|
UNIT1 FD & PA FAN FOUNDATIONS
|
TP37
|
TP35
|
TP34
|
TP33
|
TP32
|
TP31
|
TP15
|
TP14
|
TP13
|
TP12
|
TP11
|
ESP 5
|
ESP 4
|
ESP3
|
ESP2
|
ESP1
|
Boiler 5
|
Boiler 4
|
boiler 3
|
boiler 2
|
Boiler 1
|
Boiler1 RHS
|
BCN11
|
BCN10
|
U#1 ESP to ID Fan Ducting
|
Boiler U#1
|
TP-14 and TP-15
|
U#1 ESP to ID Fan Ducting
|
ESP Control Room #1
|
ESP U#1
|
U#1 FD Fans
|
Boiler U#2
|
U#1 FD Fan and PA Fan Rafts
|
CCR Building # 1
|
U#2 PA-APH Duct
|
U#2 APH
|
U#2 FD and PA Fan Rafts
|
TP-12
|
ESP Unit-2
|
Wagon tippler 3 & 4
|
Wagon tippler 1 & 2
|
Track hopper 2
|
Stock pile & Reclaimers
|
PT Clarifier Stage 2
|
PT Clarifier Stage 1
|
CHP Pent house 2
|
Overall view
|
Overall view
|
NDCT 1
|
Fire water pump house
|
ESP 1
|
DM Plant vessels
|
DM Plant MCC (Grade slab)
|
DM Plant mcc
|
DM tanks
|
DM Plant
|
DM plant RHS
|
Crusher house
|
CPU bldg
|
Clarifier 7
|
Clarifier 6
|
Clarified water tann
|
Clarified water tank
|
Clarified water PH
|
Chemical house
|
Boiler 1
|
Boiler 2 Drainable hydro test completed
|
Unit 2 IPBD foundations, CW line
|
CD bay structure erection
|
SP Bus ducts - Splice plates not matching
|
MV Switchgear - Switchgear not received
|
GT 2 long fire barrier wall
|
Battery room - Batteries not received
|
1BA switchgear positioned
|
ID Fan 5B fdn - Fan & Motor not received
|
ID Fan 5A - Motor pending frm Dec`21
|
ID Fan 4B - Motor pending from Dec`21
|
ID Fan 3A - Motor pending from Oct`21
|
ID Fan 2B - Motor not received - Pendng frm Oct`21
|
APH 1B - Bracings not received - Erection on Hold
|
Wagon tippler 3&4
|
VPH 2
|
VPH 1
|
ID Fan 5 - Motors not received (Pendng frm 9 month
|
Unit 2 condenser top view
|
Unit 1 Generator stator
|
Unit 1 condenser top view
|
Unit 3 LHS view
|
Unit 3 LHS view
|
BCN 10 trestle raft
|
Station transformer Bhopal Field Engr visit reqd
|
Transformer yard 1
|
Track hopper 2
|
Transfer point 14 & 15
|
Transfer point 12 & 13
|
Transfer point 37
|
Transfer point 35
|
Transfer point 34
|
Transfer point 33
|
Transfer point 32
|
Track hopper 1 MH1
|
Track hopper 2
|
Track hopper 1 Machine hatch 1
|
TG 2 PHE - Flanges not received
|
Heaters
|
Switchyard
|
RCERH 2
|
RCERH 1
|
PA Fan unit 2
|
NDCT 3 grillage columns casting
|
NDCT 3
|
NDCT 1
|
LP turbine unit 2
|
ID Fan 5 to Chimney 3 duct
|
ID Fan unit 2
|
ID Fan to Chimney 1 Duct
|
ID Fan 3_Motor not received
|
HP and IP turbine unit 2
|
ESP 5 OL Duct support
|
ESP 4 side insulation
|
ESP 4 OL duct support
|
ESP 3 OL duct
|
ESP 2
|
ESP 1
|
ESP Control room 1(Panels trays not rcvd)
|
ESP Control room 2 (Panels,cable traynot received)
|
ESP 5
|
ESP 4
|
ESP 3 CCR
|
ESP 2
|
DMCW unit2
|
DM Tanks
|
DM Plant (Vessels not received from BAP)
|
CW PH STAGE1
|
CCR 17m (Catwalk drawing pending)
|
Boiler 2 Internal DHT completed
|
Boiler 1
|
Boiler1 LHS (APH bracings supply critical)
|
Boiler 5 (Burner panel,OFA,wall blwr supply pendin
|
Boiler 4_Furnace tubes,safety vlvs,windbx supl pdg
|
Boiler 3_Corner sofa,furnace tubes not supplied
|
BCN 9AB
|
Auxiliary boiler
|
Ash slurry pump house
|
Air compressor bldg stage1
|
AHP MCC2
|
AHP COMPRESSOR BLDG STAGE1
|
Unit 1 TG
|
Unit 1 condenser
|
Transformer yard2
|
Transformer yard1
|
Switchyard
|
Power house 5
|
NDCT2
|
NDCT1
|
AIr compressor building stage 2
|
TP 37
|
TP 35
|
TP 15
|
TP 13
|
TP 12
|
TP 11
|
Boiler 5
|
Boiler 4
|
Boiler 2
|
Boiler 1
|
Wagon Tippler 3&4
|
VPH 1
|
Trestle fdn RTP 3
|
TP8
|
TP7 to TP8 bcn8ab
|
TP 21
|
Track Hopper 1 Machine Hatch concreting
|
RTP 1
|
RCERH2
|
RCERH 1
|
Pent house 21 foundation
|
FA towers location
|
BCN22 trestle foundation
|
BCN9 AB
|
BCN8 AB
|
BCN 22 Tunnel
|
BCN 22 tunnel
|
Bottom ash hopper #2
|
ASPH equipment fdn stg1
|
AHP Pipe pedestal area
|
Unit2 thrust block
|
Unit2 PHE
|
Unit2 PA FAN
|
Unit 2
|
Transformer yard2
|
Transformer yard1
|
Tp14and tp15
|
Tp13
|
TP12
|
TP 11
|
ST 1 ercn
|
PT clar 1&2
|
Portal crane
|
ID fan 1
|
FDfan2
|
FD PA FANS UNIT1
|
ESP 3
|
ESP 2
|
ESP 2 DUCT
|
ESP 2 CCR
|
ESP 1
|
ESP 1 DUCT
|
ESP 1 CCR
|
Dmp rhs tanks
|
Dmp mcc
|
Dmp grnd
|
Dmp grnd
|
Dmp east drns balance
|
DMCW PUMPS UNIT1
|
DM Tanks
|
Dm plnt
|
Dm plnt bldg
|
Dm plant UF Tanks DGT
|
DM Plant trenches
|
CWPH STAGE1
|
CST TANKS
|
CPU
|
Condenser2
|
Condenser 1
|
Chimney 1
|
Boiler2
|
Boiler1
|
Boiler1 RHS
|
Boiler1 LHS
|
Ash slurryph Stage1
|
APH UNIT2
|
APH UNIT1
|
Air compressor bldg stage1
|
FA Silo 2 EL @-0.300m slab
|
CPU building slab
|
NDCT 2 ring beam
|
NDCT 2 racker columns
|
NDCT 2 Grillage columns
|
Vacuum pump house 1
|
Vacuum PH2
|
Silo utility building
|
FA Silo Pipe pedestals
|
Ndct#2 shell 3rd lif concrete pouring
|
NDCT 3 Pedestal 3rd lift no 35&36 concrete pourin
|
NDCT 2 Racker column pouring started .(41B&42A)
|
FA silo5
|
FA silo
|
AHP Compressor house stg1
|
AHP Compressor house stg1(2)
|
AHP Compressor house for stg2
|
AWPH1
|
ASPH-1&2
|
ASPH 3&4
|
AHP MCC5
|
AHP MCC2
|
AHP MCC1 area
|
Vac PH 4
|
Vac PH 3
|
Boiler 3
|
RHS mills #2
|
PHE #2
|
Unit2 DMCW
|
Unit2 Condenser
|
Transformer yard2
|
Portable RODM
|
NDCT 3 basin segement casting
|
NDCT 3 basin segement casting
|
NDCT 2
|
NDCT 2 Racker column casting 40B 41A
|
NDCT 1 basin segment curing
|
ESP5
|
ESP2
|
ESP1
|
ESP CR5
|
ESP CR2
|
DMPLANT
|
DM TRANSFER PH
|
DM TRANSFER PH
|
DM TANKS AND FOPH
|
DM PLANT
|
CST PH STAGE1
|
CPU BLDG
|
PT Clarifier 1 & 2
|
Boiler5
|
Boiler4
|
boiler1
|
ACW pipe Unit 2 DM Inlet
|
Bottom ring header #2
|
Bottom ring header #2
|
Side stream filtration vessel foundation concrete_
|
Side stream filtration stage 2 Vessel foundation
|
Ndct#2 Raker column no 35B 36A
|
Ndct#1 pedestal no 23&24
|
NDCT 2 Ring beam
|
NDCT 2 Racker column number 38B&39A
|
NDCT 2 Racker column curing
|
NDCT 2 Pd47 & Pd48
|
NDCT 2 Grillage columns
|
NDCT 2 _raker column pouring
|
DM Plant _Degassed water storage tank
|
DM Clarifier 7
|
Aerator 2 raft
|
id fAN 2
|
ID Fan 1
|
ESP 5 inlet
|
ESP 2 inlet
|
ESP 2 OUTLET DUCT
|
ESP 1 DUCT AT OUTLET
|
ESP 1 CONTROL ROOM
|
Chimney 1
|
Boiler 5
|
Boiler 2
|
Boiler 1
|
NDCT 2
|
Chimney 3 270m achieved on 27 Mar 2022
|
CPU building slab concreting
|
Clarified water pump house operating floor concret
|
APH 5B module erection
|
APH 5B (Unit 5) erection
|
VPH 1&2
|
Unit2 FD PA FANS
|
TP15
|
TP14
|
TP13
|
TG1 CONDENSER
|
Stage1 air compressor bldg
|
Overall view
|
ESP2
|
ESP1
|
ESP Control room 2
|
Boiler2
|
Boiler2
|
Boiler1 - First pass
|
Boiler1 Outer view
|
Boiler1
|
Boiler1
|
Air Preheater 1
|
8.5m Unit 2 heaters
|
Condenser #2
|
Unit 2 17m BC bay
|
CCR1 0m grid 15 17
|
CCR1 0m
|
Transformer yard 2
|
Transformer yard 1
|
Transformer yard 5
|
Transformer yard 4
|
Transformer yard 3
|
TP 15
|
TP 14
|
TG Deck 4
|
TG 2 pedestals
|
TG 1
|
Switchyard
|
Switchyard control room
|
Stage1
|
ID fan 3
|
ID fan 2
|
ID Fan 1
|
ID 2
|
ESP 2 front, VPH 2
|
ID fan 4
|
ESP Control room 2
|
ESP 5
|
ESP 2 Duct supports
|
ESP 1 OL DUCT
|
CW line stage 2
|
CST PH1
|
Chimney 3
|
Boiler 2
|
Boiler2
|
Boiler 5
|
Boiler 1
|
Auxiliary boiler
|
Air Compressor bldg stage2
|
FOPH
|
DM tanks
|
DM tanks
|
DM Plant building
|
ESP 1 OL ducts
|
ID FAN 2A
|
Id fan to chimney duct unit1
|
ESP2
|
Boiler 1
|
Chimney 2 top beam erected
|
Yadadri overall
|
Track hopper 1 MH Sump
|
NDCT 2 ring beam
|
ESP 5
|
ESP 1 Outlet
|
ESP 1
|
ID to Chimney duct #1
|
Boiler 5
|
Boiler 5
|
Boiler 4
|
Boiler 4 bunker hopper
|
Boiler 4 WW hopper
|
Boiler 4
|
Boiler 2
|
Boiler 2
|
TP15
|
ID fan 4
|
ID fan 3
|
ID fan 2
|
ID Fan 1
|
ESP Controlroom 4
|
ESP control room 3
|
ESP control room 2
|
VPH 1
|
ESP 5
|
ESP 3
|
ESP 2 Duct support
|
ESP 1 duct
|
Chimney 3 (Unit #5)
|
Chimney 1(#1)
|
Boiler 2
|
Boiler 1
|
Boiler 1
|
BCN 9AB
|
AHP MCC 1
|
AHP compressor house stage 1
|
ESP 2 VPH 2
|
ESP 1
|
CW pump house stage 1
|
Chimney 1 @ 270mtrs
|
Boiler 1 spiral Water wall
|
Boiler 1
|
BOF to ESP Duct foundations #1(M row)
|
APH 1A
|
Unit 2
|
Unit 2 Hp heaters@17m BCbay
|
Thrust block #2
|
TG hall stage 1
|
Switchyard stage 1
|
Portal crane fdn #2
|
PH str A row unit#2
|
PH A row #1
|
MOT room #1
|
HP heaters #1
|
GT #1
|
DMCW pumps erection#2
|
DMCW PHE fdns #1
|
Cw stage 1 header pipes
|
CST pump house stage 1
|
Condenser plates#2
|
Condenser plate and hot well#2
|
Condenser hotwell #1
|
Compressor bldg stage 1
|
CCR1 DH bay
|
CCR1 17m structure
|
CCR 1 0m grid 11a-13
|
Bottom ring header #2
|
Boiler 2
|
Boiler 1 LHS
|
APH Duct and SCAPH #2
|
3.5m CCR1 grid 13_15 BC bay works
|
PT Plant Sludge sump
|
LDO tank fdn
|
HFO tank bitumen matting
|
HFO tank bitumen matting
|
Fuel oil road unloading arrangement by road
|
FOPH
|
FOPH(1
|
DM Trf PH
|
DM Tanks
|
DM Plant
|
Dm clarifier 7
|
Dm clarifier 6
|
Clarifier 5
|
Clarifier 4
|
Clarifier 2
|
Clarified water storage tank
|
Clarified water storage tank(1)
|
Chimney 2 & 3
|
Chimney 1 & 2
|
Boiler 2
|
TSTransco substation
|
TP 15
|
TP 14
|
TP 13 & 14
|
NDCT 2
|
NDCT 1
|
Esp 1 outlet
|
CW PH stage 1
|
CHP Stock pile
|
Boiler 1
|
Auxiliary Boiler
|
Aux Boiler ducting
|
Auxiliary Boiler
|
Aux boiler Chimney
|
Ash slurry pump house 1
|
APH 1A
|
AHP MCC 2
|
AHP compressor bldg stage 1
|
Winch for Chimney 2 Structure ercn
|
TP 14 Str
|
TG 5 deck staging
|
PT Clarifier 3 pipeline
|
NDCT 2 Ring beam shuttering works
|
NDCT 2 Racker column shuttering works
|
NDCT 2 basin segments reinforcement works
|
FA Silo 4 raft
|
ESP 3 inlet funnels
|
Clarified water PH pump floor
|
CW Pipe laying - CW Pump house Stage 1
|
NDCT 5 Pedestal bitumen coating
|
Wagon tippler 1 (-5)m slab
|
TP 33
|
TP 31
|
Crusher house 22
|
BCN 9AB trestle
|
BCN 8AB
|
Boiler 5
|
Boiler 5 Hangers and headers
|
Boiler 5 Seperator floor
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
NDCT 2
|
Switchyard control room
|
NDCT 2 segments drains
|
Chimneys
|
Clarifier - 4 Base slab concreting
|
BCN-2AB Segment 1 final lift slab concrete
|
NDCT-04 Basin floor Segment
|
CW Pit raft in unit-2 concrete casting
|
ASWP-SUMP STAGE-2 RAFT CONCRETE
|
FOPH slab concreting
|
Power House 4 slab at +29m (BC bay) concrete
|
TH1 MH1 raft
|
Silo 3 raft
|
TH2 Hopper 9 slab
|
Clarifier -2 Base slab concreting
|
ACW stage 01 slab concreting
|
Scaffolding training
|
Monthly Safety drive
|
NDCT 3 Pedestals shuttering
|
NDCT 3 Drain steel
|
NDCT 3 basin floor
|
NDCT 1 Raker column scaffolding
|
NDCT 1 Pond wall raft
|
NDCT 1 basin floor
|
NDCT 1 basin floor curing
|
Heaters #1
|
ERH 2 raft concreting
|
ERH#2 raft concrete
|
DM Clarifier 7 Shaft
|
Compresser house 3,4,5 slab final segment casting
|
clarifier no 1 sludge pit
|
Clarifier -2 Base slab concreting
|
Chimney 1 outer curing
|
ACW stage 01 slab concreting
|
PT Plant area
|
Clarified water pump house_Floor shuttering
|
Raw water pump house slab at +8.8m
|
Clarified water pump house Floor shuttering
|
NDCT 2 Raker Column 16B 17A
|
NDCT 1 basin
|
Switchyard control room first floor
|
NDCT 3 pedestal area backfilling
|
NDCT 3 basin
|
CW piping at Thrust block 1
|
TP15 Second tier frame of A1-A2 columns
|
TP 7 D1 column
|
Boiler 3 Pressure Parts erection
|
Boiler 2 area
|
Boiler-1 Pressure Part area
|
Unit-4 ID fan area
|
Unit-3 ID fan
|
Unit-2 ID fans
|
Unit-1 ID fan area
|
Stacker erection
|
PT Plant sludge pit area
|
DM Plant N pit area
|
FOPH
|
Fire water pump house
|
ESP-3 area
|
ESP-2 Rear side area
|
ESP-1 rear side area
|
DM Tanks
|
DM Tanks
|
DM Plant area
|
DM Clarifiers
|
CPU Building area
|
Clarifier5
|
Clarified water MCC
|
Clarified water PH
|
Chimneys
|
Cascade aerator
|
BCN 30
|
Auxiliary Boiler
|
Ash water pump house
|
Ash slurry ph 5
|
AHP compressor building stage2
|
AHP compressor building stage1
|
Track hopper 2
|
Water system area
|
Overall view
|
ESP 3
|
ESP 2
|
ESP 1
|
CW pit 1
|
CWPH stage1
|
CST STAGE1
|
Chimney3
|
Chimney2 @250Mtr
|
Chimney1
|
CCR area
|
Boiler4
|
Boiler2
|
Boiler2 area
|
Boiler1
|
Boiler1
|
Boiler 5
|
Boiler 5
|
Boiler 4
|
Boiler 3
|
Auxiliary boiler
|
Ash slurry area
|
APH4
|
APH 3 area
|
Air compressor building stage1
|
AHP compressor house stage2
|
track hopper 2 MH1 sump raft concrete_finishing
|
track hopper 2 MH1 sump raft concrete
|
Power House 1 slab at +35m (grid 1 to 3) concrete
|
Clarifier 7, first lift wall concrete
|
CCR 1 & 2 Slab at +8.5 m
|
C.W Pump House 1 slab concrete castin
|
BCN 2AB Segment 2 Raft concrete
|
BCN 36AB raft concrete
|
Track Hopper -2 wall 2nd stage concrete work
|
Station transformer-1 rail track 1st stage concret
|
Service water tank bottom slab concrete
|
NDCT-05 Ring raft segment number 19th segment conc
|
FOPH slab casting
|
ESP CR 2 slab 8.5 m casting
|
DM plant Roof Slab Concreting
|
CW pipe line encasing casting
|
CRH-1 Bolt lift pedestal concrete casting
|
Compressor House Stage 2 Middle 1/3 Slab casting
|
Clarifier 6, bottom Slab concrete
|
Clarified water tank slab concrete casting
|
Channel 04 Wall concreting started in CWPH #2
|
BCN-2AB Segment 01 Raft concrete casting
|
Ash water pump house stage 1 sump raft concrete
|
Water system
|
Stock pile
|
Stage 2 overview
|
NDCT Stage 1 CW PH
|
Bottom ash hopper #4 pedestal shuttering
|
U#4 Bottom ash hopper raft concreting
|
Chimney 2 - third segment concreting started
|
E11a footing casted...CCR 01
|
Chimney 1(#1) reinforcement placement
|
TG raft #3 under curing
|
D11a footing casting in CCR 1
|
TG raft #3 concreting
|
Auxiliary boiler chimney raft casted
|
Auxiliary boiler chimney
|
Auxiliary boiler footings
|
Chimney 1 reinforcement placement
|
ESP #3
|
ESP 2 from rear side
|
ESP 1 AB Pass
|
Boiler #1
|
ID Duct foundations #3
|
ID Duct #1 foundations near ESP CD Pass
|
ID Duct #1 foundations near chimney
|
GT #3 grade slab - Reinforcement placement
|
GT #1 shuttering
|
Chimney 2 Concreting - second segment raft
|
Chimney 3 Shuttering
|
ESP Control room #3
|
ESP Control room #1
|
Compressor building #1
|
Boiler #4 Column erection start
|
Boiler #2 Column erection start/pooja
|
CHP Civil - Pooja by Powermech
|
Power house #2 A19 pedestal casting
|
Chimney 2(#3 & #4) raft secon segment concreting s
|
ESP #2 column encasing - shuttering
|
CCR #3 & #4 pedestal casting
|
Power house #2 A19 raft concreting
|
Chimney 1(#1) reinforcement placement
|
Chimney 3(#5) raft first segment concreting
|
Power house #2 Structural erection
|
Power house#5 Civil works
|
Power house #4 (Submerged reinforcement due torain
|
Power house #2 (Incl TG Raft)
|
ID Duct foundations #5
|
ESP control room #5
|
ESP 5 foundations
|
ESP #4
|
ESP #2
|
Unit #5 Control room
|
Chimney 3 - Reinforcement works
|
Chimney 1 (#1 & #2)
|
Common control room #3 & #4
|
Bowl mills #4 reinforcement work
|
Boiler #5 foundations
|
Boiler #4 Foundations
|
Bottom ash hopper #4
|
Bottom ash hopper #2 excavation
|
Auxiliary boiler civil works
|
Chimney 2(#3) raft first segment casted..curing
|
Power house#1 Roof truss erection#1
|
Chimney 2(#3 & #4) raft first segment concreting s
|
ID fan 1B concreting (335/361 CuM poured)
|
ID fan 1B concreting started(361CuM)
|
Esp#3 D pass
|
Boiler #3 erection
|
Boiler #1 LHS MBL erection
|
Generator transformer #1 foundation works
|
ESP #2 AB pass
|
ESP#1AB pass
|
Boiler#1 erection
|
CEP #1 wall first lift casted
|
TG column #1 hydraulic jack fixed
|
Bottom ash hopper #4 reinforcement works
|
Power house #5
|
ID Duct #5
|
ESP Control room #5
|
ESP #5
|
Boiler #5
|
Chimney 3(#5 Single flue)
|
Power house#2 reinforcement works
|
CW pump house stage 1 excavation works
|
CW pump house stage 1
|
Power house #3
|
Chimney 1(#1) water accumulation due to rains
|
TG 4 reinforcement submerged in water due to rains
|
ID duct foundations #3
|
ID duct foundation #1
|
S418 road works
|
Auxiliary boiler
|
Chimney #3
|
CEP #1 reinforcement works
|
TG 4 raft reinforcement placement
|
Truss R2 erection in power house#1
|
Chimney 3(#5 single flue) reinforcement placement
|
ID duct foundations#1
|
Auxiliary boiler foundations
|
TG column #1 slip form assembly
|
ID duct foundations#5
|
Boiler 1
|
Transformer yard #1 GT & UT foundations
|
TG 4 reinforcement works
|
S418 road compaction u/p
|
Power house structure Column erection
|
#1 Power house structure Crane girder erection
|
Power house #2
|
ID Fan foundation shuttering
|
ID Duct foundations #5
|
ESP CR#5
|
ESP CR #3
|
ESP #5 earth mat works
|
ESP #4 Mechanical
|
ESP #2 erection
|
U#5 Control room pedestals
|
Compressor house Stage 1 backfilling
|
Chimney 3 long view
|
Chimney 3 shuttering
|
Chimney 2 (#3 & #4) bar bending works
|
CCR #3 & #4
|
Bowl mill #4
|
Boiler 5
|
Boiler 4 foundations
|
Bottom ash hopper PCC #4
|
Aux Boiler foundation
|
TG 4 shuttering works
|
ID Fan shuttering works
|
ESP #5 earth mat works
|
TG 5 PCC for raft (submerged under water)
|
TG Raft 3 Bar bending and checking
|
TG Raft 3 Bar bending and checking
|
Power house #5 pedestals
|
Power house 5 PCC
|
Power house 4 pedestals & TG Raft PCC
|
Power house #3 pedestals
|
Power house 2 Structure erection
|
Power house 2 pedestals
|
Power house 1 columns erection
|
Power house 1 pedestals
|
NDCT 2 excavation works
|
Generator transformer #5 foundation
|
ID duct foundations #3
|
ID Fan 1 B bar bending works
|
ID Duct #1 foundations
|
ESP Control room #5 plinth beam
|
ESP 5 pedestals
|
ESP #3 erection
|
ESP #3 AB Pass Earth mat works
|
ESP #2 erection
|
CW pump house 2 excavation
|
CW pump house 1 excavation
|
CW Pipeline excavation stage 1
|
Concrete cube quality tests
|
Chimney 3(#5 Single flue) Bar bending works
|
Chimney 2 (#3 & #4) bar bending works
|
Chimney 1(#1 & #2) Bar bending
|
CCR #3 & #4 pedestals
|
CCR 1 & 2 Pedestals
|
CCR 1 & 2 Pedestals
|
Boiler 5 pedestals
|
Boiler 3 Erected columns
|
Boiler 3 Mill foundations Bar bending
|
Boiler 2 Pedestals
|
Auxiliary boiler bar bending
|
ESP 3
|
TG#5 PCC completed
|
Chimney 3(#5 single flue) reinforcement placement
|
Auxiliary boiler foundations
|
Power house #2
|
Power house #1
|
ESP #4
|
ESP #2
|
ESP 5 foundatiions
|
Boiler #5 Foundations
|
Chimney 3
|
Chimney 2 (#3 & #4)
|
Chimney 1
|
Power house #3
|
Power house #4 excavation works
|
Power house #1
|
ESP #4
|
ESP #3
|
ESP #1
|
Boiler #1
|
ESP#1
|
Chimney 3(#5 single flue) reinforcement placement
|
ID duct footing#1
|
Compressor building footings
|
Chimney 2(#3 & #4) reinforcement placement
|
ID duct foundations#1
|
PCC works of Aux Boiler started
|
Chimney 3(#5 single flue) reinforcement placement
|
Close view of chimney reinforcement
|
Chimney 2(#3 & #4) reinforcement placement
|
ESP #4 intermediate frame erection
|
ESP #4 intermediate frame welding
|
Chimney 2(#3 & #4) reinforcement placement
|
TG raft #3 reinforcement
|
Boiler#5 foundations
|
Power house#3 civil works
|
Power house#1 civil works
|
ID duct foundations#1 concreting under progress
|
Chimney 3(#5 single flue) reinforcement placement
|
Chimney 3(#5 single flue) top mat reinforcement
|
ID duct foundations#1
|
Power house #3 fabrication works
|
UT #1b reinforcement for pedestal
|
GT#1b third lift staging
|
GT #1A pedestal third lift staging
|
Chimney 3(#5 single flue) reinforcement placement
|
Concreting of Power house #2 foundations
|
ID duct foundations#1
|
Sanitisation of common areas
|
Power house #5 foundations shuttering
|
Social distancing during temperature check -mrng
|
TG Raft #3 bar placement
|
Boiler #5 pedestals
|
ESP #5 pedestals completed
|
CCR 1 foundation reinforcement
|
Chimney 2 (#3 & #4) reinforcement fixing
|
ESP #2 casing wall erection
|
ESP #4 frame erection
|
Chimney 1 (#1 & #2) reinforcement placement
|
Chimney 1(#1) excavation
|
Power house #2
|
ID Duct support area #5
|
Generator transformer #5 Civil works
|
Generator transformer #1 Civil works
|
ESP #5 control room
|
ESP #5 foundations
|
ESP #4
|
ESP #3
|
ESP #1
|
ESP 2 Pass D
|
Compressor house #1
|
Chimney 2 (#3 & #4)
|
Chimney 3(#5 Single flue) Excavation
|
Chimney 1 (#1 & #2) Excavation
|
Boiler #3
|
Boiler #1
|
Boiler #5 Foundations
|
Boiler #1
|
Chimney 1 (#1 & #2) Excavation
|
ESP #4 erection
|
ESP #3 erection
|
ESP #2 erection
|
ESP #1 View from LHS
|
ESP #1
|
Boiler #1 erection
|
TG Raft#3 Reinforcement - After rains on 06 Mar 20
|
TG Raft #2 reinforcement works
|
TG Raft #1 Concreting completed
|
Chimney 3(#5 Single flue) PCC completed
|
Chimney 2 (#3 & #4)
|
Power house #5 excavation
|
Generator transformer #5 Civil works
|
Generator transformer #1 Civil works
|
Power house #4
|
Power house #3
|
Control room #5 excavation
|
CCR #3 & #4
|
CCR #1 & #2
|
Boiler #5 Foundations
|
Boiler #4 foundations
|
Boiler #3 foundations
|
Boiler #2 foundations
|
TG raft #1 concreting started
|
ESP #3
|
S418 road compaction u/p
|
Generator transformer #1 Civil works
|
Compressor house #1
|
CCR 3 & 4
|
Boiler #3
|
Power house #3
|
ESP#1 casing wall erection
|
TG raft 2 reinforcement works
|
TG raft 1
|
Power house #4
|
Power house #3
|
Power house #2
|
CW Pipe excavation #5
|
ESP Control room #3
|
TG raft area #5
|
TG raft area 4(PCC submerged under seepage water)
|
TG Raft area #3
|
ESP #4
|
ESP #3
|
ESP #2
|
ESP #1
|
Boiler #5
|
Boiler #3 foundations
|
Boiler #2 LHS Foundations
|
Boiler #1 erection
|
Power house #1
|
CCR #1 & #2
|
Chimney 3(#5 Single flue) Excavation
|
ESP Control room #3
|
ESP Control room #5
|
Generator transformer #5 Civil works
|
Generator transformer #1 Civil works
|
ESP #5
|
ID Duct support area #5
|
ESP #5
|
CCR #3 & #4
|
Boiler 4
|
Boiler #3
|
Power house #3
|
Power house #4
|
ESP #3
|
ESP #2 erection
|
ESP #1 erection
|
Boiler 1 erection
|
ESP#1 Intermediate frame erection
|
TG Raft #5 excavation
|
TG Raft #4 excavation
|
Power house #3 foundations and TG Deck excavation
|
Power house #2 foundations
|
UT 3a 3b
|
Control room #5 excavation
|
ESP #5 foundations
|
ESP Control room #3
|
ESP #1 erection
|
ESP Control room #5
|
ESP #4 Intermediate frame assy
|
CCR #3 & #4
|
Boiler #5 Foundations
|
Boiler #4
|
Chimney 3(#5 Single flue) Excavation
|
ESP #4
|
ESP #3
|
ESP #2
|
UT - 3a 3b & Fire barrier civil works
|
Power house #5
|
Power house #3
|
Power house #2
|
Power house #1 foundations
|
TG Raft #2
|
TG Raft #1
|
NDCT #2 Drilling works
|
NDCT #1 Drilling works
|
Unit#1 view from Transformer yard
|
GT #3 placed
|
Generator transformer #5 Civil works
|
Generator transformer #1 Civil works
|
CCR #3 & #4
|
CCR #1 & #2
|
Boiler #5
|
Boiler #4
|
Boiler #3 LHS
|
Boiler #3 Front side
|
Boiler #2
|
Boiler #2
|
Fabrication yard #2 & #5
|
SAW welding - column fabrication
|
ESP #5 foundations
|
ESP #4
|
ESP #3
|
ESP #2
|
ESP #1
|
TG raft PCC #1
|
Generator transformer #5
|
GT #3 Fire barrier wall
|
ESP #5 foundations
|
ESP #4
|
ESP #3 erection
|
ESP #2 assy
|
ESP #2
|
ESP #1 Intermediate frame assy
|
ESP #1 erection
|
ESP#1
|
ESP#2 D pass
|
Concreting in Boiler#4
|
ESP#1 erection
|
Power house #4
|
Gen Transformer #5
|
ESP #4
|
ESP #2
|
Boiler #5
|
Boiler #4
|
Boiler #3
|
Boiler #2
|
Boiler #1
|
Boiler #1 erection started
|
Generator Transformer foundation readiness
|
Power house #4
|
Power house #2
|
Power house #1
|
ESP #5
|
ESP #4
|
ESP #3
|
ESP #2
|
CCR Unit #3 & #4
|
Boiler #5
|
Boiler #4
|
Boiler #4
|
Boiler #3
|
Boiler #2
|
ESP#4 column erection started
|
Structure fabrication works
|
GT #3
|
ESP #5
|
ESP #4
|
ESP #2 backfilling works
|
ESP #3 Control room works
|
ESP #1
|
Boiler #5
|
Boiler #2
|
ESP #1
|
Power house 2
|
Power house 2
|
Power house 1
|
ESP 5 CD Pass
|
ESP 5 AB Pass
|
ESP 4 D Pass
|
ESP 4 C Pass
|
ESP 4 AB Pass
|
ESP 3 D Pass
|
ESP 3 C Pass
|
ESP 3 AB Pass
|
ESP 2 D Pass
|
ESP 2 C Pass
|
ESP 2 AB Pass
|
ESP 1 CD Pass
|
CCR Stage 1
|
Boiler 5
|
Boiler 4 RHS
|
Boiler 4 LHS
|
Boiler 3
|
Boiler 3 LHS
|
Boiler 2
|
Boiler 1 RHS
|
Boiler 1 LHS
|
Power house #4
|
ESP#4
|
ESP #5
|
Boiler #5
|
Blasting - Compressor house #1
|
GT #3 area
|
GT Rail track
|
Power house #3
|
ESP #3
|
Boiler #3
|
Power house #1
|
ESP #1
|
Boiler #1
|
Boiler#2
|
ESP#2
|
Boiler#2
|
Boiler#2
|
Boiler#2
|
Boiler#2
|
Boiler#2
|
Boiler#2
|
ESP#2
|
ESP#2
|
ESP#2
|
ESP#2
|
ESP#1
|
ESP#2 column erection started
|
Boiler#4
|
ESP#4
|
ESP#1 AB pass
|
ESP#1 erection
|
ESP#1
|
GT rail cum road bar placement
|
GT pedestal post rail placement
|
ESP#2 AB pass
|
ESP#2 CD pass
|
Boiler 2
|
Power house #2
|
Boiler #1 rear side
|
ESP#1 AB pass earthmat works
|
ESP#1 CD pass
|
Boiler #1
|
Boiler#5
|
ESP#5
|
Boiler #3
|
ESP#3
|
ESP#1
|
Boiler #1
|
Boiler #4
|
Power house #2
|
ESP #2
|
Boiler #2
|
Boiler #2
|
Boiler #1 front
|
Boiler #1
|
ESP#1 foundations
|
Boiler #3
|
ESP #3 rafts
|
ESP #3 bar bending works
|
Boiler #1 Main column foundations
|
Boiler #1
|
ESP#1
|
ESP #5
|
ESP #3
|
Boiler #5
|
Boiler #3
|
Boiler #1
|
Unit #3 fabrication works
|
Unit #1 & #4 Fabrication Gantry crane erection u/p
|
ESP #1 column erection started
|
GT 3C bar placement
|
GT 3A raft
|
Thrust block #3
|
Boiler #3
|
Boiler #4
|
Power house #4
|
Power house #5
|
Boiler #5
|
ESP #3
|
Boiler #3
|
ESP #1
|
Boiler #1
|
Power house #2
|
ESP #2
|
Boiler #4
|
Boiler #2
|
ESP Control room #3
|
GT #3
|
ESP #3
|
ESP #2
|
ESP #1
|
Boiler #3
|
Boiler #1
|
ESP#4
|
Boiler#4
|
ESP#1 AB pass
|
Boiler #1
|
ESP#1 CD pass
|
ESP#2 AB pass
|
ESP#2 CD pass
|
Boiler 2 RHS
|
ESP#3 control room excavation
|
Boiler #3
|
ESP#3
|
Boiler#4
|
ESP#4 rear side
|
ESP#4 front side
|
ESP#5
|
Power house #3
|
ESP#3
|
Boiler #3
|
Power house #4
|
Power house #4
|
ESP #4
|
ESP #4
|
ESP #4
|
Boiler #4
|
Boiler #4
|
Boiler #4
|
ESP#3
|
Boiler #3
|
Power house #2
|
ESP #2
|
ESP #2
|
ESP #2
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
ESP#1
|
Power house #4
|
Boiler#4
|
Boiler #4
|
Boiler #4
|
Power house #2
|
Power house #2
|
ESP #3
|
Boiler #3
|
ESP #1
|
Boiler #1
|
Boiler #1
|
ESP #1 Pedestals_Bitumen painted
|
Power house #1
|
Power house #5
|
Power house #4
|
Power house #3
|
Power house #2
|
ESP #5
|
ESP #5
|
ESP #4
|
ESP #4
|
ESP #3
|
ESP #3
|
ESP #3
|
ESP #3
|
ESP #2
|
ESP #2
|
ESP #2
|
2 Nos 65 HP pumps deployed for dewatering
|
Unit #5 control room excavation
|
Area filled with dewatering of excavation areas
|
Bar bending works #3
|
Bar bending works #3
|
Boiler #5
|
Boiler #5
|
Boiler #5
|
Boiler #4
|
Boiler #4
|
Boiler #4
|
Boiler #3
|
Boiler #3
|
Boiler #3
|
Boiler #3
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
ESP#1
|
ESP#1
|
ESP#1
|
ESP#1
|
ESP#1
|
Boiler #1
|
Boiler #1
|
ESP #3
|
ESP #3
|
ESP #3
|
ESP #2
|
ESP #1
|
Boiler #3
|
Boiler #3
|
Boiler #3
|
Boiler #2
|
Boiler #1
|
Boiler #3
|
Boiler #3
|
Boiler #3
|
ESP#3
|
ESP#3
|
ESP#3
|
ESP#5
|
ESP#5
|
ESP#5
|
ESP#5
|
Boiler#5
|
Boiler#5
|
Boiler#5
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
ESP#1
|
ESP#1
|
ESP#4
|
ESP#4
|
Boiler#4
|
Boiler#4
|
Fabrication yard #1 #4
|
ESP #5
|
ESP #5
|
ESP #5
|
ESP #4
|
ESP #4
|
ESP #4
|
ESP #3
|
ESP #3
|
ESP #2 bar bending works
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #1
|
ESP #1
|
ESP #1
|
Boiler #5
|
Boiler #5
|
Boiler #4
|
Boiler #4
|
Boiler #3 bar bending works
|
Boiler #3
|
Boiler #2
|
Boiler #2
|
Boiler #1
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Boiler #2
|
ESP #2
|
ESP #4
|
Boiler #4
|
ESP #3
|
ESP #3
|
ESP #3
|
Boiler #3
|
Boiler #3
|
ESP#1
|
ESP#1
|
ESP#1
|
ESP#1
|
ESP#1
|
Boiler #1
|
Boiler #1
|
Boiler #2
|
Boiler #2
|
ESP #4
|
Boiler #4
|
ESP #5
|
ESP #5
|
ESP #3
|
ESP #3
|
ESP #3
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
Boiler #5
|
Boiler #5
|
Boiler #3
|
Boiler #3
|
Boiler #3
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
Storage yard from CCTV view
|
ESP #5 Water logged
|
Storage sheds
|
Storage sheds
|
Power house #1
|
ESP #5
|
ESP #5
|
ESP #4
|
ESP #3
|
ESP #2
|
ESP #1
|
Boiler #5
|
Boiler #4
|
Boiler #4
|
Boiler #3
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
Power house #3
|
Power house #3
|
ESP #5
|
ESP #4
|
ESP #4
|
ESP #4
|
ESP #3
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #1
|
ESP #1
|
ESP #1
|
Boiler #5
|
Boiler #4
|
Boiler #4
|
Boiler #3
|
Boiler #3
|
Boiler #2
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Power house #1 excavation
|
ESP #5
|
ESP #5
|
ESP #4
|
ESP #3
|
ESP #3
|
ESP #2 F8 Re-bar placement
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
Boiler #5
|
Boiler #4
|
Boiler #4
|
Boiler #3
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
MPH 2
|
MPH 1
|
ESP 5
|
ESP 5
|
ESP 4
|
ESP 4
|
ESP 3
|
ESP 3
|
ESP 3
|
ESP 2
|
ESP 2
|
ESP 1
|
Boiler 4
|
Boiler 4
|
Boiler #3
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Boiler 1
|
Power house #4
|
ESP #5
|
ESP #4
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #2
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #4
|
Boiler #5
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #4
|
Boiler #4
|
Power house #1
|
ESP #1
|
Boiler #1
|
Power house #2
|
Power house #1
|
ESP #5
|
ESP #4
|
ESP #3
|
ESP #3
|
ESP #2
|
ESP #2
|
ESP #1
|
ESP #5
|
Boiler#5
|
Boiler#5
|
Boiler#4
|
Boiler #4
|
Boiler #3
|
Boiler #3
|
Boiler #3
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Power house #4
|
Power house #2 - Drilling for blasting
|
Power house #2
|
Power house #1
|
ESP #2 F8 Raft RCC works
|
ESP #2
|
ESP #1
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
ESP #1
|
Boiler #2
|
Boiler #1
|
ESP#2
|
Explosive vehicles behind chimney area
|
Boiler#5
|
ESP#5
|
Boiler#4
|
ESP#4
|
ESP#3
|
Boiler #3
|
Boiler #3
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
ID Duct area#2
|
ESP#2
|
Boiler 2
|
Unit-2 ESP
|
M) Excavation@ Boiler#5
|
L) Excavation in Boiler#2
|
k) Boiler#1
|
Unit-4 ESP
|
Unit-4 Boiler
|
Unit-2 Boiler
|
d) 33KV line provided by customer.
|
a) 33 KV/11 KV substation area
|
e) M./s RVPR Batching Plant.
|
f) M/s Kanwar Batching Plant.
|
j) Material placed in open storage yard.
|
c) Inside view of closed storage view
|
b) Closed storage shed
|
i) ID Duct support Unit#1
|
h) ESP#2- RCC work under progress.
|
g) ESP#1- RCC work under progress.
|
ID Duct support area #2
|
ESP #5
|
ESP #3
|
ESP #3
|
ESP #1
|
ESP #2
|
ESP #2
|
ESP #1
|
ESP #1
|
Boiler#5
|
Boiler#4
|
Boiler#3
|
Boiler #5
|
Boiler#1
|
Boiler #2
|
Boiler #2
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Batching plant complex
|
ID Duct support area #2
|
ESP #2
|
Boiler #4
|
Boiler #2
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
Boiler #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP#2 for PCC
|
ESP#2 Excavation
|
ESP #2
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
ESP #1
|
Quality lab_Kanwar
|
Batching plant_RVPR
|
Batching plant_Kanwar
|
ESP #2
|
ESP #1
|
Boiler 2 ESP 2
|
Boiler 2
|
Boiler 2
|
Boiler 1
|
ESP #3
|
ESP #4
|
ESP #4
|
ID Duct support area #2
|
ESP #2
|
ESP #1
|
ESP #1 water seepage
|
ESP #1
|
Boiler #1 Drilling works for blasting
|
Boiler #1 Drilling works for blasting
|
Boiler #3 area
|
ESP #2 area
|
ESP#1 area
|
BOF # 1area
|
BOF #1 area
|
Switchyard
|
NDCT Stage 2
|
NDCT Stage 1
|
FOPH area
|
CHP area
|
CHP area
|
Canteen area
|
Admin area
|
Admin area
|
Storage sheds
|
Storage sheds construction
|
Steel
|
Stacked material
|
CW Pipes storage
|
Substation1
|
CHP area
|
CHP area
|
CHP area
|
CHP Area
|
Closed shed construction - Tinny craft
|
Closed shed construction - Tinny craft
|
Closed shed construction - Tinny craft
|
Closed shed construction - Tinny craft
|
Closed shed construction - Tinny craft
|
Closed shed construction - Tinny craft
|
Main plant area
|
Construction water tanks
|
Sheds under construction by Tinny craft
|
Sheds under construction by Tinny craft
|
33/11KV Substation
|
Substation 1
|
Switch yard Stage 2
|
Switch yard Stage 2
|
Main plant area_
|
Main plant area
|
NDCT area
|
Main plant area
|
Admin building area
|
NDCT Stage 2
|
Main plant Stage 2
|
Construction water tanks
|
Construction water tanks fencing
|
Coal Handling plant area
|
Admin building area
|
Construction power Substation 1
|
Construction power Substation 1
|
Stage 2 area
|
Stage 2 area
|
Stage 2 Main plant area
|
Non plant building area
|
Admin building area
|
FGL checking of Stage 2 Main plant area
|
Stage 2 - Carriage of disposal
|
Construction power Substation 2
|
FOPH and BOP areas
|
Main plant area under final grading
|
Construction water tanks under progress
|
Office building 2 -Construction under progress
|
Closed shed side view
|
Closed storage shed with racks
|
Shed under construction
|
Closed sheds
|
Construction power input (TSGENCO)
|
Construction power substation
|
NDCT Stage 1
|
Main plant stage 1
|
CHP area
|
CHP area
|
Construction water tanks
|
Construction power Substation 2
|
Stage 2 Switchyard
|
CHP area
|
Stage 1 NDCT
|
Stage 1 switchyard
|
NDCT STAGE 2
|
Construction power Substation 2
|
Construction power Substation 2
|
Foundation for construction water tanks
|
Construction water storage tanks
|
Stage 2 Switch yard area
|
Stage 2 NDCT area
|
Stage 2 NDCT area
|
Stage 2 NDCT area - Blasting preparation
|
Admin building area
|
Construction water - tank manhole
|
Construction water - tank top cover
|
Construction water - Tank foundation beams
|
Construction water - tank foundations
|
Distribution skid Transformer testing under progress
|
33/11KV Substation - Input supply works under programme
|
33/11KV Substation - Bay 2
|
33/11KV Substation - Bay 1
|
33/11KV Substation - 8 Pole structure
|
Stage 2 NDCT area
|
Stage 2 Main plant area
|
Stage 2 Main plant area
|
Stage 1 NDCT Area
|
Stage 1 Main plant area
|
Stage 1 Main plant area
|
FOPH area
|
CHP Area with hamlets in view
|
Stage 1 NDCT Area
|
Hamlet to be evacuated in CHP Area
|
Temple non excavated in CHP Area
|
Stage 1 NDCT & CW area
|
Stage 1 Heep of Excavated earth
|
CHP Area excavation
|
Construction water tank base erection
|
Construction water tank erection under progress
|
Construction water - tank foundations
|
Construction water - tank foundations
|
Stage 2 Switch yard area
|
Stage 2 CW Pump house area
|
Stage 1 Transformer yard area
|
Office building 3
|
Office building 1
|
Stage 2 NDCT area
|
Stage 2 Main plant area
|
Internal readiness of closed shed
|
4 Closed sheds in Yard 2
|
Stage 1 Chimney area
|
33KV Substation Bay 2
|
33 KV Substation _ Bay 1
|
Site office-1 Furniture to be supplied
|
Stores Shed
|
Construction Power sub station
|
Construction Water Tank
|
Stacked excavated earth
|
Office building 2 - Supply yet to start
|
Office building 3 - G K Roofings under completion
|
Office building 1 -
|
Stage 2 NDCT area
|
Mess building
|
Main plant area - mostly excavated
|
Non plant building excavation - Canteen area
|
FOPH area under excavation
|
FOPH area under excavation
|
Existing office
|
Construction water tank area
|
Storage sheds construction
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 2 Excavation works
|
Stage 2 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 2 Excavation works
|
Stage 2 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 2 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 2 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 2 Blasting related activities
|
Stage 2 Blasting related activities
|
Stage 2 Blasting related activities
|
Stage 2 Blasting related activities
|
Stage 2 Excavation works
|
Stage 2 Excavation works
|
Stage 1 Excavation works
|
Stage 1 Excavation works
|
Stage 1 - Excavation works
|
Stage 2 Excavation works
|
Stage 2 Excavation works
|
Stage 2 Excavation works
|
Stage-2 Leveling work
|
Stage-1 Leveling work
|
Stage 1 Leveling work
|
Contour survey under progress.Excavation stopped at site
|
Stage 1 Levelling works
|
Stage 1 Levelling works
|
Stage 1 Levelling works
|
Stage 1 Levelling works
|
Stage 1 Levelling works
|
Stage 1 Levelling works
|
Stage 2 Levelling works under progress
|
Stage 2 Levelling works under progress
|
Stage 2 Levelling works under progress
|
Stage 2 Levelling works under progress
|
Stage 2 Levelling works under progress
|
Stage 2 Levelling works under progress
|
Stage 2 Excavation and jungle cleaning works
|
Stage 1 Levelling & drilling works
|
Stage 1 Levelling & drilling works - Switchyard
|
Levelling & grading Stage 2 area
|
Levelling & grading Stage 2 area
|
Excavation under progress
|
Jungle cleaning - Levelling & grading
|
Taking spot levels - Levelling & grading
|
Contour survey - Levelling & Grading
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|