Home   

YADADRI TPS (5X800 MW)


Vac pumps unit 4

Unit 5 MVHV cable vault

Unit 4 LT cable vault 8.5m

Unit 4 debris filter

Unit 3 LT switchgear

U3&4.. Battery room... 17m slab and 8.5AR tiling b

U3&4 HT switchgear

Tf yard 4

Power house 1&2

Fire water tanks

Foam Pump house

Fire water PH

FGD Inlet & Outlet duct opening _ Material not avb

FGD #1 duct pedestals curing

FGD #1 duct foundations excavation

Esp CR 5

Esp cr 4 cable vault

Esp control room 5

DM plant

CST PH stage 2 and CST tank 5

Condenser tubes insertion unit 4

Compressor bldg stg 2

Clarified water PH

Chimneys and ESP 5

Chimney 1

Boiler 5 RHS and TP 35

Water system area

Overall BTG view

Plant from rear side

TP 11 & 31

Switchyard

Pipe rack 12

Power house 2

Fly ash silos

Fire water tanks

ESP control room 3

ESP 5

ESP 4

ESP 3

DM Plant tanks

CST tanks area

CPU regeneration bldg

CHP Stock pile

CHP Galleries

Chimney 1

CCR 2

Boiler 5

Boiler 5 LHS

Boiler 4

Boiler 4

Boiler 3

Boiler & Power house 3

Boiler 3

Boiler 5 RHS

NDCT 1(Right) & 2 (Left)

Pre Treatment plant channels

PT Chemical house

PT Clarifier 1

DM Plant Acid unloading tanks

Fuel oil tanks

NDCT 3

BOP Switchgear 2

ACW Pumps stage 1

TG rotor insertion

TG 1

Fuel oil pump house

FO Tanks

PT Plant

PT Clarifier

DM Clarifier

DM Clarifier 1

Overall

DM Plant

Chimney - Flue can with Borosilicate glass

Chimney 1 Borosilicate application

Vacuum pump house

Vph 1&2

Unit3 ESP TO ID FAN

Transformer yard 2

TG 2

Stage 2 transfer points

Stage 2 compressors

Stage 1 RHS

Service building stage 1(TSGENCo)

Primary water skid 2

PR2 PR3

PR1 PR7

Ndct 2

NDCT 2 Upper tie beam shuttering

Ndct 1

HPH 7a b

Hph 6a b

FOPH

Foam system

Fire water tanks

Fire water pump house

Esp cr3 (2)

Esp cr 3

Esp 3

Esp 2

Esp 1

DM Transfer PH

CWPH stage1

CST pUmp house stage 2

CST PH STAGE1

CPU Regen building

CPU 2

Condenser #2

CHP MCC 5

Chimney 2 Unit 3 Flue can ground assembly

Chimney 1 Flue can #2 primer application completed

Chimney 1 access winch

CER wall tiling

CCR OWS room with ducts

BOP Switchgear 1

Boiler 3 SCR Platforms

Boiler 2 RHS

Boiler 3

Boiler 2

Boiler 2 RHS

Boiler to ESP Duct #2

Boiler 2

Boiler 1

BCN 9AB

Aux boiler

Aux boiler MCC

AHP pipe rack

FGD Primary hydrocuclone feed storage tank B excav

FGD Duct Footing chiselling

FGD Duct #2 pedestals Civil works

Chimney 2 Flue can works #3

NDCT 5 racker columns

NDCT 3

Chimney 1 Flue can liner grinding works

Boiler 2 RHS

IPBD Alluminium welding test

UPS Battery charging

FOPH MCC

DM Plant Stream 1

Dm plant bulk acid storage tanks

DM Cascade aerator and clarifier 6 and 7

Clarifier 3,4,5

Clarifier 1 and 2, cascade aerator

Chimney 2 unit 3 flue can assy

RWPH pump floor

RWPH gates

RWPH battery room

PR 11 trestle erection

NDCT 5

NDCT 4

Clarified Water PH Pump floor

Clarified Water tank

Chimney 2 and 3

NDCT 5 Grillage columns

NDCT 5 Racker columns

SCR LHS Hopper Boiler 4

Chimney 2 unit 3 flue can assembly

Raw water pump house Stage 2 Pipe connections

5 units

TG 1

Ash slurry PH 1

CWPH NDCT Stage 1

SSF Stage 1

CWTP Stage 1

CPU Vessels Unit 1

Bottom ash hopper #2

Boiler 2

ESP 1 Rear ducting

ESP 1 front

ESP 2 rear ducting

ESP 2 front

Fuel oil tanks

Fire water tanks

DM vessels

DM tanks

DM plant Bulk acid storage tank

DM Plant

Boiler 1

Boiler 1

Switchyard

PT Clarifier

PT Plant Distribution pedestals

DM Aerator

PR 13

PR 2

PR 1

NDCT 1

MOT #2

LDO 2

LDO 1

ID duct unit 2

HFO 2

HFO 1

FOPH

ESP to ID Fan #1

ESP Control room 2

ESP 2

ESP 1

CW PH STage 1

CPU Vessels Unit 1

Chimney 1

CCR 1(Outside)

CCR 1 _Panel room

Boiler 1 RHS

Boiler 1 LHS

BCN 11ab

Ash slurry PH Stage 2

Station transformer 1

Boiler 1 RHS

NDCT 2

CHP conveyor galleries

Boiler 2

NDCT 3 & 4

Power block 3 LHS

PT Plant view

Boiler floor

Deaerator unit 2

AHP Silos

Boiler 2 insulation works

Coal piping unit 2

BOP Switchgear 1

Primary Water skid unit 2

Switchyard

TG 2

Transformer yard 2

CPU service vessels 2

HT switchgear 2

Bottom ash hopper 2

TP37

TP36

TP35

TP34

TP33

TP32

TP31

TP14

TP11

side stream filtration stage1

NDCT2

NDCT1

CWPH1

Boiler 1 to 5

PT storage tank

PT pump house

PR3

PR2

FOPH

Fire water tanks

ESP control room 3

CPU

Clarifier

CHP

ESP5

ESP4

ESP3

Boiler5 LHS

Boiler3 LHS

Boiler2 LHS

Boiler4 LHS

BCN9 & PR2

DM plant

DM tanks

Unit1 ESP TO CHIMNEY1 DUCT

Transformer yard1

SSF STAGE1

Ndct2

Ndct1

Esp2 to chimney duct

Esp control room3

Esp control room1

Cwph1

Chimney1 Fluecan can

BOP SWGR1

Boiler2 RHS

Boiler 1 LHS

BCN 10ab erection

BCN 9ab

Switchyard

Stage2

Stage1

Raw water pump house

Raw water MCC

Raw water MCC & Pump house

NDCT 4

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2 (1)

NDCT 1

Fuel oil PH

FO tanks

DM PLANT

CWPH STAGE1

Clarified water PH

Chemical house

PT Sludge sump

PT Clarifiers

PR 4

PR 3

NDCT 5 basin

NDCT 5 basin & Pedestals

NDCT 2 Grillage columns

NDCT 1 ring beam

Fire water tanks

Fire water pump house

DM tanks

DM Plant UFT tanks

DM Clarifiers & aerator

CPU Building

BCN and Chimney 1

NDCT2

NDCT1

Raw water pump house

Raw water pump house

Raw water reservoir

Raw water pump house

NDCT4

NDCT stage 1

FOPH

ESP5

ESP4

ESP3

ESP1

DM plant

DM Clarifiers

Clarified water pump house

Chemical house

Boiler5

Boiler4 LHS

Boiler3 RHS

Boiler3 LHS

Boiler2 RHS

Boiler1 LHS

Auxiliary Boiler

CPU Building

DM Plant

FOPH

DM Plant

Clarified Water Pump House

CCR-1

Aerator-1

NDCT-4

Raw Water Pump House

Unit#2 PHE

CHP Crusher & MCC

Aux Blr Dearator Chimney

Auxiliary boiler

NDCT#2

NDCT#1

ESP Control Room #3

ESP U#3

BCN 9AB

CCR Building #1

U#2 ID Fan to Chimney Duct

U#1 PA and FD Fan Foundations

VPH #1 and #2

ID Fan to Chimney Duct U#1

Flue Can Assembly U#1

ESP Control Room #1

ESP Unit-1

Boiler U#1, LHS

CWPH #1

Transformer Yard #1

DG Building #1

Station Transformer

Transformer Yard #2

Powerhouse #1 & #2

ESP U#2

ESP Control Room #2

Boiler#2 RHS

Powerhouse, CCR#2

Boiler#4 LHS

Vacuum Pump House #3

Vacuum Pump House #4

U#4 APH-2

ESP#4 CCR

ESP#5

Powerhouse, CCR#3

Boiler#5

Switchyard earthpit boring

Switchyard AC Kiosk fdn

TP 7 stool fixing

Clarifier 1 drain casting

PT Clarifier 2

PT Clarifier 2 Bridge erection

NDCT 2 grillage columns

NDCT 2 Ring beam 3rd lift

ACW line Unit 2 encasing

ACW line Unit 2

NDCT 5 Grillage column

NDCT 5 Basin floor preparation

NDCT 5 Basin floor

Boiler 4 DHT

NDCT 3 Racker column reinformcement work

NDCT 3 Racker columns work

NDCT 3 Grillage columns

NDCT 3 Racker columns works

NDCT 2 Ring beam 18th segment

Pipe rack 4 foundations

Pipe rack 5

NDCT 5 partition wall

NDCT 5 basin floor

NDCT 5 grillage columns

NDCT 3 Racker columns(2)

NDCT 3 pedestals

NDCT 3 Grillage structure

NDCT 2 Ring beam casting

NDCT 2 Racker columns

NDCT 2 Precast beam castings

NDCT 1 Ring beam

FOPH building(arrangement for FO by road handling)

FD PA fan fdns 1B

FD PA 2B

ESP 3 rear side

DM Transfer PH

DM tanks

CPU regeneration bldg

Boiler 1

BCN 8AB

UNIT2 FD & PA FAN FOUNDATIONS

UNIT1 FD & PA FAN FOUNDATIONS

TP37

TP35

TP34

TP33

TP32

TP31

TP15

TP14

TP13

TP12

TP11

ESP 5

ESP 4

ESP3

ESP2

ESP1

Boiler 5

Boiler 4

boiler 3

boiler 2

Boiler 1

Boiler1 RHS

BCN11

BCN10

U#1 ESP to ID Fan Ducting

Boiler U#1

TP-14 and TP-15

U#1 ESP to ID Fan Ducting

ESP Control Room #1

ESP U#1

U#1 FD Fans

Boiler U#2

U#1 FD Fan and PA Fan Rafts

CCR Building # 1

U#2 PA-APH Duct

U#2 APH

U#2 FD and PA Fan Rafts

TP-12

ESP Unit-2

Wagon tippler 3 & 4

Wagon tippler 1 & 2

Track hopper 2

Stock pile & Reclaimers

PT Clarifier Stage 2

PT Clarifier Stage 1

CHP Pent house 2

Overall view

Overall view

NDCT 1

Fire water pump house

ESP 1

DM Plant vessels

DM Plant MCC (Grade slab)

DM Plant mcc

DM tanks

DM Plant

DM plant RHS

Crusher house

CPU bldg

Clarifier 7

Clarifier 6

Clarified water tann

Clarified water tank

Clarified water PH

Chemical house

Boiler 1

Boiler 2 Drainable hydro test completed

Unit 2 IPBD foundations, CW line

CD bay structure erection

SP Bus ducts - Splice plates not matching

MV Switchgear - Switchgear not received

GT 2 long fire barrier wall

Battery room - Batteries not received

1BA switchgear positioned

ID Fan 5B fdn - Fan & Motor not received

ID Fan 5A - Motor pending frm Dec`21

ID Fan 4B - Motor pending from Dec`21

ID Fan 3A - Motor pending from Oct`21

ID Fan 2B - Motor not received - Pendng frm Oct`21

APH 1B - Bracings not received - Erection on Hold

Wagon tippler 3&4

VPH 2

VPH 1

ID Fan 5 - Motors not received (Pendng frm 9 month

Unit 2 condenser top view

Unit 1 Generator stator

Unit 1 condenser top view

Unit 3 LHS view

Unit 3 LHS view

BCN 10 trestle raft

Station transformer Bhopal Field Engr visit reqd

Transformer yard 1

Track hopper 2

Transfer point 14 & 15

Transfer point 12 & 13

Transfer point 37

Transfer point 35

Transfer point 34

Transfer point 33

Transfer point 32

Track hopper 1 MH1

Track hopper 2

Track hopper 1 Machine hatch 1

TG 2 PHE - Flanges not received

Heaters

Switchyard

RCERH 2

RCERH 1

PA Fan unit 2

NDCT 3 grillage columns casting

NDCT 3

NDCT 1

LP turbine unit 2

ID Fan 5 to Chimney 3 duct

ID Fan unit 2

ID Fan to Chimney 1 Duct

ID Fan 3_Motor not received

HP and IP turbine unit 2

ESP 5 OL Duct support

ESP 4 side insulation

ESP 4 OL duct support

ESP 3 OL duct

ESP 2

ESP 1

ESP Control room 1(Panels trays not rcvd)

ESP Control room 2 (Panels,cable traynot received)

ESP 5

ESP 4

ESP 3 CCR

ESP 2

DMCW unit2

DM Tanks

DM Plant (Vessels not received from BAP)

CW PH STAGE1

CCR 17m (Catwalk drawing pending)

Boiler 2 Internal DHT completed

Boiler 1

Boiler1 LHS (APH bracings supply critical)

Boiler 5 (Burner panel,OFA,wall blwr supply pendin

Boiler 4_Furnace tubes,safety vlvs,windbx supl pdg

Boiler 3_Corner sofa,furnace tubes not supplied

BCN 9AB

Auxiliary boiler

Ash slurry pump house

Air compressor bldg stage1

AHP MCC2

AHP COMPRESSOR BLDG STAGE1

Unit 1 TG

Unit 1 condenser

Transformer yard2

Transformer yard1

Switchyard

Power house 5

NDCT2

NDCT1

AIr compressor building stage 2

TP 37

TP 35

TP 15

TP 13

TP 12

TP 11

Boiler 5

Boiler 4

Boiler 2

Boiler 1

Wagon Tippler 3&4

VPH 1

Trestle fdn RTP 3

TP8

TP7 to TP8 bcn8ab

TP 21

Track Hopper 1 Machine Hatch concreting

RTP 1

RCERH2

RCERH 1

Pent house 21 foundation

FA towers location

BCN22 trestle foundation

BCN9 AB

BCN8 AB

BCN 22 Tunnel

BCN 22 tunnel

Bottom ash hopper #2

ASPH equipment fdn stg1

AHP Pipe pedestal area

Unit2 thrust block

Unit2 PHE

Unit2 PA FAN

Unit 2

Transformer yard2

Transformer yard1

Tp14and tp15

Tp13

TP12

TP 11

ST 1 ercn

PT clar 1&2

Portal crane

ID fan 1

FDfan2

FD PA FANS UNIT1

ESP 3

ESP 2

ESP 2 DUCT

ESP 2 CCR

ESP 1

ESP 1 DUCT

ESP 1 CCR

Dmp rhs tanks

Dmp mcc

Dmp grnd

Dmp grnd

Dmp east drns balance

DMCW PUMPS UNIT1

DM Tanks

Dm plnt

Dm plnt bldg

Dm plant UF Tanks DGT

DM Plant trenches

CWPH STAGE1

CST TANKS

CPU

Condenser2

Condenser 1

Chimney 1

Boiler2

Boiler1

Boiler1 RHS

Boiler1 LHS

Ash slurryph Stage1

APH UNIT2

APH UNIT1

Air compressor bldg stage1

FA Silo 2 EL @-0.300m slab

CPU building slab

NDCT 2 ring beam

NDCT 2 racker columns

NDCT 2 Grillage columns

Vacuum pump house 1

Vacuum PH2

Silo utility building

FA Silo Pipe pedestals

Ndct#2 shell 3rd lif concrete pouring

NDCT 3 Pedestal 3rd lift no 35&36 concrete pourin

NDCT 2 Racker column pouring started .(41B&42A)

FA silo5

FA silo

AHP Compressor house stg1

AHP Compressor house stg1(2)

AHP Compressor house for stg2

AWPH1

ASPH-1&2

ASPH 3&4

AHP MCC5

AHP MCC2

AHP MCC1 area

Vac PH 4

Vac PH 3

Boiler 3

RHS mills #2

PHE #2

Unit2 DMCW

Unit2 Condenser

Transformer yard2

Portable RODM

NDCT 3 basin segement casting

NDCT 3 basin segement casting

NDCT 2

NDCT 2 Racker column casting 40B 41A

NDCT 1 basin segment curing

ESP5

ESP2

ESP1

ESP CR5

ESP CR2

DMPLANT

DM TRANSFER PH

DM TRANSFER PH

DM TANKS AND FOPH

DM PLANT

CST PH STAGE1

CPU BLDG

PT Clarifier 1 & 2

Boiler5

Boiler4

boiler1

ACW pipe Unit 2 DM Inlet

Bottom ring header #2

Bottom ring header #2

Side stream filtration vessel foundation concrete_

Side stream filtration stage 2 Vessel foundation

Ndct#2 Raker column no 35B 36A

Ndct#1 pedestal no 23&24

NDCT 2 Ring beam

NDCT 2 Racker column number 38B&39A

NDCT 2 Racker column curing

NDCT 2 Pd47 & Pd48

NDCT 2 Grillage columns

NDCT 2 _raker column pouring

DM Plant _Degassed water storage tank

DM Clarifier 7

Aerator 2 raft

id fAN 2

ID Fan 1

ESP 5 inlet

ESP 2 inlet

ESP 2 OUTLET DUCT

ESP 1 DUCT AT OUTLET

ESP 1 CONTROL ROOM

Chimney 1

Boiler 5

Boiler 2

Boiler 1

NDCT 2

Chimney 3 270m achieved on 27 Mar 2022

CPU building slab concreting

Clarified water pump house operating floor concret

APH 5B module erection

APH 5B (Unit 5) erection

VPH 1&2

Unit2 FD PA FANS

TP15

TP14

TP13

TG1 CONDENSER

Stage1 air compressor bldg

Overall view

ESP2

ESP1

ESP Control room 2

Boiler2

Boiler2

Boiler1 - First pass

Boiler1 Outer view

Boiler1

Boiler1

Air Preheater 1

8.5m Unit 2 heaters

Condenser #2

Unit 2 17m BC bay

CCR1 0m grid 15 17

CCR1 0m

Transformer yard 2

Transformer yard 1

Transformer yard 5

Transformer yard 4

Transformer yard 3

TP 15

TP 14

TG Deck 4

TG 2 pedestals

TG 1

Switchyard

Switchyard control room

Stage1

ID fan 3

ID fan 2

ID Fan 1

ID 2

ESP 2 front, VPH 2

ID fan 4

ESP Control room 2

ESP 5

ESP 2 Duct supports

ESP 1 OL DUCT

CW line stage 2

CST PH1

Chimney 3

Boiler 2

Boiler2

Boiler 5

Boiler 1

Auxiliary boiler

Air Compressor bldg stage2

FOPH

DM tanks

DM tanks

DM Plant building

ESP 1 OL ducts

ID FAN 2A

Id fan to chimney duct unit1

ESP2

Boiler 1

Chimney 2 top beam erected

Yadadri overall

Track hopper 1 MH Sump

NDCT 2 ring beam

ESP 5

ESP 1 Outlet

ESP 1

ID to Chimney duct #1

Boiler 5

Boiler 5

Boiler 4

Boiler 4 bunker hopper

Boiler 4 WW hopper

Boiler 4

Boiler 2

Boiler 2

TP15

ID fan 4

ID fan 3

ID fan 2

ID Fan 1

ESP Controlroom 4

ESP control room 3

ESP control room 2

VPH 1

ESP 5

ESP 3

ESP 2 Duct support

ESP 1 duct

Chimney 3 (Unit #5)

Chimney 1(#1)

Boiler 2

Boiler 1

Boiler 1

BCN 9AB

AHP MCC 1

AHP compressor house stage 1

ESP 2 VPH 2

ESP 1

CW pump house stage 1

Chimney 1 @ 270mtrs

Boiler 1 spiral Water wall

Boiler 1

BOF to ESP Duct foundations #1(M row)

APH 1A

Unit 2

Unit 2 Hp heaters@17m BCbay

Thrust block #2

TG hall stage 1

Switchyard stage 1

Portal crane fdn #2

PH str A row unit#2

PH A row #1

MOT room #1

HP heaters #1

GT #1

DMCW pumps erection#2

DMCW PHE fdns #1

Cw stage 1 header pipes

CST pump house stage 1

Condenser plates#2

Condenser plate and hot well#2

Condenser hotwell #1

Compressor bldg stage 1

CCR1 DH bay

CCR1 17m structure

CCR 1 0m grid 11a-13

Bottom ring header #2

Boiler 2

Boiler 1 LHS

APH Duct and SCAPH #2

3.5m CCR1 grid 13_15 BC bay works

PT Plant Sludge sump

LDO tank fdn

HFO tank bitumen matting

HFO tank bitumen matting

Fuel oil road unloading arrangement by road

FOPH

FOPH(1

DM Trf PH

DM Tanks

DM Plant

Dm clarifier 7

Dm clarifier 6

Clarifier 5

Clarifier 4

Clarifier 2

Clarified water storage tank

Clarified water storage tank(1)

Chimney 2 & 3

Chimney 1 & 2

Boiler 2

TSTransco substation

TP 15

TP 14

TP 13 & 14

NDCT 2

NDCT 1

Esp 1 outlet

CW PH stage 1

CHP Stock pile

Boiler 1

Auxiliary Boiler

Aux Boiler ducting

Auxiliary Boiler

Aux boiler Chimney

Ash slurry pump house 1

APH 1A

AHP MCC 2

AHP compressor bldg stage 1

Winch for Chimney 2 Structure ercn

TP 14 Str

TG 5 deck staging

PT Clarifier 3 pipeline

NDCT 2 Ring beam shuttering works

NDCT 2 Racker column shuttering works

NDCT 2 basin segments reinforcement works

FA Silo 4 raft

ESP 3 inlet funnels

Clarified water PH pump floor

CW Pipe laying - CW Pump house Stage 1

NDCT 5 Pedestal bitumen coating

Wagon tippler 1 (-5)m slab

TP 33

TP 31

Crusher house 22

BCN 9AB trestle

BCN 8AB

Boiler 5

Boiler 5 Hangers and headers

Boiler 5 Seperator floor

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

NDCT 2

Switchyard control room

NDCT 2 segments drains

Chimneys

Clarifier - 4 Base slab concreting

BCN-2AB Segment 1 final lift slab concrete

NDCT-04 Basin floor Segment

CW Pit raft in unit-2 concrete casting

ASWP-SUMP STAGE-2 RAFT CONCRETE

FOPH slab concreting

Power House 4 slab at +29m (BC bay) concrete

TH1 MH1 raft

Silo 3 raft

TH2 Hopper 9 slab

Clarifier -2 Base slab concreting

ACW stage 01 slab concreting

Scaffolding training

Monthly Safety drive

NDCT 3 Pedestals shuttering

NDCT 3 Drain steel

NDCT 3 basin floor

NDCT 1 Raker column scaffolding

NDCT 1 Pond wall raft

NDCT 1 basin floor

NDCT 1 basin floor curing

Heaters #1

ERH 2 raft concreting

ERH#2 raft concrete

DM Clarifier 7 Shaft

Compresser house 3,4,5 slab final segment casting

clarifier no 1 sludge pit

Clarifier -2 Base slab concreting

Chimney 1 outer curing

ACW stage 01 slab concreting

PT Plant area

Clarified water pump house_Floor shuttering

Raw water pump house slab at +8.8m

Clarified water pump house Floor shuttering

NDCT 2 Raker Column 16B 17A

NDCT 1 basin

Switchyard control room first floor

NDCT 3 pedestal area backfilling

NDCT 3 basin

CW piping at Thrust block 1

TP15 Second tier frame of A1-A2 columns

TP 7 D1 column

Boiler 3 Pressure Parts erection

Boiler 2 area

Boiler-1 Pressure Part area

Unit-4 ID fan area

Unit-3 ID fan

Unit-2 ID fans

Unit-1 ID fan area

Stacker erection

PT Plant sludge pit area

DM Plant N pit area

FOPH

Fire water pump house

ESP-3 area

ESP-2 Rear side area

ESP-1 rear side area

DM Tanks

DM Tanks

DM Plant area

DM Clarifiers

CPU Building area

Clarifier5

Clarified water MCC

Clarified water PH

Chimneys

Cascade aerator

BCN 30

Auxiliary Boiler

Ash water pump house

Ash slurry ph 5

AHP compressor building stage2

AHP compressor building stage1

Track hopper 2

Water system area

Overall view

ESP 3

ESP 2

ESP 1

CW pit 1

CWPH stage1

CST STAGE1

Chimney3

Chimney2 @250Mtr

Chimney1

CCR area

Boiler4

Boiler2

Boiler2 area

Boiler1

Boiler1

Boiler 5

Boiler 5

Boiler 4

Boiler 3

Auxiliary boiler

Ash slurry area

APH4

APH 3 area

Air compressor building stage1

AHP compressor house stage2

track hopper 2 MH1 sump raft concrete_finishing

track hopper 2 MH1 sump raft concrete

Power House 1 slab at +35m (grid 1 to 3) concrete

Clarifier 7, first lift wall concrete

CCR 1 & 2 Slab at +8.5 m

C.W Pump House 1 slab concrete castin

BCN 2AB Segment 2 Raft concrete

BCN 36AB raft concrete

Track Hopper -2 wall 2nd stage concrete work

Station transformer-1 rail track 1st stage concret

Service water tank bottom slab concrete

NDCT-05 Ring raft segment number 19th segment conc

FOPH slab casting

ESP CR 2 slab 8.5 m casting

DM plant Roof Slab Concreting

CW pipe line encasing casting

CRH-1 Bolt lift pedestal concrete casting

Compressor House Stage 2 Middle 1/3 Slab casting

Clarifier 6, bottom Slab concrete

Clarified water tank slab concrete casting

Channel 04 Wall concreting started in CWPH #2

BCN-2AB Segment 01 Raft concrete casting

Ash water pump house stage 1 sump raft concrete

Water system

Stock pile

Stage 2 overview

NDCT Stage 1 CW PH

Bottom ash hopper #4 pedestal shuttering

U#4 Bottom ash hopper raft concreting

Chimney 2 - third segment concreting started

E11a footing casted...CCR 01

Chimney 1(#1) reinforcement placement

TG raft #3 under curing

D11a footing casting in CCR 1

TG raft #3 concreting

Auxiliary boiler chimney raft casted

Auxiliary boiler chimney

Auxiliary boiler footings

Chimney 1 reinforcement placement

ESP #3

ESP 2 from rear side

ESP 1 AB Pass

Boiler #1

ID Duct foundations #3

ID Duct #1 foundations near ESP CD Pass

ID Duct #1 foundations near chimney

GT #3 grade slab - Reinforcement placement

GT #1 shuttering

Chimney 2 Concreting - second segment raft

Chimney 3 Shuttering

ESP Control room #3

ESP Control room #1

Compressor building #1

Boiler #4 Column erection start

Boiler #2 Column erection start/pooja

CHP Civil - Pooja by Powermech

Power house #2 A19 pedestal casting

Chimney 2(#3 & #4) raft secon segment concreting s

ESP #2 column encasing - shuttering

CCR #3 & #4 pedestal casting

Power house #2 A19 raft concreting

Chimney 1(#1) reinforcement placement

Chimney 3(#5) raft first segment concreting

Power house #2 Structural erection

Power house#5 Civil works

Power house #4 (Submerged reinforcement due torain

Power house #2 (Incl TG Raft)

ID Duct foundations #5

ESP control room #5

ESP 5 foundations

ESP #4

ESP #2

Unit #5 Control room

Chimney 3 - Reinforcement works

Chimney 1 (#1 & #2)

Common control room #3 & #4

Bowl mills #4 reinforcement work

Boiler #5 foundations

Boiler #4 Foundations

Bottom ash hopper #4

Bottom ash hopper #2 excavation

Auxiliary boiler civil works

Chimney 2(#3) raft first segment casted..curing

Power house#1 Roof truss erection#1

Chimney 2(#3 & #4) raft first segment concreting s

ID fan 1B concreting (335/361 CuM poured)

ID fan 1B concreting started(361CuM)

Esp#3 D pass

Boiler #3 erection

Boiler #1 LHS MBL erection

Generator transformer #1 foundation works

ESP #2 AB pass

ESP#1AB pass

Boiler#1 erection

CEP #1 wall first lift casted

TG column #1 hydraulic jack fixed

Bottom ash hopper #4 reinforcement works

Power house #5

ID Duct #5

ESP Control room #5

ESP #5

Boiler #5

Chimney 3(#5 Single flue)

Power house#2 reinforcement works

CW pump house stage 1 excavation works

CW pump house stage 1

Power house #3

Chimney 1(#1) water accumulation due to rains

TG 4 reinforcement submerged in water due to rains

ID duct foundations #3

ID duct foundation #1

S418 road works

Auxiliary boiler

Chimney #3

CEP #1 reinforcement works

TG 4 raft reinforcement placement

Truss R2 erection in power house#1

Chimney 3(#5 single flue) reinforcement placement

ID duct foundations#1

Auxiliary boiler foundations

TG column #1 slip form assembly

ID duct foundations#5

Boiler 1

Transformer yard #1 GT & UT foundations

TG 4 reinforcement works

S418 road compaction u/p

Power house structure Column erection

#1 Power house structure Crane girder erection

Power house #2

ID Fan foundation shuttering

ID Duct foundations #5

ESP CR#5

ESP CR #3

ESP #5 earth mat works

ESP #4 Mechanical

ESP #2 erection

U#5 Control room pedestals

Compressor house Stage 1 backfilling

Chimney 3 long view

Chimney 3 shuttering

Chimney 2 (#3 & #4) bar bending works

CCR #3 & #4

Bowl mill #4

Boiler 5

Boiler 4 foundations

Bottom ash hopper PCC #4

Aux Boiler foundation

TG 4 shuttering works

ID Fan shuttering works

ESP #5 earth mat works

TG 5 PCC for raft (submerged under water)

TG Raft 3 Bar bending and checking

TG Raft 3 Bar bending and checking

Power house #5 pedestals

Power house 5 PCC

Power house 4 pedestals & TG Raft PCC

Power house #3 pedestals

Power house 2 Structure erection

Power house 2 pedestals

Power house 1 columns erection

Power house 1 pedestals

NDCT 2 excavation works

Generator transformer #5 foundation

ID duct foundations #3

ID Fan 1 B bar bending works

ID Duct #1 foundations

ESP Control room #5 plinth beam

ESP 5 pedestals

ESP #3 erection

ESP #3 AB Pass Earth mat works

ESP #2 erection

CW pump house 2 excavation

CW pump house 1 excavation

CW Pipeline excavation stage 1

Concrete cube quality tests

Chimney 3(#5 Single flue) Bar bending works

Chimney 2 (#3 & #4) bar bending works

Chimney 1(#1 & #2) Bar bending

CCR #3 & #4 pedestals

CCR 1 & 2 Pedestals

CCR 1 & 2 Pedestals

Boiler 5 pedestals

Boiler 3 Erected columns

Boiler 3 Mill foundations Bar bending

Boiler 2 Pedestals

Auxiliary boiler bar bending

ESP 3

TG#5 PCC completed

Chimney 3(#5 single flue) reinforcement placement

Auxiliary boiler foundations

Power house #2

Power house #1

ESP #4

ESP #2

ESP 5 foundatiions

Boiler #5 Foundations

Chimney 3

Chimney 2 (#3 & #4)

Chimney 1

Power house #3

Power house #4 excavation works

Power house #1

ESP #4

ESP #3

ESP #1

Boiler #1

ESP#1

Chimney 3(#5 single flue) reinforcement placement

ID duct footing#1

Compressor building footings

Chimney 2(#3 & #4) reinforcement placement

ID duct foundations#1

PCC works of Aux Boiler started

Chimney 3(#5 single flue) reinforcement placement

Close view of chimney reinforcement

Chimney 2(#3 & #4) reinforcement placement

ESP #4 intermediate frame erection

ESP #4 intermediate frame welding

Chimney 2(#3 & #4) reinforcement placement

TG raft #3 reinforcement

Boiler#5 foundations

Power house#3 civil works

Power house#1 civil works

ID duct foundations#1 concreting under progress

Chimney 3(#5 single flue) reinforcement placement

Chimney 3(#5 single flue) top mat reinforcement

ID duct foundations#1

Power house #3 fabrication works

UT #1b reinforcement for pedestal

GT#1b third lift staging

GT #1A pedestal third lift staging

Chimney 3(#5 single flue) reinforcement placement

Concreting of Power house #2 foundations

ID duct foundations#1

Sanitisation of common areas

Power house #5 foundations shuttering

Social distancing during temperature check -mrng

TG Raft #3 bar placement

Boiler #5 pedestals

ESP #5 pedestals completed

CCR 1 foundation reinforcement

Chimney 2 (#3 & #4) reinforcement fixing

ESP #2 casing wall erection

ESP #4 frame erection

Chimney 1 (#1 & #2) reinforcement placement

Chimney 1(#1) excavation

Power house #2

ID Duct support area #5

Generator transformer #5 Civil works

Generator transformer #1 Civil works

ESP #5 control room

ESP #5 foundations

ESP #4

ESP #3

ESP #1

ESP 2 Pass D

Compressor house #1

Chimney 2 (#3 & #4)

Chimney 3(#5 Single flue) Excavation

Chimney 1 (#1 & #2) Excavation

Boiler #3

Boiler #1

Boiler #5 Foundations

Boiler #1

Chimney 1 (#1 & #2) Excavation

ESP #4 erection

ESP #3 erection

ESP #2 erection

ESP #1 View from LHS

ESP #1

Boiler #1 erection

TG Raft#3 Reinforcement - After rains on 06 Mar 20

TG Raft #2 reinforcement works

TG Raft #1 Concreting completed

Chimney 3(#5 Single flue) PCC completed

Chimney 2 (#3 & #4)

Power house #5 excavation

Generator transformer #5 Civil works

Generator transformer #1 Civil works

Power house #4

Power house #3

Control room #5 excavation

CCR #3 & #4

CCR #1 & #2

Boiler #5 Foundations

Boiler #4 foundations

Boiler #3 foundations

Boiler #2 foundations

TG raft #1 concreting started

ESP #3

S418 road compaction u/p

Generator transformer #1 Civil works

Compressor house #1

CCR 3 & 4

Boiler #3

Power house #3

ESP#1 casing wall erection

TG raft 2 reinforcement works

TG raft 1

Power house #4

Power house #3

Power house #2

CW Pipe excavation #5

ESP Control room #3

TG raft area #5

TG raft area 4(PCC submerged under seepage water)

TG Raft area #3

ESP #4

ESP #3

ESP #2

ESP #1

Boiler #5

Boiler #3 foundations

Boiler #2 LHS Foundations

Boiler #1 erection

Power house #1

CCR #1 & #2

Chimney 3(#5 Single flue) Excavation

ESP Control room #3

ESP Control room #5

Generator transformer #5 Civil works

Generator transformer #1 Civil works

ESP #5

ID Duct support area #5

ESP #5

CCR #3 & #4

Boiler 4

Boiler #3

Power house #3

Power house #4

ESP #3

ESP #2 erection

ESP #1 erection

Boiler 1 erection

ESP#1 Intermediate frame erection

TG Raft #5 excavation

TG Raft #4 excavation

Power house #3 foundations and TG Deck excavation

Power house #2 foundations

UT 3a 3b

Control room #5 excavation

ESP #5 foundations

ESP Control room #3

ESP #1 erection

ESP Control room #5

ESP #4 Intermediate frame assy

CCR #3 & #4

Boiler #5 Foundations

Boiler #4

Chimney 3(#5 Single flue) Excavation

ESP #4

ESP #3

ESP #2

UT - 3a 3b & Fire barrier civil works

Power house #5

Power house #3

Power house #2

Power house #1 foundations

TG Raft #2

TG Raft #1

NDCT #2 Drilling works

NDCT #1 Drilling works

Unit#1 view from Transformer yard

GT #3 placed

Generator transformer #5 Civil works

Generator transformer #1 Civil works

CCR #3 & #4

CCR #1 & #2

Boiler #5

Boiler #4

Boiler #3 LHS

Boiler #3 Front side

Boiler #2

Boiler #2

Fabrication yard #2 & #5

SAW welding - column fabrication

ESP #5 foundations

ESP #4

ESP #3

ESP #2

ESP #1

TG raft PCC #1

Generator transformer #5

GT #3 Fire barrier wall

ESP #5 foundations

ESP #4

ESP #3 erection

ESP #2 assy

ESP #2

ESP #1 Intermediate frame assy

ESP #1 erection

ESP#1

ESP#2 D pass

Concreting in Boiler#4

ESP#1 erection

Power house #4

Gen Transformer #5

ESP #4

ESP #2

Boiler #5

Boiler #4

Boiler #3

Boiler #2

Boiler #1

Boiler #1 erection started

Generator Transformer foundation readiness

Power house #4

Power house #2

Power house #1

ESP #5

ESP #4

ESP #3

ESP #2

CCR Unit #3 & #4

Boiler #5

Boiler #4

Boiler #4

Boiler #3

Boiler #2

ESP#4 column erection started

Structure fabrication works

GT #3

ESP #5

ESP #4

ESP #2 backfilling works

ESP #3 Control room works

ESP #1

Boiler #5

Boiler #2

ESP #1

Power house 2

Power house 2

Power house 1

ESP 5 CD Pass

ESP 5 AB Pass

ESP 4 D Pass

ESP 4 C Pass

ESP 4 AB Pass

ESP 3 D Pass

ESP 3 C Pass

ESP 3 AB Pass

ESP 2 D Pass

ESP 2 C Pass

ESP 2 AB Pass

ESP 1 CD Pass

CCR Stage 1

Boiler 5

Boiler 4 RHS

Boiler 4 LHS

Boiler 3

Boiler 3 LHS

Boiler 2

Boiler 1 RHS

Boiler 1 LHS

Power house #4

ESP#4

ESP #5

Boiler #5

Blasting - Compressor house #1

GT #3 area

GT Rail track

Power house #3

ESP #3

Boiler #3

Power house #1

ESP #1

Boiler #1

Boiler#2

ESP#2

Boiler#2

Boiler#2

Boiler#2

Boiler#2

Boiler#2

Boiler#2

ESP#2

ESP#2

ESP#2

ESP#2

ESP#1

ESP#2 column erection started

Boiler#4

ESP#4

ESP#1 AB pass

ESP#1 erection

ESP#1

GT rail cum road bar placement

GT pedestal post rail placement

ESP#2 AB pass

ESP#2 CD pass

Boiler 2

Power house #2

Boiler #1 rear side

ESP#1 AB pass earthmat works

ESP#1 CD pass

Boiler #1

Boiler#5

ESP#5

Boiler #3

ESP#3

ESP#1

Boiler #1

Boiler #4

Power house #2

ESP #2

Boiler #2

Boiler #2

Boiler #1 front

Boiler #1

ESP#1 foundations

Boiler #3

ESP #3 rafts

ESP #3 bar bending works

Boiler #1 Main column foundations

Boiler #1

ESP#1

ESP #5

ESP #3

Boiler #5

Boiler #3

Boiler #1

Unit #3 fabrication works

Unit #1 & #4 Fabrication Gantry crane erection u/p

ESP #1 column erection started

GT 3C bar placement

GT 3A raft

Thrust block #3

Boiler #3

Boiler #4

Power house #4

Power house #5

Boiler #5

ESP #3

Boiler #3

ESP #1

Boiler #1

Power house #2

ESP #2

Boiler #4

Boiler #2

ESP Control room #3

GT #3

ESP #3

ESP #2

ESP #1

Boiler #3

Boiler #1

ESP#4

Boiler#4

ESP#1 AB pass

Boiler #1

ESP#1 CD pass

ESP#2 AB pass

ESP#2 CD pass

Boiler 2 RHS

ESP#3 control room excavation

Boiler #3

ESP#3

Boiler#4

ESP#4 rear side

ESP#4 front side

ESP#5

Power house #3

ESP#3

Boiler #3

Power house #4

Power house #4

ESP #4

ESP #4

ESP #4

Boiler #4

Boiler #4

Boiler #4

ESP#3

Boiler #3

Power house #2

ESP #2

ESP #2

ESP #2

Boiler #2

Boiler #1

Boiler #1

ESP#1

Power house #4

Boiler#4

Boiler #4

Boiler #4

Power house #2

Power house #2

ESP #3

Boiler #3

ESP #1

Boiler #1

Boiler #1

ESP #1 Pedestals_Bitumen painted

Power house #1

Power house #5

Power house #4

Power house #3

Power house #2

ESP #5

ESP #5

ESP #4

ESP #4

ESP #3

ESP #3

ESP #3

ESP #3

ESP #2

ESP #2

ESP #2

2 Nos 65 HP pumps deployed for dewatering

Unit #5 control room excavation

Area filled with dewatering of excavation areas

Bar bending works #3

Bar bending works #3

Boiler #5

Boiler #5

Boiler #5

Boiler #4

Boiler #4

Boiler #4

Boiler #3

Boiler #3

Boiler #3

Boiler #3

Boiler #2

Boiler #2

Boiler #2

ESP#1

ESP#1

ESP#1

ESP#1

ESP#1

Boiler #1

Boiler #1

ESP #3

ESP #3

ESP #3

ESP #2

ESP #1

Boiler #3

Boiler #3

Boiler #3

Boiler #2

Boiler #1

Boiler #3

Boiler #3

Boiler #3

ESP#3

ESP#3

ESP#3

ESP#5

ESP#5

ESP#5

ESP#5

Boiler#5

Boiler#5

Boiler#5

Boiler #1

Boiler #1

Boiler #1

Boiler #1

Boiler #1

ESP#1

ESP#1

ESP#4

ESP#4

Boiler#4

Boiler#4

Fabrication yard #1 #4

ESP #5

ESP #5

ESP #5

ESP #4

ESP #4

ESP #4

ESP #3

ESP #3

ESP #2 bar bending works

ESP #2

ESP #2

ESP #2

ESP #2

ESP #1

ESP #1

ESP #1

Boiler #5

Boiler #5

Boiler #4

Boiler #4

Boiler #3 bar bending works

Boiler #3

Boiler #2

Boiler #2

Boiler #1

Boiler #2

Boiler #1

Boiler #1

Boiler #2

ESP #2

ESP #4

Boiler #4

ESP #3

ESP #3

ESP #3

Boiler #3

Boiler #3

ESP#1

ESP#1

ESP#1

ESP#1

ESP#1

Boiler #1

Boiler #1

Boiler #2

Boiler #2

ESP #4

Boiler #4

ESP #5

ESP #5

ESP #3

ESP #3

ESP #3

ESP #1

ESP #1

ESP #1

ESP #1

Boiler #5

Boiler #5

Boiler #3

Boiler #3

Boiler #3

Boiler #1

Boiler #1

Boiler #1

Storage yard from CCTV view

ESP #5 Water logged

Storage sheds

Storage sheds

Power house #1

ESP #5

ESP #5

ESP #4

ESP #3

ESP #2

ESP #1

Boiler #5

Boiler #4

Boiler #4

Boiler #3

Boiler #2

Boiler #1

Boiler #1

Boiler #1

Power house #3

Power house #3

ESP #5

ESP #4

ESP #4

ESP #4

ESP #3

ESP #2

ESP #2

ESP #2

ESP #2

ESP #1

ESP #1

ESP #1

Boiler #5

Boiler #4

Boiler #4

Boiler #3

Boiler #3

Boiler #2

Boiler #2

Boiler #1

Boiler #1

Power house #1 excavation

ESP #5

ESP #5

ESP #4

ESP #3

ESP #3

ESP #2 F8 Re-bar placement

ESP #1

ESP #1

ESP #1

ESP #1

Boiler #5

Boiler #4

Boiler #4

Boiler #3

Boiler #2

Boiler #1

Boiler #1

ESP #2

ESP #2

ESP #2

ESP #2

MPH 2

MPH 1

ESP 5

ESP 5

ESP 4

ESP 4

ESP 3

ESP 3

ESP 3

ESP 2

ESP 2

ESP 1

Boiler 4

Boiler 4

Boiler #3

Boiler #2

Boiler #2

Boiler #2

Boiler #1

Boiler #1

Boiler 1

Power house #4

ESP #5

ESP #4

ESP #2

ESP #2

ESP #2

ESP #2

ESP #2

ESP #2

ESP #2

ESP #2

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #4

Boiler #5

Boiler #2

Boiler #2

Boiler #2

Boiler #2

Boiler #2

Boiler #2

Boiler #2

Boiler #2

Boiler #2

Boiler #4

Boiler #4

Power house #1

ESP #1

Boiler #1

Power house #2

Power house #1

ESP #5

ESP #4

ESP #3

ESP #3

ESP #2

ESP #2

ESP #1

ESP #5

Boiler#5

Boiler#5

Boiler#4

Boiler #4

Boiler #3

Boiler #3

Boiler #3

Boiler #2

Boiler #1

Boiler #1

Power house #4

Power house #2 - Drilling for blasting

Power house #2

Power house #1

ESP #2 F8 Raft RCC works

ESP #2

ESP #1

Boiler #2

Boiler #1

Boiler #1

ESP #1

Boiler #2

Boiler #1

ESP#2

Explosive vehicles behind chimney area

Boiler#5

ESP#5

Boiler#4

ESP#4

ESP#3

Boiler #3

Boiler #3

Boiler #1

Boiler #1

Boiler #1

ID Duct area#2

ESP#2

Boiler 2

Unit-2 ESP

M) Excavation@ Boiler#5

L) Excavation in Boiler#2

k) Boiler#1

Unit-4 ESP

Unit-4 Boiler

Unit-2 Boiler

d) 33KV line provided by customer.

a) 33 KV/11 KV substation area

e) M./s RVPR Batching Plant.

f) M/s Kanwar Batching Plant.

j) Material placed in open storage yard.

c) Inside view of closed storage view

b) Closed storage shed

i) ID Duct support Unit#1

h) ESP#2- RCC work under progress.

g) ESP#1- RCC work under progress.

ID Duct support area #2

ESP #5

ESP #3

ESP #3

ESP #1

ESP #2

ESP #2

ESP #1

ESP #1

Boiler#5

Boiler#4

Boiler#3

Boiler #5

Boiler#1

Boiler #2

Boiler #2

Boiler #2

Boiler #1

Boiler #1

Batching plant complex

ID Duct support area #2

ESP #2

Boiler #4

Boiler #2

Boiler #1

Boiler #1

Boiler #1

Boiler #1

Boiler #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP#2 for PCC

ESP#2 Excavation

ESP #2

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

ESP #1

Quality lab_Kanwar

Batching plant_RVPR

Batching plant_Kanwar

ESP #2

ESP #1

Boiler 2 ESP 2

Boiler 2

Boiler 2

Boiler 1

ESP #3

ESP #4

ESP #4

ID Duct support area #2

ESP #2

ESP #1

ESP #1 water seepage

ESP #1

Boiler #1 Drilling works for blasting

Boiler #1 Drilling works for blasting

Boiler #3 area

ESP #2 area

ESP#1 area

BOF # 1area

BOF #1 area

Switchyard

NDCT Stage 2

NDCT Stage 1

FOPH area

CHP area

CHP area

Canteen area

Admin area

Admin area

Storage sheds

Storage sheds construction

Steel

Stacked material

CW Pipes storage

Substation1

CHP area

CHP area

CHP area

CHP Area

Closed shed construction - Tinny craft

Closed shed construction - Tinny craft

Closed shed construction - Tinny craft

Closed shed construction - Tinny craft

Closed shed construction - Tinny craft

Closed shed construction - Tinny craft

Main plant area

Construction water tanks

Sheds under construction by Tinny craft

Sheds under construction by Tinny craft

33/11KV Substation

Substation 1

Switch yard Stage 2

Switch yard Stage 2

Main plant area_

Main plant area

NDCT area

Main plant area

Admin building area

NDCT Stage 2

Main plant Stage 2

Construction water tanks

Construction water tanks fencing

Coal Handling plant area

Admin building area

Construction power Substation 1

Construction power Substation 1

Stage 2 area

Stage 2 area

Stage 2 Main plant area

Non plant building area

Admin building area

FGL checking of Stage 2 Main plant area

Stage 2 - Carriage of disposal

Construction power Substation 2

FOPH and BOP areas

Main plant area under final grading

Construction water tanks under progress

Office building 2 -Construction under progress

Closed shed side view

Closed storage shed with racks

Shed under construction

Closed sheds

Construction power input (TSGENCO)

Construction power substation

NDCT Stage 1

Main plant stage 1

CHP area

CHP area

Construction water tanks

Construction power Substation 2

Stage 2 Switchyard

CHP area

Stage 1 NDCT

Stage 1 switchyard

NDCT STAGE 2

Construction power Substation 2

Construction power Substation 2

Foundation for construction water tanks

Construction water storage tanks

Stage 2 Switch yard area

Stage 2 NDCT area

Stage 2 NDCT area

Stage 2 NDCT area - Blasting preparation

Admin building area

Construction water - tank manhole

Construction water - tank top cover

Construction water - Tank foundation beams

Construction water - tank foundations

Distribution skid Transformer testing under progress

33/11KV Substation - Input supply works under programme

33/11KV Substation - Bay 2

33/11KV Substation - Bay 1

33/11KV Substation - 8 Pole structure

Stage 2 NDCT area

Stage 2 Main plant area

Stage 2 Main plant area

Stage 1 NDCT Area

Stage 1 Main plant area

Stage 1 Main plant area

FOPH area

CHP Area with hamlets in view

Stage 1 NDCT Area

Hamlet to be evacuated in CHP Area

Temple non excavated in CHP Area

Stage 1 NDCT & CW area

Stage 1 Heep of Excavated earth

CHP Area excavation

Construction water tank base erection

Construction water tank erection under progress

Construction water - tank foundations

Construction water - tank foundations

Stage 2 Switch yard area

Stage 2 CW Pump house area

Stage 1 Transformer yard area

Office building 3

Office building 1

Stage 2 NDCT area

Stage 2 Main plant area

Internal readiness of closed shed

4 Closed sheds in Yard 2

Stage 1 Chimney area

33KV Substation Bay 2

33 KV Substation _ Bay 1

Site office-1 Furniture to be supplied

Stores Shed

Construction Power sub station

Construction Water Tank

Stacked excavated earth

Office building 2 - Supply yet to start

Office building 3 - G K Roofings under completion

Office building 1 -

Stage 2 NDCT area

Mess building

Main plant area - mostly excavated

Non plant building excavation - Canteen area

FOPH area under excavation

FOPH area under excavation

Existing office

Construction water tank area

Storage sheds construction

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 2 Excavation works

Stage 2 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 2 Excavation works

Stage 2 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 2 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 2 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 2 Blasting related activities

Stage 2 Blasting related activities

Stage 2 Blasting related activities

Stage 2 Blasting related activities

Stage 2 Excavation works

Stage 2 Excavation works

Stage 1 Excavation works

Stage 1 Excavation works

Stage 1 - Excavation works

Stage 2 Excavation works

Stage 2 Excavation works

Stage 2 Excavation works

Stage-2 Leveling work

Stage-1 Leveling work

Stage 1 Leveling work

Contour survey under progress.Excavation stopped at site

Stage 1 Levelling works

Stage 1 Levelling works

Stage 1 Levelling works

Stage 1 Levelling works

Stage 1 Levelling works

Stage 1 Levelling works

Stage 2 Levelling works under progress

Stage 2 Levelling works under progress

Stage 2 Levelling works under progress

Stage 2 Levelling works under progress

Stage 2 Levelling works under progress

Stage 2 Levelling works under progress

Stage 2 Excavation and jungle cleaning works

Stage 1 Levelling & drilling works

Stage 1 Levelling & drilling works - Switchyard

Levelling & grading Stage 2 area

Levelling & grading Stage 2 area

Excavation under progress

Jungle cleaning - Levelling & grading

Taking spot levels - Levelling & grading

Contour survey - Levelling & Grading