TRANSFORMER YARD
|
STG
|
SERVICE BUILDING
|
RWPH AND MCC
|
ROMB
|
IDCT
|
IDCT
|
HRSG
|
GTG
|
GBC
|
FIRE STATION
|
ETP
|
DG BUILDING
|
CWTP
|
CWPH
|
CWPH
|
CW OZONE
|
BFP BUILDING
|
AC PLANT & MCC
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Raw Water Pump House MCC
|
RW Ozone Building
|
Raw Water Pump House
|
ETP Chamber
|
DG Building
|
Transformer Yard
|
AC Plant
|
RODM Building
|
CWPH Building
|
GBC Building
|
Cooling Tower
|
Compressor Building
|
Fire station building
|
Cooling Tower
|
Gas Turbine area
|
GBC Building
|
Gas Storage Shed
|
RODM Building
|
STG Building
|
BFP Building
|
Effluent Treatment Plant
|
RODM Building
|
Cooling Tower
|
Cooling Water Treatment Plant
|
Gas Conditioning Skid
|
Diesel engine hydrant pump 4 hrs. trial run starte
|
Fire station building lintel beam reinforcement i/
|
Steam turbine bearing housing cleaning i/p
|
CW Ozone MCC building plastering work i/p
|
BFP Building outer wall plastering i/p
|
CW Ozone MCC panel all 18 panels erected
|
CW Ozone MCC building plastering work i/p
|
BFP Building brickwork i/p
|
STG final swing check completed
|
Acid resistant paint final coating in CW Ozone battery room
|
CW Ozone PMCC panels shifting & erection i/p
|
IDCT Cell 4 bitumen painting i/p
|
CWPH internal plastering i/p
|
BFP Building brickwork i/p
|
CWPH MCC Building plastering i/p
|
BFP Building brickwork i/p
|
CW Ozone MCC Building plastering i/p
|
CW Ozone building internal plastering i/p
|
STG LP-Generator coupling bolts fixing i/p
|
Fire station building tie beam RCC i/p
|
CWPH building internal plastering i/p
|
CWPH Building destaging work i/p
|
BFP Building staging work i/p
|
CW Ozone MCC building parapet wall plastering i/p
|
Fire station building column concreting i/p
|
RWR Chamber-2 balance wall shuttering works i/p
|
Drain wall shuttering i/p near CWPH MCC room
|
HP LP coupling hole dia measurement & hole fixing
|
CW Ozone building brickwork i/p
|
Fire station building lintel beam reinforcement
|
DE hydrant pump alignment & coupling completed
|
Destaging work i/p north of CWPH building
|
IDCT west plinth protection work i/p
|
Fire station building tie beam reinforcement i/p
|
CW Ozone building drain wall deshuttering i/p
|
RW Ozone building parapet wall RCC i/p
|
DMCW hoist load testing i/p
|
STG LP Generator coupling reaming honing i/p
|
BFP Building shuttering i/p for plaster work
|
CW Ozone MCC Building grade slab RCC completed
|
Fire station building tie beam shuttering i/p
|
CWPH Brickwork i/p
|
CW Ozone pumps grouting work i/p
|
BFP Building brickwork i/p
|
Fire station building lintel shuttering work i/p
|
IDCT Cell 4 bitumen painting i/p
|
BFP A pump seal body replacement work i/p
|
Plastering work i/p in CWPH
|
CW Ozone building pumps grouting u/p
|
Fire station building column shuttering work i/p
|
HP to LP ,14/14 coupling reaming honing completed
|
Transformer yard rail road plate fixing i/p
|
DV Shed brickwork i/p near BFP Building
|
Plastering work i/p in CWPH
|
Fire station building lintel shuttering work i/p
|
DV Shed brickwork i/p near BFP Building
|
BFP Building brickwork i/p
|
Plastering work i/p in CWPH
|
CW Ozone building brickwork i/p
|
Fire station building column shuttering work i/p
|
DG Hydrant pump reassembly i/p
|
RWPH brickwork i/p
|
CW Ozone MCC building wall & roof putty completed
|
BFP Building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building column shuttering work i/p
|
Site view from top
|
Dosing & chiller pumps alignment in Ozone building
|
Dosing & chiller pumps alignment in Ozone building
|
CW Ozone building balance drainwall shuttering i/p
|
DV Shed brickwork i/p near BFP Building
|
BFP Building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building column shuttering work i/p
|
RWR Chamber-2 balance wall shuttering works i/p
|
BFP Building brickwork i/p
|
DV Shed brickwork i/p near BFP Building
|
CWPH MCC building painting i/p
|
Fire station building column shuttering work i/p
|
LP Turbine to generator coupling & CRO i/p
|
RWR Chamber-2 balance wall reinforcement works i/p
|
BFP Building sunshade work i/p
|
Plastering work i/p in CWPH
|
Fire station building column shuttering work i/p
|
RWR Chamber-2 balance wall reinforcement works i/p
|
DV Shed raft shuttering work i/p
|
CW Ozone building brickwork i/p
|
CWPH plastering work i/p
|
Fire station building plinth beam reinforcement i/
|
BFP Building brickwork i/p
|
CW Ozone building brickwork i/p
|
CWPH destaging work i/p
|
Fire station building plinth beam concreting i/p
|
HP IP to LP coupled runout checking i/p
|
STG HP IP to LP temporary coupling & CRO checking
|
RWPH brickwork i/p
|
STG Building A row sunshade shuttering work i/p
|
BFP Building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building column reinforcement work
|
RWR Chamber-2 screed finishing works i/p
|
STG gable end sunshade shuttering work i/p
|
BFP Building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building plinth beam deshuttering i/p
|
DG Hydrant pump reassembly i/p
|
BFP Building brickwork i/p
|
CW Ozone building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building plinth beam shuttering i/p
|
All 960 filters erected in Inlet Air Filter
|
STG alignment correction works i/p
|
CW Ozone building brickwork i/p
|
CW Ozone MCC Building plastering i/p
|
BFP Building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building plinth beam shuttering i/p
|
RWR Chamber-2 screed concreting
|
RWPH staging work i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
Fire station building plinth beam reinforcement i/
|
Gas piping terminal joints fit up cleared at GAIL area
|
Fire station building column shuttering work i/p
|
CW Ozone building brickwork i/p
|
CWPH plastering work i/p
|
GBC gable end plastering work i/p
|
BFP Building east side brickwork i/p
|
BFP Building east side brickwork i/p
|
CW Ozone MCC building plastering work i/p
|
CW Ozone building brickwork i/p
|
Plastering work i/p in CWPH
|
Fire station building plinth beam reinforcement i/p
|
DG Hydrant pump reassembly i/p
|
DG Hydrant pump reassembly i/p
|
CWTP AR Tiling works i/p
|
Fire station building plinth beam reinforcement i/p
|
CWPH Brickwork i/p
|
Fire station building plinth beam reinforcemen i/p
|
ETP Chamber 2 balance wall final lift shuttering i/p
|
CW Ozone building brickwork i/p
|
CWTP AR Tiling works i/p
|
Plastering work i/p in CWPH
|
Fire station building column reinforcement wor i/p
|
Fire station building plinth beam reinforcement i/
|
CW Ozone building tanks erection i/p
|
RWR Chamber-2 screed concreting i/p
|
BFP Building brickwork i/p
|
Service building column shuttering work i/p
|
Drain wall shuttering i/p near compressor building
|
CWPH west side brickwork i/p
|
Fire station building plinth beam reinforcement i/p
|
DG Hydrant pump base plate leveling & blue matching i/p
|
CWTP AR Tiling works i/p
|
Plastering work i/p in CWPH
|
Fire station building plinth beam shuttering i/p
|
IDCT Cell 1 fan cylinder final lift RCC i/p
|
DG Hydrant pump reassembly i/p
|
Road works i/p north of RODM Building
|
BFP Building brickwork i/p
|
Drain wall shuttering i/p near compressor building
|
Plastering work i/p in CWPH
|
Fire station building column shuttering work i/p
|
Fire station building column shuttering work i/p
|
ETP west side Road RCC i/p
|
CWTP AR Tiling works i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
Fire station building column shuttering work i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
CWTP AR Tiling works i/p
|
RW Ozone building slab concreting completed
|
Transformer yard rail road 2nd stage RCC completed
|
IDCT Cell 1 fan cylinder final lift shuttering i/p
|
Drill tower backfilling i/p
|
Fire station building plinth beam shuttering i/p
|
Transformer yard rail road angle fixing works i/p
|
ETP Chamber 2 balance wall 2nd lift RCC i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
Fire station building plinth beam deshuttering i/p
|
RWPH brickwork i/p
|
Road works i/p west of ETP
|
BFP Building brickwork i/p
|
CWTP foundation plastering work i/p
|
Fire station building plinth beam RCC i/p
|
Road works i/p west of ETP
|
BFP Building brickwork staging i/p
|
CWTP foundation plastering work i/p
|
CWPH Brickwork i/p
|
Drill tower backfilling i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
IDCT Cell 1 fan cylinder final lift shuttering i/p
|
Fire station building plinth beam shuttering i/p
|
Drill tower backfilling i/p
|
Drill tower backfilling i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
Fire station building plinth beam reinforcement i/
|
Switchyard south side road cleaning & shuttering i/p
|
ETP Chamber 2 balance wall 2nd lift shuttering i/p
|
AAQMS backfilling completed
|
Drill tower backfilling i/p
|
BFP Building
|
STG Building
|
CWPH building
|
CWPH building
|
BFP building west side brickwork i/p
|
CWPH south side brickwork i/p
|
AAQMS pedestals bitumen painting i/p
|
Fire station building plinth beam shuttering i/p
|
BFP Building brickwork i/p
|
ETP Chamber 2 wall 2nd lift shuttering i/p
|
CWPH south side staging work i/p
|
Transformer yard rail road shuttering works i/p
|
BFP Building brickwork i/p
|
CWPH north side destaging work i/p
|
BFP Building brickwork i/p
|
IDCT Cell 1 fan cylinder final lift shuttering i/p
|
Fire station building backfilling & leveling i/p
|
AAQMS pedestals ready for casting
|
CW Ozone building brickwork i/p
|
BFP Building brickwork i/p
|
Switchyard south side road shuttering work i/p
|
Transformer yard rail road reinforcement works i/p
|
BFP Building brickwork i/p
|
Rail road reinforcement i/p for 2nd stage concrete
|
Drill tower columns cleared for concreting
|
AAQMS footing PCC completed
|
AAQMS footing PCC completed
|
Drill tower column deshuttering i/p
|
Switchyard south side road reinforcement work i/p
|
Switchyard south side reinforcement work i/p
|
GBC MCC Building POP i/p
|
Ozone MCC room brickwork i/p
|
BFP Building brickwork i/p
|
Drill tower column shuttering & bitumen painting i/p
|
Drill tower column shuttering & bitumen painting i
|
BFP Building south side brickwork i/p
|
IDCT cell 1 fan cylinder shell 2nd lift deshuttering i/p
|
CWPH west side parapet concrete i/p
|
Transformer yard rail road reinforcement works i/p
|
CW Ozone MCC Building south side brickwork i/p
|
GT Inlet Air Filter element erection i/p
|
CW Ozone MCC Building south side brickwork i/p
|
Transformer yard rail road reinforcement works i/p
|
Switchyard south side road shuttering i/p
|
BFP Building brickwork i/p
|
CWPH west side brickwork i/p
|
Drill tower last footing reinforcement work i/p
|
CW Ozone building brickwork i/p
|
Drill tower
|
Service building 1st floor column reinforcement i/p
|
CWPH east side parapet wall concreting i/p
|
BFP Building brickwork i/p
|
RWPH brickwork i/p
|
Drill tower staircase foundation reinforcement i/p
|
BFP Building brickwork i/p
|
BFP building Sun shade bottom shuttering i/p
|
BFP south side brickwork i/p
|
CWPH west side brickwork i/p
|
CW Ozone building brickwork i/p
|
Drill tower spiral staircase foundation preparatory work i/p
|
RWPH brickwork i/p
|
BFP Building brickwork i/p
|
Drill tower plinth beam deshuttering i/p
|
RWPH brickwork i/p
|
BFP Road edge angle fixing i/p
|
Final painting for GT GT IPBD i/p
|
Drill tower staircase foundation work i/p
|
BFP south side brickwork i/p
|
CWPH west side brickwork i/p
|
IDCT south road panel reinforcement i/p
|
IDCT Cell 1 second lift shuttering i/p
|
Drill tower column shuttering work i/p
|
CWPH west side brickwork i/p
|
ETP Chamber 2 balance wall reinforcement i/p
|
ETP Chamber 2 balance wall reinforcement i/p
|
BFP Building brickwork i/p
|
CWPH west side brickwork i/p
|
IDCT east slope portion road slab RCC started
|
Drill tower plinth beam shuttering i/p
|
Drill tower plinth beam shuttering i/p
|
CW Ozone building brickwork i/p
|
CW Ozone building brickwork i/p
|
STG A row glass fixing work i/p
|
Tr. yard rail road angle fixing i/p
|
BFP west side brickwork i/p
|
IDCT east side road reinforcement i/p
|
BFP Building westside brickwork i/p
|
IDCT Cell 1 fan cylinder cell 2nd lift reinforcement i/p
|
Plant road slope portion slab shuttering work i/p
|
Drill tower plinth beam shuttering i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
Fire station building backfilling work i/p
|
Drill tower plinth beam reinforcement i/p
|
BFP Building brickwork i/p
|
Drain shuttering i/p near compressor bldg
|
CW Ozone building brickwork i/p
|
CW Ozone MCC Building brickwork i/p
|
Fire station building backfilling work i/p
|
CW Ozone MCC room brickwork i/p
|
CWPH north side parapet wall concreting i/p
|
Drill tower plinth beam reinforcement i/p
|
Road slab south of BFP cleared for RCC
|
Drill tower plinth beam reinforcement i/p
|
CW Ozone building brickwork i/p
|
CW Ozone building brickwork i/p
|
IDCT east drain wall shuttering i/p
|
BFP Building Westside brickwork i/p
|
CW Ozone MCC Building brickwork i/p
|
Drill tower plinth beam shuttering i/p
|
Drill tower plinth beam shuttering i/p
|
CWPH west side scaffolding i/p
|
Drill tower plinth beam bottom shuttering i/p
|
CW Ozone building brickwork i/p
|
Transformer yard rail road grouting i/p
|
CW Ozone building brickwork i/p
|
CWPH east side brickwork i/p
|
Transformer yard rail fixing works i/p
|
Drill tower plinth beam shuttering i/p
|
Drill tower plinth beam shuttering i/p
|
BFP west side brickwork i/p
|
CWPH east side brickwork i/p
|
IDCT east drain wall deshuttering i/p
|
CW Ozone building brickwork i/p
|
CW Ozone building brickwork i/p
|
IDCT east drain wall cleared for concrete
|
CWPH east side brickwork i/p
|
ETP Chamber 2 screed concreting completed
|
RW Ozone building slab shuttering i/p
|
CW Ozone MCC Building brickwork i/p
|
Main road shuttering i/p in front of BFP
|
IDCT west side road curing i/p
|
DV Shed slab concreted near GTG
|
Road slab shuttering & cleaning i/p south of BFP
|
CWPH east side brickwork i/p
|
OHT Column 2nd lift staging work preparation i/p
|
Ozone MCC building brick shifting i/p
|
SOHT Columns 2nd lift RCC started
|
RWR Chamber-2 screed finishing i/p
|
BFP Building brickwork i/p
|
IDCT east side drain wall deshuttering i/p
|
CW Ozone building brickwork i/p
|
Steam blowing temporary piping works i/p
|
IDCT east slope portion drain wall RCC i/p
|
IDCT Cell 1 fan cylinder shell 1st lift touch up
|
SOHT Columns 2nd lift reinforcement i/p
|
CWPH Brickwork i/p
|
IDCT east drain wall deshuttering i/p
|
RW Ozone building staging work i/p
|
CWPH east side brickwork i/p
|
IDCT Cell 1 fan cylinder cell 1st lift RCC started
|
Drain wall west of ETP shuttering i/p
|
CWPH east side brickwork i/p
|
OHT Column shuttering work i/p
|
DV Shed grade slab reinforcement i/p near GTG
|
SOHT Column shuttering i/p
|
CWPH east side brickwork i/p
|
DV Shed excavation near CST tank started
|
CW Recirculation pipe pedestal reinforcement i/p
|
RW Ozone building roof slab staging work i/p
|
IDCT Cell 1 fan cylinder cell 1st lift shuttering i/p
|
CWPH lintel beam shuttering i/p
|
CWPH east side brickwork i/p
|
Drill tower column shuttering work i/p
|
Fire station building column shuttering work i/p
|
CW Ozone building brickwork i/p
|
Drain wall west of ETP shuttering i/p
|
CW Recirculation pipe footing cleared for concreting
|
CW Ozone building drain reinforcement i/p
|
IDCT Cell 1 first lift shuttering i/p
|
GCS Drain tank brickwork i/p
|
CW Ozone building toilet area brickwork i/p
|
IDCT east drain wall shuttering i/p
|
CW Ozone building toilet area brickwork i/p
|
Fire station building column shuttering work i/p
|
ETP Chamber 2 wall 2nd lift reinforcement binder work i/p
|
Drill tower column shuttering work i/p
|
IDCT west side road works i/p
|
ETP Chamber 2 wall 2nd lift reinforcement binder work i/p
|
Drill tower
|
CW Ozone building balance grade slab works i/p
|
Inlet air duct bellow covering works i/p
|
CWPH parapet wall reinforcement work i/p
|
Steam blowing temporary piping works i/p
|
BFP Building brickwork i/p
|
CW Ozone building brickwork i/p
|
Drill tower footing RCC i/p
|
Main road drain wall shuttering work i/p
|
CWPH Brickwork i/p
|
CW Ozone building Grade slab reinforcement i/p
|
CW Ozone building brickwork i/p
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
CW Ozone Building cable slit angle fixing i/p
|
Main road drain wall binder reinforcement i/p
|
ETP Chamber 2 balance slab RCC completed
|
CWPH Brickwork i/p
|
IDCT west side road shuttering i/p
|
Steam blowing temporary piping works i/p
|
CW Ozone Building brickwork i/p
|
Fire station building column shuttering work i/p
|
CWPH Brickwork i/p
|
BFP Building brickwork i/p
|
CW Ozone Building brickwork i/p
|
OHT tank column reinforcement works i/p
|
Excavation i/p for CW Recirculation pipe support
|
CW Ozone building brickwork i/p
|
CW Ozone building cable slit angle fixing i/p
|
RW Ozone building lintel beam shuttering i/p
|
OHT Column ring fixing work i/p
|
ETP Chamber 2 balance slab reinforcement work i/p
|
CWPH north side brickwork i/p
|
ETP Chamber 2 balance slab reinforcement work i/p
|
BFP Building brickwork i/p
|
Ozone MCC building parapet wall deshuttering i/p
|
Ozone MCC building south side firewall brickwork i/p
|
RW Ozone building lintel beam shuttering i/p
|
BFP Building brickwork i/p
|
IDCT Cell 1 leveling grading work i/p
|
CWPH Brickwork i/p
|
Drill tower raft shuttering i/p
|
CW Ozone building plinth beam cleaning i/p
|
Drill tower footing column reinforcement i/p
|
BFP Building eastside brickwork i/p
|
Ozonisation ATM tank pedestals curing i/p
|
CWPH Brickwork i/p
|
Drill tower footing shuttering work i/p
|
CW Ozone building foundation pocket fixing i/p
|
Ozone building ATM tank raft & pedestal bitumen painting i/p
|
CW Ozone building brickwork i/p
|
Drill tower footing reinforcement work i/p
|
Ozone MCC building brickwork i/p
|
Ozone building grade slab reinforcement i/p
|
Drill tower footing reinforcement work i/p
|
CWPH Brickwork i/p
|
Ozone MCC building parapet wall shuttering i/p
|
RW Ozone building board making for lintel beam i/p
|
IDCT Cell 1 shell shuttering inner support fixing i/p
|
CWPH Brickwork i/p
|
Ozone building grade slab reinforcement i/p
|
Ozone building ATM tank pedestal reinforcement i/p
|
Drill tower foundation dewatering works i/p
|
IDCT Cell 1 shell shuttering i/p
|
CWPH Brickwork i/p
|
Ozone building grade slab reinforcement i/p
|
Ozone building ATM tank raft reinforcement i/p
|
Ozone MCC parapet wall shuttering work i/p
|
CWPH Brickwork i/p
|
STG 0 mt brickwork i/p
|
Ozone building foundation reinforcement work i/p
|
Transformer yard rail fixing works i/p
|
RW Ozone building grade slab soling work i/p
|
CWPH Brickwork i/p
|
IDCT Cell 1 first lift shuttering i/p
|
Ozone building foundation side shuttering i/p
|
STG alignment checking i/p
|
CWPH Brickwork i/p
|
Drill tower 6 no. foundation PCC completed
|
IDCT south side road curing i/p
|
CW Ozone building grade slab RCC completed
|
ETP Chamber 2 balance M10 filling completed
|
Drain wall shuttering i/p near BFP building
|
Drill tower 3 no. foundation PCC completed
|
BFP south road drain shuttering i/p
|
CWPH Brickwork i/p
|
STG Building A row brickwork i/p
|
STG Building A row brickwork i/p
|
CWPH brick curing work i/p
|
AC Plant tie beam reinforcement work i/p
|
STG A row brickwork i/p
|
IDCT Cell 1 shell ring beam shuttering i/p
|
RW Ozone building cable trench touch up work i/p
|
STG 0 mt brickwork i/p
|
Ozone MCC room slab shuttering work i/p
|
Road panel slab shuttering i/p near GBC building
|
CWPH Brickwork i/p
|
CW Forebay water filling started
|
Ozone MCC room slab shuttering & reinforcement i/p
|
STG Building 0 mt brickwork i/p
|
CWPH Brickwork i/p
|
Slope road reinforcement work i/p near GBC building
|
Ozone MCC room slab shuttering & reinforcement i/p
|
Brickwork i/p at STG 0 mt
|
Excavation i/p for earth mat works near Ozone building
|
CWPH Brickwork i/p
|
Preparatory work for PCC i/p at Drill tower
|
Cleaning i/p for road reinforcement work near GBC
|
Earth mat work i/p near Ozone MCC building
|
Ozone MCC room slab shuttering & reinforcement i/p
|
CWPH Brickwork i/p
|
Transformer yard rail road plate fixing works i/p
|
CW Ozone MCC slab reinforcement & shuttering i/p
|
CWPH Brickwork i/p
|
LP Turbine outer casing parting plane matching i/p
|
STG Gable end brickworks i/p
|
CWPH east side brickwork i/p
|
Ozone MCC room slab reinforcement & shuttering i/p
|
STG Gable end brickworks i/p
|
IDCT cell no. 1 shell reinforcement binding work i/p
|
CWPH Brickwork i/p
|
Ozone MCC building staging work i/p
|
CWPH east side brickwork i/p
|
STG south side gable end brickwork i/p
|
Ozone MCC room slab shuttering & reinforcement i/p
|
PCC completed at east of IDCT main road slope portion
|
IDCT east main road slope portion PCC i/p
|
RW Ozone building cable trench wall shuttering i/p
|
BFP Drain raft shuttering work i/p
|
CWPH Brickwork i/p
|
Ozone MCC building roof beam reinforcement work i/
|
Drill tower earth excavation work i/p
|
Pull pit wall deshuttering i/p near Ozone building
|
IDCT east side main road drain reinforcement i/p
|
Drill tower earth excavation work i/p
|
CWPH Brickwork i/p
|
Ozone MCC room slab shuttering work i/p
|
HRSG north road shuttering i/p for PCC
|
CWPH Brickwork i/p
|
Drain wall reinforcement i/p near BFP building
|
Inlet duct bellow leakage test with water i/p
|
Ozone MCC building staging work i/p
|
Drill tower earth excavation work i/p
|
Cable pull pit wall near compressor bldg cleared for RCC
|
CWPH Brickwork i/p
|
Drain wall reinforcement work i/p near BFP Building
|
Vacuum pump piping works i/p
|
Ozone building grade slab reinforcement i/p
|
Transformer yard rail road slab reinforcement i/p
|
Gas analyser building inside plastering i/p
|
Drain wall near GBC shuttering work i/p
|
IDCT south side road slab reinforcement work i/p
|
STG bearing cleaning works i/p
|
CWPH Brickwork i/p
|
BFP Drain raft reinforcement work i/p
|
CWPH Staging work i/p
|
Ozone MCC room beam shuttering work i/p
|
Transformer yard rail road reinforcement work i/p
|
Vacuum pump piping i/p
|
Gas analyser building north side brickwork i/p
|
CWPH east side staging work i/p
|
BFP Drain raft reinforcement work i/p
|
Ozone MCC room beam shuttering work i/p
|
Excavation i/p for balance 2 footings in service building
|
CPHRC Pump A alignment i/p
|
Transformer yard rail fixing works i/p
|
LP Turbine outer casing seating matching i/p
|
Ozone MCC room beam bottom shuttering work i/p
|
Ozone building grade slab reinforcement i/p
|
Gas analyser building outside plastering i/p
|
CWPH Brickwork i/p
|
Road shuttering & reinforcement i/p near IDCT
|
Ozone building grade slab reinforcement work i/p
|
CWPH Staging work i/p
|
Turbine pedestal cleaning i/p
|
Flow nozzle fixing in CW Forebay filling line
|
GBC Coupling guard fixing work started
|
Gas analyser building outside plastering i/p
|
CWPH Brickwork i/p
|
Ozone MCC room grade slab reinforcement i/p
|
Road rail shuttering i/p for grouting
|
Ozone MCC room slab staging i/p
|
Road reinforcement work i/p near Cooling tower
|
CW Ozone MCC room slab staging work i/p
|
CWPH Brickwork i/p
|
125 V battery maintenance work i/p
|
Ozone building cleaning i/p for grade slab reinforcement
|
IDCT south side road RCC (35 CuM) completed
|
BFP Building brickwork i/p
|
CWPH Brickwork i/p
|
IDCT south side road RCC i/p
|
Condensate spray control valve erection i/p
|
CWPH Staging work i/p
|
BFP Building brickwork i/p
|
CW Ozone building Grade slab reinforcement i/p
|
Cable pull pit wall shuttering work i/p near CW Ozone building
|
CWPH Staging work i/p
|
CWPH Brickwork i/p
|
Soling work i/p for Ozone MCC room
|
Road slab panel reinforcement i/p north of compressor building
|
Road slab bund making i/p west of compressor building
|
Drain wall shuttering i/p west of IDCT
|
Final cleaning i/p for painting of GTG IP bus duct
|
Control fluid oil tank system cleaning completed
|
Soil compaction work i/p for Ozone MCC room
|
Fire station building all footings completed
|
DB 6 side deshuttering work i/p
|
CWPH Brickwork i/p
|
Service water flushing at ETP dosing tank inlet
|
AC MCC final cleaning i/p for permanent charging
|
ETP Chamber-2 raft cleaning & bitumen painting i/p
|
BFP Building Zero mt floor brickwork i/p
|
CWPH Brickwork i/p
|
STG HP IP centering & horndrop i/p
|
RW Ozone bldg toilet roof parapet wall reinforcement i/p
|
BFP Building brickwork i/p
|
DB 6 shuttering work i/p
|
CWPH Brickwork i/p
|
Road RCC (31 CuM) completed at IDCT south east corner
|
STG HP IP centering works i/p
|
Forebay final cleaning work i/p
|
BFP Building 10 mt floor bracing & beams painting i/p
|
DB 6 reinforcement & shuttering i/p
|
Brickwork i/p in CWPH
|
AC Plant cooling tower basin painting completed
|
DB 6 Pipe placement i/p near CW Ozone building
|
Cooling tower basin floor cleaning work i/p
|
OHT raft curing work i/p
|
CWPH north side scaffolding i/p
|
Brickwork i/p in CWPH
|
IDCT east side road bund making i/p
|
BFP Building floor beam painting i/p
|
DB 6 reinforcement i/p nearCW Ozonisation building
|
Final painting of Service Transformer 1 completed
|
STG grouting work u/p
|
RW Ozone building toilet roof slab casted
|
Road panel curing work i/p near DG Building
|
Brickwork started in CWPH
|
RWR Chamber-2 screed concreting i/p
|
ETP Chamber 2 balance wall 1st lift binder reinfor
|
IDCT east side road shuttering work i/p
|
Ozone MCC room plinth beam preparatory work i/p
|
Service overhead tank raft reinforcement work i/p
|
Fire station building backfilling work i/p
|
ETP Chamber-2 balance wall 1st lift lap reinforcement i/p
|
Watering done for soil consolidation in Ozone MCC room
|
GCS area coalescent filter housing inside cleaning
|
RWR Chamber-2 cleaning i/p for screed
|
Drain wall east of IDCT RCC i/p
|
RWR Chamber-2 basin slab panel (300 sqm) concreting completed
|
OHT raft reinforcement work i/p
|
Ozone MCC room backfilling work i/p
|
Preparatory work for road pavement with paver i/p
|
Fire station building bitumen paint i/p
|
Drain raft casted near BFP Building
|
OHT raft reinforcement work i/p
|
Tie beam shuttering work i/p at Ozone MCC building
|
Road panel curing work i/p near DG Building
|
ETP Chamber-2 balance wall 1st lift shuttering i/p
|
BFP Building 10 mt wall plastering work i/p
|
Road panel slab west of compressor bldg. curing i/
|
ETP Chamber 2 balance wall 1st lift shuttering i/p
|
CW Ozone MCC room cable trench wall shuttering i/p
|
Overhead tank raft reinforcement work i/p
|
BFP Building 10 mt wall plastering i/p
|
GBC A&B suction control valve erection completed
|
Looping works in turbine control oil lines
|
ETP North side drain cross over slab RCC i/p
|
Road panel shuttering works i/p near ETP
|
Road panel slab west of compressor bldg. bund maki
|
Fire station building footings bitumen paint i/p
|
STG Alignment work u/p
|
Drain wall shuttering i/p east of IDCT
|
CW Ozone MCC Building
|
Fire station building footings bitumen paint i/p
|
Overhead tank raft bottom mat reinforcement i/p
|
DB 6 at CW Ozonisation building PCC completed
|
Branch tray work i/p for RODM UF Blower
|
Drain wall casted west of ETP slope portion
|
Drain wall deshuttering i/p west of compressor house
|
Fire station building column 1st lift shuttering i/p
|
CW Ozone MCC room cable trench wall shuttering i/p
|
Road panel shuttering works i/p near DG building
|
Cleaning u/p for CWPH Ser. transf. 2 for final painting
|
Drain wall shuttering i/p south of GBC building
|
BFP Building 10 mt plastering work i/p
|
Fire station building
|
PCC preparatory works i/p for DB6 at CW Ozone bldg
|
RCC Chamber 2 PCC i/p near entrance
|
CW Ozone MCC room cable trench wall shuttering i/p
|
Ozone MCC room cable trench wall cleared for concrete
|
Ozone MCC room tie beam side deshuttering i/p
|
Final painting i/p at 11 mt floor beams of IAF
|
RWR Chamber-2 screed curing i/p near RWPH
|
ETP wall dowel reinforcement for 2nd lift wall fixing i/p
|
GBC CCW Pump A & B in circulation for flushing
|
ETP Chamber 2 balance wall 1st lift shuttering i/p
|
Fire station building
|
CW Ozone MCC room cable trench wall shuttering i/p
|
CWPH Ser. Tr.-1 cleaning i/p for final painting
|
Drain wall shuttering i/p east of IDCT
|
Power cable termination for ETP main pump i/p
|
RWR Chamber-2 screed concreting i/p
|
Drain wall shuttering i/p west of BFP building
|
ETP Chamber-2 wall 1st lift reinforcement complete
|
CW Ozone MCC room column reinforcement work i/p
|
GBC CCW Pump A & B in circulation for flushing
|
Power cable termination for flash mixer in ETP completed
|
ETP Chamber-2 wall binder fixing i/p
|
CW Ozone MCC cable trench wall shuttering i/p
|
LP Turbine rotor end stage cleaning i/p
|
RWPH Ser. Transformer 2 cleaning i/p for final painting
|
STG Building A row cladding sheet erection i/p
|
CW Ozone MCC balance trench raft concreting started
|
ETP Chamber 2 balance wall 1st lift reinforcement i/p
|
Drain wall shuttering i/p west of BFP building
|
ETP Chamber 2 balance raft cleared for concreting
|
Drain wall shuttering i/p west of BFP building
|
CPHRC pump normalisation works i/p
|
CW Ozone MCC building tie beam shuttering i/p
|
Fire station building column shuttering work i/p
|
CWPH building rain water down take pipe fixing i/p
|
Drain wall casted south east of GBC building
|
CPHRC normalisation works i/p
|
Overhead tank raft cleaning completed
|
Drain shuttering i/p west of CW Ozone MCC building
|
RWPH Service transformer cleaning i/p for final painting
|
RW Ozone building toilet roof side shuttering i/p
|
RW Ozone cable trench raft casting completed
|
RWR Chamber-2 screed concreting i/p
|
BFP Building south side plastering work i/p
|
ETP Chamber 2 shear key chipping i/p
|
CW Ozone MCC Building cable trench reinforcement i/p
|
Drain wall shuttering i/p at south east corner of Piperack
|
Drain wall shuttering on east side of slope road i/p
|
BFP Building outside wall plastering i/p
|
CW Ozonisation Building roof screed concreting completed
|
STG A row cladding i/p
|
CW Ozone MCC Building trench shuttering i/p
|
RWR Chamber-2 screed concreting (220 sq mt) completed
|
CW Ozonisation building rain water downtake pipe fixing i/p
|
Fire station building
|
BFP Building wall outside plastering i/p
|
Drain shuttering i/p west of CW Ozone MCC building
|
Ozone MCC building tie beam shuttering i/p
|
Drain wall shuttering i/p east of RODM building
|
RWR Chamber-2 screed concreting i/p
|
RW Ozone building toilet roof shuttering i/p
|
ETP Chamber 2 balance wall raft shear key chip i/p
|
Ozone MCC building cable trench reinforcement i/p
|
Fire station building column reinforcemen work i/p
|
RW Ozone building cable trench reinforcement work i/p
|
Drain wall south of GBC cleared for concreting
|
Fire station building column shuttering work i/p
|
BFP Building parapet wall outside plastering i/p
|
CW Ozone building roof treatment preparatory works i/p
|
Ozone MCC building cable trench reinforcement i/p
|
Cladding sheet fixing i/p along STG A row
|
RW Ozone building cable trench soling i/p
|
Booster Pump A suction fit up i/p
|
Tie beam shuttering work i/p at Ozone MCC building
|
Fire station building column shuttering work i/p
|
Ozone MCC building fire barrier wall plastering i/p
|
Fire station building footings RCC i/p
|
Ozone MCC building fire barrier wall plastering i/p
|
Tie beam reinforcement i/p at Ozone MCC Building
|
RW Ozone building plinth filling levelling i/p
|
ETP Chamber 2 balance wall raft reinforcement i/p
|
CEP B discharge flange concentricity & parallelity checking
|
BFP A booster pump discharge flow element cleaning completed
|
BFP Building parapet wall outside plastering i/p
|
Drain excavation west of CWPH MCC building i/p
|
Service building staircase 3rd flight shuttering work i/p
|
Scaffolding i/p for painting of GCB floor beam structures
|
Tie beam reinforcement i/p at Ozone MCC Building
|
BFP 14m roof screeding completed
|
CEP Min Recirculation valve erection
|
CW OZONE MCC Brick work in progress
|
ETP 2 raft reinforcement in progress
|
Fire station building column 1st lift in progress
|
Service building casting
|
RWR 2 screeding 6935/12625 Sqm completed
|
Overhead tank slush removal completed
|
fire station bldg 25/34 total footing completed
|
ETP 2 NW corner raft reinforcement in progress
|
Drain cum retaining wall north of CWPH in progress
|
BFP building 10M brick work and plastering
|
BFP Building roof screed curing i/p
|
RWPH MCC building roof treatment work i/p
|
RWR Chamber-2 screed curing i/p
|
ETP Chamber 2 balance wall raft reinforcement i/p
|
Service building slab concreting completed
|
Fire station building footings work i/p
|
Concreting i/p for service building slab
|
CWPH north drain wall shuttering i/p
|
BFP Building 10 mt MCC wall brickwork i/p
|
RWPH MCC roof treatment work i/p
|
ETP Chamber 2 balance wall raft reinforcement i/p
|
Zoomlion crane boom down for dismantling
|
RWR Chamber-2 screeding i/p
|
CW Ozonisation building parapet wall shuttering i/p
|
Service building slab cleared for concrete
|
BFP Building 10 mt brickwall plastering i/p
|
ETP Chamber 2 balance wall raft shear key excavation i/p
|
STG PMCC Service transformer final painting completed
|
IDCT east road drain raft reinforcement work i/p
|
BFP Building 10 mt brickwork i/p
|
BFP Roof screeding work i/p
|
RWR Chamber-2 screed curing i/p
|
ETP Ch-2 balance wall raft shear key excavation & dewatering i/p
|
Painting of STG UAT completed
|
Grading on north side of IDCT i/p
|
BFP Bldg 14 mt preparatory works for roof screeding i/p
|
Switchyard road panel reinforcement work i/p
|
CW Ozone MCC Building brickwork i/p
|
Ozone building westside parapet wall cleared for concrete
|
RWR Chamber-2 basin screeding (280 sqm) completed
|
BFP Building 10 mt brickwork i/p
|
Service building slab shuttering & reinforcement i/p
|
CW Ozone MCC Building trench PCC completed
|
CO2 bank area wire fencing work completed
|
OHT Tank raft brickwork completed
|
Ventilation duct structure bottom cladding sheet work i/p
|
RWR Chamber-2 basin screeding works i/p
|
STG A row window support channel erection i/p
|
Staging work i/p in BFP Building
|
Drain reinforcement work i/p near compressor house
|
ETP Chamber 2 raft PCC work i/p
|
ETP Chamber 2 area slush removal completed
|
Service building slab beam reinforcement work i/p
|
Staging material shifting i/p for BFP Building
|
Slush cleaning i/p for Overhead tank
|
CW Ozone MCC Building brickwork i/p
|
Brick masonry work in BFP building
|
Cooling tower west area grading work i/p
|
Fencing post fabrication works i/p
|
DV Shed for 8 mt. cable gallery welding work i/p
|
GBC east side drain raft reinforcement & shuttering i/p
|
Service building beam side shuttering works i/p
|
Drain wall shuttering works i/p west of BFP building
|
ETP Chamber 2 balance raft excavation i/p
|
STG Building A row cladding sheet fixing i/p
|
Service building slab reinforcement works i/p
|
Overhead tank brick works i/p
|
Service building side shuttering board making i/p
|
RWR Chamber-2 screed curing i/p
|
ETP west road cleaning for reinforcement i/p
|
BFP Building scaffolding work for brickwork i/p
|
CW Ozone MCC Building brickwork i/p
|
BFP MCC 10 Mtr brickwork i/p
|
ETP Chamber 2 balance raft excavation i/p
|
Service building slab reinforcement work i/p
|
ETP inlet channel wall shuttering work i/p
|
BFP Building staging i/p
|
RODM east side drain preparatory work for PCC i/p
|
CWPH Toilet portion shuttering i/p
|
RWR screeding work i/p
|
Fire station bldg foundation work i/p
|
Brick work in HRSG MCC room in BFP bldg i/p
|
Drain wall works near CWPH i/p
|
STG A row cladding works i/p
|
Service bldg first floor slab works i/p
|
CW Ozone MCC cable trench preparatory work i/p
|
CW Ozone MCC brick work i/p
|
Service bldg - First level slab works i/p
|
Exacavation of balance raft of ETP i/p
|
Road works on west side of BFP bldg i/p
|
Drain works near GBC MCC bldg i/p
|
Ozone MCC brick work in progress
|
Fire station bldg foundation works i/p
|
Preparatory works for overhead tank foundation i/p
|
Brick work in BFP 10m i/p
|
Fire station bldg foundation bldg i/p
|
BFP bldg west side brick work i/p
|
BFP west side road works i/p
|
Service overhead tank foundation preparatory works
|
CW Ozone MCC fire barrier wall brick work i/p
|
RWPH MCC roof screed completed
|
Fire station bldg foundation works in progress
|
RWR chamber 2 screeding works in progress
|
BFP bldg internal plastering works in progress
|
Forebay hand rail finishing works in progress
|
RWR - M10 filling concret at approach portion
|
Service bldg first floor slab works
|
Road works near DG building
|
BFP bldg SWAS room brick work in progress
|
Road works in main plant area
|
Main plant road view
|
Service building first floor slab work in progress
|
ETP inlet chamber works in progress
|
RWR chamber 2 screeding works in progress
|
Control room particle board fixing in progress
|
CWTP plastering work completed
|
RWR chamber -2 screeding works in progress
|
BFP bldg west side brick work in progress
|
Ozone building slab de shuttering in progress
|
Approach road to STG unloading bay in pro
|
RWR wall lift casted upto grade slab level
|
GBC MCC fire door fixing in progress
|
Ozone MCC fire barrier wall brick work in progress
|
Fire station building foundation work in progress
|
Transformer yard to RWR road works
|
Service building first floor slab works
|
Road works on west side of BFP
|
Drain wall works on east side of RODM
|
CWPH toilet roof slab casted
|
Raw water reservoir - Wall and screeding works
|
Fire station building - Foundation work in progres
|
CW Ozone MCC Building brickwork i/p
|
Fire station building PCC completed for 8 footing
|
RWR Chamber-2 wall shuttering work i/p
|
Service Building shuttering & reinforcement works i/p
|
Transformer yard to RWR slope road PCC i/p
|
CWTP Plastering works i/p
|
STG Building A row cladding sheet fixing i/p
|
ETP North side drain cross over slab reinforcement i/p
|
Drain raft shuttering work i/p west of ETP
|
Service building slab shuttering & reinforcement i/p
|
Road panel reinforcement work i/p west of BFP
|
Road curing works i/p near DG Building
|
Box culvert concreted in front of AC Building
|
BFP suction pipe edge preparation i/p
|
Road panel shuttering works i/p near DG building
|
Road pavement slab west of BFP reinforcement i/p
|
RWR Ch-2 wall raft balance portion RCC completed
|
Road PCC shuttering i/p west of ETP
|
RWR Chamber-2 wall raft balance portion RCC i/p
|
ETP buried piping wrapping coating i/p at RW reservoir
|
Drain wall reinforcement i/p west of ETP
|
STG Building A row cladding sheet fixing i/p
|
Service building slab shuttering works i/p
|
IDCT west side levelling & grading works i/p
|
CW Intake channel wall top finishing work i/p
|
Final painting for STG GT Radiators i/p
|
Ozone Building slab deshuttering work i/p
|
Box culvert slab side shuttering i/p in front of AC Building
|
Road panel shuttering preparatory work i/p near DG building
|
Road pavement slab shuttering i/p west of BFP building
|
ETP buried piping wrapping coating i/p at RW reservoir
|
Reinforcement work started in CWPH Toilet slab
|
CWTP Plastering works i/p
|
Drain wall reinforcement i/p west of ETP
|
Alignment of BFP-B Pump with hydraulic coupling i/p
|
STG Building A row cladding sheet fixing i/p
|
ETP west road soling spreading i/p
|
Drain wall shuttering i/p west of ETP
|
Transformer yard road preparatory works i/p near DG building
|
Switchyard south east corner 2 panels ready for concrete
|
CW Intake channel cleaning i/p
|
Road pavement slab RCC i/p west of HRSG
|
Service building slab shuttering works i/p
|
CWPH toilet roof slab staging work i/p
|
Cooling tower east side area grading i/p
|
Box culvert shuttering works i/p in front of AC Building
|
DG Building south side 1 road panel casted
|
Main plant road works i/p
|
RWR Ch-2 wall raft balance portion reinforcement i/p
|
STG Building A row (Grid 2-3) inner cladding sheet fixing i/p
|
BFP west Road panel shuttering work i/p
|
BFP Building handrail grinding & finishing work i/p
|
Drain wall deshuttering i/p near AC Building
|
Road pavement slab west of BFP RCC i/p
|
RWR Ch-2 wall raft balance portion reinforcement i/p
|
Road PCC curing west of ETP i/p
|
Pipe culvert reinforcement i/p near BFP building entrance
|
MOV erected for AC Plant cooling tower
|
Drain wall deshuttering work i/p near DG Building
|
Road PCC along west side of ETP i/p
|
Grading on CWPH MCC east side i/p
|
CST area Earth mat excavation work i/p
|
LP BFP Normalisation works i/p
|
Pipe culvert PCC completed near BFP building entrance
|
Deaerator normalisation work i/p
|
ETP Tube settler fills cleaning i/p
|
CWTP external plastering works i/p
|
AC Plant drain wall shuttering i/p
|
Drain wall deshuttering works i/p near DG building
|
Switchyard south road curing i/p
|
ETP Tank platform erection i/p
|
Drain raft reinforcement work i/p west of ETP
|
AC Plant inner drain wall shuttering works i/p
|
Drain wall shuttering i/p east of RODM building
|
LP BFP piping & pump inspection i/p
|
CWTP Plastering works i/p
|
Road slab reinforcement work i/p west of HRSG
|
STG Building A row outer cladding sheet fixing i/p
|
ETP west road soling spreading i/p
|
CWTP Column plastering work i/p
|
Road slab shuttering i/p west of BFP Building
|
Switchyard south side road panel shuttering work i/p
|
Drain wall curing i/p near DG Building
|
STG Building A row outer cladding sheet fixing
|
BFP building west side brickwork i/p
|
Road panels reinforcement & shuttering i/p west of Chimney
|
Bund making i/p for road casted in front of RODM
|
Drain wall deshuttering works i/p near DG building
|
ETP Pipe erection i/p at STP area
|
Road west of BFP building PCC completed
|
Steam blowing temporary piping works from HPMS to CRH i/p
|
Drain wall shuttering works i/p south of DG building
|
DV Shed raft reinforcement works i/p near staircase 4
|
Switchyard south side road panels (3 no.) casted
|
RODM entrance road panel shuttering works i/p
|
Preparatory works for road PCC i/p on west side of Chimney
|
Bund making & curing of road panels i/p
|
Drain raft west of BFP casted
|
DG Building corner road PCC completed
|
STG Building A row outer cladding sheet fixing i/p
|
Grading works along A row of STG Building i/p
|
Drain wall reinforcement works at switchyard south
|
Switchyard south road reinforcement works i/p
|
Road PCC completed north of RODM
|
Road pavement slab completed west of compressor building
|
ST GT Transformer gravel levelling work i/p
|
Road reinforcement works i/p near compressor build
|
BFP building west side brickwork i/p
|
Switchyard road panel reinforcement work i/p
|
Switchyard south side drain wall deshuttering i/p
|
Excavation along slope main road i/p
|
ETP discharge piping hydro test preparation u/p
|
Service building slab shuttering works i/p
|
CO2 area paving casting completed
|
Road panel (2 no.) casted
|
Compressor building entrance ramp concrete completed
|
CW Treatment Plant plastering works i/p
|
Road soling works i/p south of DG building
|
GBC Foundation EP painting i/p
|
3 road panels ready for casting north of CWPH
|
STG Building A row outer cladding sheet fixing i/p
|
GT Slip ring to turning gear alignment u/p
|
STG GT HV Bushings cleaning for Tan Delta test
|
Compressor south drain wall reinforcement work i/p
|
Soling works i//p for DV Shed at staircase 4
|
Ozone Building destaging works i/p
|
Earthmat excavation started between STG & BFP Building
|
ST GT Transformer south side fencing wire work i/p
|
STG Building A row outer cladding sheet fixing i/p
|
BFP South side (3 panels) concreting completed
|
Drain concrete completed south of switch yard
|
CO2 bank west side grade slab ready for concrete
|
Drain wall shuttering works i/p west of ETP
|
RWR Chamber-2 basin slab cleaning works i/p
|
Staging works i/p in CWTP
|
Brickwork i/p in Gas Analyzer Building
|
CWTP Beam & Column plastering works i/p
|
Soling works i/p in front of DG Building
|
BFP Building east side wall plastering works i/p
|
CW Ozone building deshuttering works i/p
|
STG Gable end cladding outer sheet works completed
|
RW Fire water control room false ceiling completed
|
CO2 area grade slab reinforcement i/p
|
Compressor building ramp shuttering works i/p
|
Road drain reinforcement works i/p at BFP west
|
CWTP Beam & Column plastering works i/p
|
RODM Building ventilator frame fixing completed
|
HRSG Paving drain shuttering work i/p
|
Drain raft south of DG Building cleared for concrete
|
CO2 area west side balance paving PCC completed
|
ETP Chamber 2 floor slab RCC (31 CuM) completed
|
STG Gable end cladding sheet erection i/p
|
BFP Building brickwork i/p in east side
|
Drain PCC completed west side of BFP building
|
2 panels ready for approach road to BOP area
|
Drain reinforcement fixing i/p south of compressor building
|
Drain reinforcement fixing i/p south of DG Building
|
Compressor building south side road drain reinforcement i/p
|
Drain excavation & dressing work i/p west side of BFP Building
|
GTG Slipping coupling runout checking i/p
|
Rail fixing works i/p at rail road between ST GT & GT GT
|
ETP Chamber 2 basin slab reinforcement i/p
|
Road PCC west of compressor house completed
|
RWR Chamber 2 wall 2nd lift deshuttering i/p
|
Road soling works i/p in front of Compressor building
|
RODM east side drain wall reinforcement work i/p
|
HRSG Paving reinforcement works i/p
|
Switchyard south side levelling work i/p for road
|
Road pavement slab RCC (13 CuM) completed near RODM CWPH MCC Junction
|
BFP Building brickwork i/p
|
Side shuttering works i/p for paving in transformer yard
|
ETP Disposal pump discharge piping erection i/p
|
STG Gable end cladding sheet erection i/p
|
Switchyard drain wall deshuttering works i/p
|
Balance shuttering for box culvert top slab near AC Plant
|
Road PCC completed between BFP & Compressor building
|
Transformer yard rail road sand filling works i/p
|
ETP Chamber 2 floor slab cleaning i/p
|
Compressor building north side road compaction i/p
|
Transformer yard area soling works i/p
|
Road excavation south side of CW Ozonisation building
|
RWR Chamber 2 wall 2nd lift shuttering i/p near entrance
|
Soling works between compressor building & BFP
|
Compressor west drain deshuttering works i/p
|
Switchyard east side drain raft PCC (20 rmt) completed
|
IDCT south side drain raft RCC (35 rmt) completed
|
Approach to Power House building drain work i/p
|
HRSG Paving reinforcement works i/p
|
CWPH north side drain deshuttering works i/p
|
RWR Chamber-2 basin slab panel RCC (35 CuM) completed
|
STG Gable end cladding sheet erection i/p
|
RWR Chamber-2 wall 2nd lift shuttering i/p near entrance
|
BFP Building brickwork i/p
|
Drain wall west of ETP shuttering i/p
|
Switchyard drain reinforcement works i/p
|
RODM DCS Room false ceiling completed
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Drain wall reinforcement i/p near Compressor house
|
GTG east side road concreting completed
|
Drain wall west of ETP RCC (1CuM) completed
|
Drain raft north of ETP RCC (2 CuM) completed
|
Reinforcement i/p for drain wall on south side of AC Building
|
DM Water transfer pump mechanical seal replacement i/p
|
Rail road side shuttering work i/p near burnt oil pit
|
Reinforcement for drain wall on north side of CWPH i/p
|
Drain wall deshuttering works i/p near DG building
|
STG Gable end cladding sheet erection i/p
|
Platform work i/p inside BFP Building
|
Road panel casted on north approach to CW MCC
|
Road panel casted on north side of RODM
|
Drain wall concrete completed at south of AC building
|
Drain wall reinforcement works i/p south of DG building
|
RWR Chamber-2 basin slab panel (30 CuM) RCC Completed
|
Rail road reinforcement i/p near burnt oil pit
|
HRSG Paving slab RCC (65 CuM) completed
|
Transformer yard 2 panels casting completed
|
Soling works i/p near ST GT Transformer
|
Cement plastering for chilled water line i/p near AC Plant
|
BFP entrance grade slab works i/p
|
CWPH north drain wall reinforcement work i/p
|
Bund making for road panel casted between RODM & CWPH
|
GBC A FG Suction line normalisation work i/p
|
Switchyard south side drain wall shuttering i/p
|
GTG east road panel concreting completed
|
RODM approach road one panel cleared for concreting
|
Flushing drain out piping erection at transformer yard
|
STG Gable end cladding sheet erection i/p
|
Transformer yard road curing works i/p
|
Drain PCC south of DG building completed
|
Drain raft RCC completed south of AC building
|
Road panel reinforcement at RODM & CWPH junction i/p
|
BFP entrance grade slab reinforcement fixing i/p
|
RWR Chamber 2 wall final lift shuttering i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Rail road side deshuttering work i/p
|
Transformer road curing works i/p
|
Drain PCC along south side of IDCT i/p
|
RWR Chamber-2 wall shuttering supporting works i/p
|
HRSG grade slab reinforcement i/p
|
BFP Building brickwork i/p
|
CW Ozonisation building parapet wall concreting i/p
|
Transformer Yard
|
BFP Building brickwork i/p
|
RW Ozone Building column shuttering i/p
|
Transformer yard 3 panels casting completed
|
Scaffolding works for vent insulation i/p at HRSG
|
RWR Chamber-2 basin slab 30 Cum PCC completed
|
HRSG Paving reinforcement works i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
STG Gable end cladding sheet fixing i/p
|
CWPH north east corner PCC completed
|
Plate fixing i/p for transformer yard rail road
|
Painting i/p for AC system condenser water line & makeup tank
|
RWR Chamber 2 wall 3rd lift shuttering preparation i/p
|
Drain wall shuttering i/p at west of ETP
|
Scaffolding works for vent line insulation i/p at HRSG
|
Soling works i/p at south east of STGT
|
RWR Chamber-2 basin slab panel concreting completed
|
Switchyard south drain raft (20 Mt) concreting completed
|
RWR Chamber-2 basin slab panel reinforcement i/p
|
STG Gable end cladding insulation works i/p
|
Compressor building corner road drain PCC complete
|
GT GT Rail road 2nd stage concreting completed
|
GTG east road panel concreting completed
|
HRSG grade slab reinforcement works i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Switchyard south side drain wall shuttering i/p
|
RODM north side 7 Mt wide road panel shuttering i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
GT approach road side deshuttering work i/p
|
Deshuttering of drain wall i/p west of ETP
|
GT GT Rail road 2nd stage concrete reinforcement i/p
|
Switchyard south side drain wall deshuttering i/p
|
Switchyard south side drain wall concreting completed
|
CW Annex building north road panel concreting completed
|
ETP Chamber 2 floor slab RCC (40 CuM) i/p
|
GT East approach road side shuttering works i/p
|
Ozone building parapet wall deshuttering i/p
|
GT GT Rail road 2nd stage concrete shuttering works i/p
|
LP Vent line insulation i/p
|
AC System condenser water pipe painting i/p
|
ETP Chamber 2 wall final lift RCC i/p
|
Road drain wall south of DG building deshuttering i/p
|
STG Gable end cladding sheet erection i/p
|
CW Annex building north road panel shuttering i/p
|
RWR Chamber-2 basin slab bund making & cleaning i/p
|
BFP A motor to HC coupling i/p
|
IP downcomer & drains insulation work i/p
|
RWR Chamber-2 basin slab RCC i/p
|
ETP-2 wall shuttering final alignment work i/p
|
GT GT Rail road 1/4 no. grouting completed
|
Reinforcement placing preparatory work at drain near AC Building
|
ST UAT transformer fencing work completed
|
RWR Chamber-2 basin slab panels cleared for concreting
|
Bitumen painting of CT basin slab of Cell 6
|
Road dressing work i/p between transformer yard to ETP
|
ETP Chamber 2 basin slab reinforcement i/p
|
Transformer yard pipe culvert shuttering works i/p
|
RO 2 Membrane loading i/p in RODM
|
ETP Pipes wrapping coating i/p
|
GBC B Motor to gear box coupling completed
|
CWPH MCC Building inside wall plastering i/p
|
STG cross around pipe insulation work i/p
|
Drain excavation i/p near AC Plant
|
Cooling Tower basin cleaning i/p
|
STG Gable end z purlin fixing i/p
|
BFP Building bricks shifting work i/p
|
GT GT Rail road shuttering works i/p
|
CW outlet gate monorail welding i/p
|
Service transformer fencing wire mesh fixing i/p
|
Cleaning works in intake channel
|
Transformer yard pipe culvert reinforcement fixing i/p
|
RO 2 Flushing i/p in RODM
|
STG Building B row cladding erection i/p
|
Monorail alignment i/p in CW outlet area
|
ETP Chamber 2 basin slab reinforcement i/p
|
GBC B Motor to gear box alignment i/p
|
Switchyard road south side drain reinforcement i/p
|
ETP Chamber 2 basin slab reinforcement i/p
|
DV Shed piping work u/p
|
ST GT Rail road 2nd stage concreting completed
|
Switchyard road south side drain reinforcement i/p
|
DG Plant east side corner drain shuttering i/p
|
GBC B Motor to gear box alignment i/p
|
Wrapping coating i/p for ETP disposal pump discharge piping
|
STG B row cladding erection i/p
|
ETP 2nd chamber balance 3rd lift wall shuttering i/p
|
Backfilling of drain sides along IDCT west side road
|
ST GT Rail road angle fixing i/p
|
Grade slab RCC (7 Cum) below HRSG completed
|
ST GT Transformer fencing works i/p
|
DV Valve charging u/p
|
Road panel deshuttering & curing at RODM north side
|
CW Ozonisation building parapet wall shuttering i/p
|
ETP Chamber 2 balance 3rd lift wall shuttering i/p
|
Preparatory work for ETP Chamber-2 grade slab i/p
|
HRSG grade slab cleaning i/p
|
Insulation work i/p near flash tank area
|
Detergent flushing temporary piping works i/p
|
RWR to transformer yard road drain wall cleared for concreting
|
ST GT PCC paving concrete completed
|
RODM north side road slab RCC completed
|
RODM north side road slab RCC i/p
|
Bitumen painting i/p in IDCT
|
CEP Pit cleaning works i/p
|
CW Ozonisation building slab parapet wall reinforcement i/p
|
Transformer yard pipe culvert raft shuttering works i/p
|
ST GT Rail grouting works i/p
|
RWR Chamber-2 basin slab cleaning works i/p
|
STG B row cladding erection i/p
|
Leftover drains & vents insulation i/p in HRSG
|
Bitumen painting i/p on west side of IDCT
|
Steel window frame fixing completed in CWPH MCC
|
CW Ozonisation building slab concrete (96 Cum) completed
|
N2 generation system charged
|
STG B row cladding erection i/p
|
CW Ozonisation building slab concreting i/p
|
Insulation work i/p near flash tank
|
CWPH east side backfilling i/p
|
Fencing wire mesh placing around CWPH transformers
|
STG B row cladding erection
|
STG B row cladding works i/p
|
Steel window frame fixing in CWPH MCC i/p
|
CWPH Screen erection completed
|
Transformer yard road pipe culvert PCC preparatory works i/p
|
Rail road grouting shuttering works i/p
|
Detergent Flushing drain out piping works i/p
|
Fuel gas pipeline cleaning i/p
|
HRSG Drain line insulation works i/p
|
Transformer yard PCC preparatory works i/p
|
CEP Strainer flange hinge relocation works i/p
|
Detergent flushing draining pipe erection i/p
|
Fuel gas pipeline pigging arrangement i/p
|
Feed water system flushing readiness checking i/p
|
Cooling Tower bitumen painting i/p
|
Firefighting system compressor A & B healthiness checking
|
Detergent flushing temporary piping works i/p
|
HRSG Drain line insulation works i/p
|
Rail fixing i/p for approach road of GT GT in transformer yard
|
Tie rod cutting of ETP south side wall i/p
|
Backfilling on north side of CWPH i/p
|
Reinforcement work for road panel on north side of CWPH
|
Final alignment works of fan in Cooling Tower
|
IDCT West side scaffolding erection for bitumen painting i/p
|
ETP Piping preassembly i/p
|
FFU Plenum erection i/p at 32 Mt GTG Building
|
CWTP Main cable tray work i/p
|
STG Gable end inner cladding works completed
|
Reinforcement work i/p for approach road to CWPH
|
Air Inlet Filter Platform grating erection i/p
|
Backfilling on north side of CWPH i/p
|
Paver blocks unloading near GBC building road
|
Bitumen painting i/p on west side of IDCT
|
Gas Turbine on Barring Gear
|
Flash tank insulation work i/p
|
RODM Neutralisation Pit Chamber 1 cleaning i/p
|
Brickworks i/p in Raw Water Pump House
|
STG Gable end cladding sheet fixing i/p
|
Bitumen painting i/p on west side of IDCT
|
Backfilling on north side of CWPH i/p
|
STG Gable end cladding sheet erection i/p
|
RODM UF Blower B Trial run u/p
|
Gap setting of speed sensors completed
|
GT GT Rail road rail fixing works i/p
|
STG Drain piping insulation i/p
|
IDCT Cell 11 west side painting i/p
|
GTG North side preparatory works for precast slab placement i/p
|
GCS area fencing post erection i/p
|
Brickwork i/p along south side in RW Pump House
|
Fuel gas pipe 1st stretch cleaning completed
|
Bitumen painting in progress on north side of IDCT cell 11
|
UF Membrane loading completed in RODM
|
Air compressor motor A & B (Fire Hydrant System) trial run u/p
|
AC Fire hydrant motor trial run u/p
|
UF Membrane installation i/p in RODM
|
STG Gable end cladding sheet erection i/p
|
Rail fixing works i/p for ST GT Rail road
|
STG Drain piping insulation i/p
|
CW Ozonisation building reinforcement works i/p
|
GT Aft pedestal side key inspection with GE & customer i/p
|
STG Gable end cladding sheet erection i/p
|
Road soling spreading i/p north of RODM
|
Rail fixing works i/p for ST GT Rail road
|
Levelling work i/p for paving in transformer yard
|
IDCT Cell 11 bitumen painting i/p
|
HRSG Warm up line work u/p
|
IDCT Cell 10 bitumen painting i/p
|
Main approach road PCC (12 CuM) completed
|
CW Ozonisation building slab shuttering works i/p
|
Rail placing i/p at ST GT Rail road
|
Road panel shuttering works i/p at RODM north side
|
STG A row column painting i/p
|
GT Rail fixing works in progress
|
Preparatory works for road soling at RODM north
|
IDCT Cell 8 Fill beam bitumen painting i/p
|
Road pavement RCC (2 panels) completed south of GBC MCC
|
Preparatory works for PCC i/p for main approach road
|
STG A row cladding sheet erection in progress
|
Road excavation at north of RODM i/p
|
RODM North side road reinforcement i/p
|
GT Generator Exciter end outer oil labyrinth fixing i/p
|
Cooling Tower bitumen painting i/p
|
Excavation for TR. yard rail road pipe culvert i/p
|
Ozone Building staging works i/p
|
Staircase-4 handrail fixing work i/p
|
STG A row cladding sheet erection i/p
|
Staircase-4 handrail fixing work i/p
|
Reinforcement work i/p at approach road to GBC
|
RODM MCC Room wall POP application i/p
|
Drain wall shuttering works i/p near DG building
|
Earth levelling on north side of RODM i/p
|
ETP 2nd chamber south 3rd lift wall concreting i/p
|
STG A row cladding sheet erection i/p
|
RWPH Staircase portion grade slab PCC i/p
|
RODM MCC Room wall POP application i/p
|
ST GT East grade slab preparatory works i/p
|
STG A row cladding i/p
|
ST GT South side levelling work i/p
|
ST GT Rail road curing & side deshuttering work /p
|
Bund making i/p for rail road curing
|
CWPH approach road PCC i/p
|
ST GT Rail road concrete i/p
|
DV Shed plastering work i/p
|
Painting work at GCS area
|
Soling spreading in RWPH unloading bay i/p
|
CW Ozonisation building slab reinforcement i/p
|
GBC Slope road deshuttering work i/p
|
STG A row cladding i/p
|
IDCT Cell 6 bitumen painting i/p
|
Preparatory works for soling below grade slab in RWPH Maintenance bay
|
ETP 2nd chamber south side final lift shuttering alignment i/p
|
Preparatory works for PCC for approach road to CWPH i/p
|
PRV fixing in GT jacking oil line
|
GBC A suction line air blasting in progress
|
ST GT rail road preparatory works for concreting
|
CW ozonisation building slab reinforcement works
|
GT-GT rail cum road first stage concreting casted
|
ETP north side wall final lift casted
|
HPBFP B voith coupling trial run completed
|
Transformer yard fencing post erection
|
Raw water reservoir basin slab panel concreting
|
GTG Gable end chhajja plastering i/p
|
GTG A row cladding i/p
|
RODM North side drain wall shuttering i/p
|
GBC MCC Building chhajja plastering i/p
|
Rail road plate fixing work i/p
|
STG building A row pipe rack painting work i/p
|
STG Gable end structural painting works i/p
|
CW Ozonisation building slab beam reinforcement i/p
|
GTG A row cladding i/p
|
RWR-2 - Basin slab reinf work
|
CW make up pump B trial run
|
Generator ATT in progress
|
EP fixing for rail road in transformer yard
|
Steam blowing piping erection in progress
|
GTG A row cladding i/p
|
Steam blowing piping erection outside GT building
|
GTG Rail road bolt fixing works i/p
|
Steam blowing piping erection at GT north
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Cooling Tower bitumen painting i/p
|
Painting work inside BFP building i/p
|
GTG east side road deshuttering & cleaning work i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Rail road plate fixing work i/p
|
Cooling Tower painting i/p
|
IDCT south side road ramp PCC completed
|
Steam blowing piping fabrication work i/p
|
Drain raft shuttering work i/p near AC Building
|
IDCT south side road ramp PCC i/p
|
GTG east side road shuttering & cleaning work i/p
|
Pipe rack pipe cleaning i/p
|
RODM north side road soling work i/p
|
CW Ozonisation building slab shuttering works i/p
|
RWR Chamber-2 basin slab panel (130 sqm) concreting completed
|
GTG Building insulated cladding sheet fixing i/p
|
RWR Chamber-2 basin slab concreting i/p
|
GTG east road concreting works i/p
|
DV Shed slab concreting i/p
|
ETP Oil storage tank placed on foundation
|
HRSG Fill pump space heater installation i/p
|
Box culvert BC-3 top slab concrete completed
|
Rail road concreting completed
|
Pipe rack hand rail erection i/p
|
Pipe culvert deshuttering work i/p near compressor building
|
RODM North side road balance soling work i/p
|
Rail road concreting i/p
|
GTG Gable end cladding sheet fixing i/p
|
ETP 2nd chamber south side 2nd lift wall concreting i/p
|
Painting work at CW Pipe i/p
|
Plinth beam reinforcement work at BFP entrance i/p
|
Earthmat interconnection between GBC & BFP grid /p
|
ETP screed concrete completed
|
GTG road shuttering works i/p
|
Ozone Building staging & shuttering works i/p
|
Reinforcement work i/p for box culvert at transformer yard area
|
GTG Gable end cladding sheet fixing i/p
|
Transformer yard rail road EP fixing works i/p
|
STG 8th grid plastering work i/p
|
Ozone Building staging works i/p
|
Box culvert slab cleaning i/p near DG Building
|
STG A row cladding runner painting i/p
|
Earthmat laying works i/p near chimney
|
Road panel shuttering works i/p near GBC building
|
Drain shuttering works i/p near GBC MCC
|
GTG 12th grid outer plastering works i/p
|
CWTP Plastering works i/p
|
GTG Gable end plastering works i/p
|
RODM North side drain wall shuttering i/p
|
Preparatory works for Drain raft PCC near AC Building
|
GTG Gable end plastering i/p
|
ETP Chamber 2 reinforcement works i/p
|
RWR Chamber-2 wall shuttering i/p
|
Road reinforcement placing & concreting i/p near GBC
|
BFP Building handrail erection i/p
|
Gas room inside plastering works i/p
|
GTG Gable end plastering works i/p
|
RODM Building cage ladder works i/p
|
Gas room inside plastering works i/p
|
GTG Gable end balance brickworks i/p
|
Ozone Building staging works i/p
|
DG Building east side drain raft reinforcement i/p
|
DM Tank platform works i/p
|
GTG Gable end cladding sheet fixing i/p
|
Drain wall shuttering i/p west of GBC MCC Building
|
GTG Building grid 10-11 plastering works completed
|
Transformer yard rail road plate fixing works i/p
|
Handrail erection i/p between HRSG & BFP interconnection
|
DM Tank platform erection i/p
|
Ozone Building staging works i/p
|
GTG C row inner plastering works i/p
|
GTG Gable end cladding sheet fixing i/p
|
GTG Gable end cladding sheet fixing i/p
|
Ozone Building staging works i/p
|
CE Pump-A alignment i/p
|
STG DV shed piping fittings & gasket fixing i/p
|
GTG C row inner plastering works i/p
|
Transformer yard rail road plate fixing works i/p
|
Handrail erection i/p at STG to BFP interconnection platform
|
STG A row cladding runner painting i/p
|
Preparatory works for drain shuttering near GBC MCC
|
CW Ozonisation building slab shuttering works i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
HRSG Staircase handrail work i/p
|
Road soling & leveling works i/p north of CWPH MCC
|
Painting of ACW discharge piping i/p
|
GTG East side road reinforcement works i/p
|
Plant water piping erection to Compressor building
|
STG A row cladding runner painting i/p
|
Pipe painting works in GT Building
|
SW/PW Piping to compressor building
|
Drain wall reinforcement i/p near GBC MCC
|
RWR Chamber-2 basin slab panel concreted
|
GTG Building C row plastering i/p
|
DMCW piping painting works i/p
|
Approach road slush removal i/p near chimney
|
RWR Chamber-2 basin slab panel cleared for concreting
|
GTG C row inner plastering works i/p
|
Insulation lagging works i/p at HRSG Pipe rack
|
STG A row cladding runner painting i/p
|
Pipe culvert encasing shuttering i/p at RODM north
|
Box culvert slab concreting i/p near Compressor building
|
GTG C row inner plastering works i/p
|
RW Pump House platform welding i/p
|
GTG Gable end cladding sheet fixing i/p
|
Box culvert shuttering completed near compressor building
|
Pipe culvert side shuttering completion below pipe rack
|
Slush removal for drain raft near RODM i/p
|
Pipe culvert encasing shuttering i/p at RODM north
|
Rail road plate fixing works i/p
|
ETP north side road drain wall shuttering i/p
|
DV Shed piping work u/p
|
Box culvert slab shuttering i/p near Compressor building
|
ETP north side road drain wall shuttering i/p
|
STG A row cladding runner painting i/p
|
Rail road plate fixing preparatory works i/p
|
GTG Gable end cladding sheet fixing i/p
|
Box culvert wall concrete done near compressor building
|
ETP north side grade slab reinforcement i/p
|
Drain raft RCC i/p west of GBC MCC
|
GTG Gable end cladding sheet fixing i/p
|
Rail road plate fixing preparatory works i/p
|
Box culvert wall deshuttering i/p near compressor
|
Preparatory works for grade slab reinforcement at ETP
|
Transformer yard rail road reinforcement works i/p
|
RODM north side drain raft casting
|
Ozone building beam bottom shuttering works i/p
|
STG A row cladding runner painting i/p
|
Pipe culvert reinforcement work i/p south of GBC MCC
|
Beam bottom shuttering making for Ozone building
|
GTG Gable end cladding sheet fixing i/p
|
STGT Rail road reinforcement works i/p
|
Drain wall shuttering works i/p near DG building
|
Earthmat work to RWPH grid i/p
|
RWPH Pump floor brickworks i/p
|
Road drain raft reinforcement i/p west of IDCT
|
STG A row cladding runner painting i/p
|
RODM north side drain raft shuttering i/p
|
GTG B row cladding completed for available front
|
GTG East side road reinforcement works i/p
|
Transformer yard road reinforcement works i/p
|
Road near compressor building PCC completion
|
Drain wall concreting i/p near DG Building
|
RWPH Pump floor brickworks i/p
|
ETP north side grade slab PCC completed
|
GTG B row cladding works i/p
|
Pipe culvert encasing shuttering near CWPH
|
RODM North side drain wall RCC i/p
|
RWPH Pump floor brickworks i/p
|
ETP north side soling i/p
|
RW to transformer yard road slab shuttering i/
|
GBC B Row cladding i/p
|
Transformer yard rail road reinf work
|
Drain reinf work near Raw water reservoir
|
Raw water reservoir basin slab panel concreting
|
Excavation for earth mat on west side of BFP bldg
|
Drain shuttering works near CWPH MCC
|
Drain excavation towards compressor bldg completed
|
Staircase 3 hand railing works
|
Road excavation near RODM bldg
|
Internal plastering in STG bldg Brow Grid 2-3
|
ETP north side grade slab soling
|
Drain wall shuttering near GCS area
|
GT east side road reinforcement works i/p
|
ETP Wall shuttering alignment i/p
|
GBC Building balance floor screeding finishing
|
Drain raft reinforcement i/p along road from RWR to Tr. yard
|
Box culvert slab shuttering i/p near DG Building
|
RWR Chamber-2 basin slab panel (130 sqm) concreting completed
|
GBC Building balance floor screeding completion
|
RWR Chamber-2 basin slab panel (130 sqm) concreting i/p
|
ETP Pump foundation reinforcement i/p
|
RODM north corner drain wall deshuttering i/p
|
Drain shuttering works along sloping road near GBC
|
RODM South side pipe culvert reinforcement i/p
|
GTG B row cladding works i/p
|
Compressor building box culvert reinforcement i/p
|
CW Ozonisation duct bank concrete work completion
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Duct bank concreting i/p near compressor building
|
GBC Building Floor screeding
|
RWR Chamber-2 basin slab reinforcement works i/p
|
ETP Chamber-2 Wall shuttering alignment i/p
|
RODM South side Hume pipe laying i/p
|
Compressor building box culvert raft reinforcement
|
PCC done on the road near GBC building
|
Compressor building
|
BFP Building
|
RODM Pump Floor south side brickworks i/p
|
ETP north side grade slab watering i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Drain wall reinforcement near DG Building
|
Main plant road preparatory works i/p
|
Duct bank PVC pipe placement i/p
|
AC Building
|
GTG Gable end cladding sheet fixing i/p
|
Road soling & leveling works i/p near GBC Building
|
DG Building
|
GTG Gable end plastering works i/p
|
Duct bank PVC pipe placement i/p
|
Raw Water Reservoir chamber 1
|
Raw Water Reservoir chamber 2
|
ETP South side wall shuttering i/p
|
Cooling water pump house
|
Pipe culvert concreted near CWPH transformer yard
|
Handrail erection in Neutralisation Pit
|
Cooling water treatment plant
|
BFP Building
|
ETP North side wall shuttering i/p
|
GTG B row cladding works i/p
|
IDCT Cell no. 1 fan deck slab concreted
|
GTG A row beam painting i/p
|
Pipe culvert shuttering work near CWPH transformer yard
|
GTG Gable end cladding sheet fixing i/p
|
IDCT. Cell no. 1 fan deck slab cleared for concret
|
Road drain reinforcement works near DG building
|
RWR to transformer yard road drain excavation work
|
Service building slab staging works i/p
|
GTG B row cladding works i/p
|
IDCT. Cell no. 1 fan deck slab reinforcement i/p
|
Transformer yard road drain reinforcement works
|
STG unloading bay road pipe culvert reinforcement
|
DV Shed plastering work i/p
|
Switchyard road PCC works i/p
|
Drain wall shuttering works i/p near CWPH
|
Fire station building excavation i/p
|
GTG Building C row inner plastering i/p
|
DG Building road earth compaction work i/p
|
Cooling water pump house
|
Cooling Tower
|
GTG B row insulated cladding works i/p
|
GTG Building C row plastering in progress
|
GTG B row insulated cladding works i/p
|
Road near south of Cooling Tower PCC i/p
|
RWR Chamber-2 East side wall final lift i/p
|
Pipe culvert reinforcement work between RODM & CW
|
STG Building C row plastering i/p
|
Excavation for fire station building
|
Earthmat excavation near DG building i/p
|
GTG B row insulated cladding works i/p
|
STG Gable end brickworks i/p
|
Service building staging works i/p
|
DV Shed slab reinforcement work in progress
|
STG unloading bay road compaction works
|
GBC Road drain shuttering works i/p
|
Road excavation works i/p near BEPL office
|
CO2 Distribution bank grade slab filling works in progress
|
Excavation of main approach road at IDCT East side
|
Road excavation works in progress near overhead tank
|
Drain works in front of CWPH
|
Service building slab works in progress
|
CW Ozonisation building slab staging works in progress
|
GTG B row cladding works in progress
|
Ammonia dosing pipe pressure test i/p
|
STG Ventilation duct riser preassembling i/p
|
CWTP Roof sheet completion
|
ETP Oil storage tank foundation cleared for pcc
|
Transformer yard road pcc works i/p
|
Service building slab beam shuttering works i/p
|
Road & drain work i/p in RODM south side
|
Plastering work i/p in CWTP
|
Vent fan gas compartment roof sheeting i/p
|
Cooling Tower
|
RWPH Outdoor cable tray covering i/p
|
Transformer yard road cleared for pcc
|
Cooling water pump house
|
Compressor building
|
Cable and branch tray work for FFU i/p at 32 mt
|
DG Plant exhaust pipe & silencer insulation i/p
|
HRSG Structure painting i/p
|
Cable tray covering along RWPH tray
|
RWR Road deshuttering works i/p
|
Switchyard road excavation works i/p
|
Service building beam shuttering works i/p
|
DG Building brickworks i/p
|
GTG B row cladding works i/p
|
RW Road panels concreting i/p
|
STG Building B row brickworks i/p
|
DG Building brickworks i/p
|
Service building roof bottom shuttering works i/p
|
STG Building B row cladding works i/p
|
Gable end structural painting works i/p
|
Service building staging works i/p
|
Transformer yard road excavation i/p
|
STG Building C row plastering i/p
|
DPC preparatory works i/p in CWTP
|
Service building staging works i/p
|
Switchyard drain wall cleared for concrete
|
RWR Chamber-2 basin screening works i/p
|
Service building lintel beam shuttering works i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Switchyard drain wall shuttering works i/p
|
RW Ozonisation bldg. plinth beam deshuttering i/p
|
Service building tie beam staging works i/p
|
GTG Building C row plastering i/p
|
Shunt welding completed for LAVT
|
STG Gable end final painting works i/p
|
Drain excavation on north side of CWPH i/p
|
RODM Building West side Outer plastering i/p
|
STG Gable end sag fixing i/p
|
Cable tray covering along GBC north
|
Ozone MCC Room column reinforcement work i/p
|
Service building beam staging works i/p
|
RODM Building
|
GTG Building C row plastering i/p
|
Covering for outdoor cable tray along GBC & BFP pi
|
Drain reinforcement between GBC & CWPH road
|
STG Building Gable end brickwork i/p
|
CW Ozonisation building works i/p
|
STG Building C row plastering i/p
|
Switchyard drain wall cleared for concrete
|
GTG Building C row brickworks i/p
|
Turbine insulation i/p
|
Cooling water pump house
|
RODM Building
|
GTG Building C row brickworks i/p
|
Service building grade slab pcc work i/p
|
Shunt welding for LAVT i/p
|
Ozonisation MCC plinth beam concrete i/p
|
Pedestals casted from forebay to CWTP
|
Preparatory works for drain casting in DM tank are
|
Erection of Inspection cover for STG IPBD
|
STG Building C row plastering i/p
|
GTG Building C row brickworks i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
Compressor building
|
BFP Building
|
RODM Building Outer plastering i/p
|
Al. welding for STG IPBD i/p
|
HRSG South side paving area levelling i/p
|
Fencing post work in CWPH transformer yard i/p
|
ETP North side road drain cutting i/p
|
Surface preparation for LAVT & SPVT shunt welding
|
IP Discharge piping looping i/p
|
Service building Soling works i/p
|
STG Building B row plastering i/p
|
HRSG Paving reinforcement works i/p
|
Erection of HAB for IPBD i/p
|
CWTP Soling spreading i/p
|
STG Main cable tray work i/p
|
RODM Building Outer plastering i/p
|
GTG Building C row plastering i/p
|
Compressor house north side levelling works i/p
|
HRSG Paving soling works i/p
|
RWR Chamber-2 basin slab reinforcement works i/p
|
RODM Building Outer plastering i/p
|
GTG Building C row plastering i/p
|
Service building staging works i/p
|
Welding of IPBD supports i/p
|
RODM Building Outer plastering i/p
|
Staging works i/p in DV Shed-7
|
Brickworks i/p above GT rolling shutter
|
Permanent hanger supports work i/p for STG IPBD
|
CWPH & RODM Building
|
ST Transformer soling works i/p
|
GBC & GCS Building
|
RW Ozonisation bldg. plinth beam shuttering works i/p
|
Fencing wire mesh fixing in transformer yard
|
STG Building Gable end brickwork i/p
|
DV Shed plastering work i/p
|
Cooling water pump house
|
GBC MCC external plastering i/p
|
Service building column shuttering works i/p
|
DM tank area paving soling i/p
|
STG Building C row plastering i/p
|
AC Building outside plastering work i/p
|
Enclosure assembly for GTG
|
Trench wall angle fixing work i/p
|
ST Transformer soling works i/p
|
Compressor building
|
Alignment of SPVT tap off i/p
|
STG Building
|
Raw Water Reservoir 2nd chamber
|
LAVT Cubicle alignment
|
RW Ozonisation bldg. plinth beam reinforcement i/p
|
CWPH Roof slab reinforcement works i/p
|
Road levelling works between GBC & CWPH
|
AC MCC Building outer plastering completion
|
ETP 2nd chamber 2nd lift reinforcement i/p
|
Switchyard drain reinforcement works i/p
|
DV Shed plastering work i/p
|
RW Ozonisation building plinth staging i/p
|
GTG Building C row brickworks i/p
|
AC Building
|
DV Shed slab reinforcement work i/p
|
Cooling Tower
|
Compressor building
|
STG Building C row plastering i/p
|
RODM Building Internal plastering i/p
|
FFU Enclosure erection at 32 Mt STG Building
|
AC Building outside plastering work i/p
|
Raw Water Reservoir 2nd chamber
|
Service building tie beam shuttering works i/p
|
Final alignment of RWPH Bus duct with Ser. transformer
|
CW Ozonisation building plinth beam shuttering i/p
|
Compressor building external plastering i/p
|
AC Plant plastering work i/p
|
Staircase-2 handrail fixing work i/p
|
DV Shed internal plastering work i/p
|
CW make up piping to forebay
|
Service building column shuttering works i/p
|
Final scrubber to Gas pipeline vent connection u/p
|
Compressor building external plastering i/p
|
CW Ozonisation MCC room pedestal reinforcement i/p
|
DV Shed outer plastering work i/p
|
Grade slab shuttering work i/p at STG A row
|
CWTP Dosing foundation reinforcement work i/p
|
CEP discharge piping supports i/p
|
Chilled water pipe insulation i/p in AC Building
|
Raw water pump house brickworks i/p
|
CWPH maintenance bay grade slab rcc
|
GTG 14 Mt slab reinforcement work i/p
|
GBC west side road drain levelling work
|
Compressor building external plastering i/p
|
Nitrogen skid grouting completion
|
STG Floor
|
RODM Building
|
AC Building
|
DG Building
|
Computer and C&I room
|
Compressor building
|
GBC Building
|
Cooling Water Pump House
|
Switchgear room
|
Condenser rear side hinge assembly fit up
|
GTG Building 14 mt slab reinforcement work i/p
|
Compressor building outside plastering i/p
|
Soling works below HRSG i/p
|
Brickworks i/p in CWPH
|
DG Plant exhaust pipe works completion
|
STG Building C row plastering i/p
|
Cooling Tower cell 6 screeding i/p
|
Cable tray from HRSG to BFP NaOH dosing skid i/p
|
CWPH maintenance bay grade slab works
|
ETP Chamber 2 south side wall shuttering i/p
|
RWPH MCC building outside plastering i/p
|
CWPH unloading bay preparatory work for soling in progress
|
STG Building C row plastering in progress
|
AC Building inside plastering work in progress
|
CW Forebay handrail works in progress
|
HRSG Spray station area soling works in progress
|
DMCW South soling works in progress
|
Exaust Pipe erection for DG
|
GT Waterwash pit PCC Completion
|
STG GT IPBD erection in front of GCB
|
STG GT Oil filtration in progress
|
CW Ozonisation building slab staging works in progress
|
RW Reservoir 2nd chamber basin slab reinforcement in progress
|
Flare header work under progress in GCB
|
GBC B grouting under progress
|
Cable tray work along GCS in progress
|
Detergent flushing Piping works in progress
|
Compressor building external plastering in progress
|
DMCW RC Valve approach platform works
|
Hot oil circulation for STG GT in progress
|
Roof plates erection of DG enclosure in progress
|
ETP west side wall 1st lift concreting in progress
|
STG Gable end brickworks in progress
|
RW Reservoir 2nd chamber basin slab reinforcement
|
ETP west side wall shuttering work in progress
|
GBC Surge tank piping under progress
|
AC Plant brickwork in progress
|
GCS paving slab reinforcement work in progress
|
Service building tie beam works in progress
|
Compressor building
|
LCI Transformer metal filling works in progress
|
Gas Analyzer Room roof slab staging work in progress
|
STG Building C row plastering in progress
|
MOT area plastering work in progress
|
GSC floor bottom shuttering in progress
|
ETP East side wall raft reinforcement in progress
|
AC Building plastering work in progress
|
DG Plant acoustic enclosure work in progress
|
Compressor building external plastering in progress
|
Service building tie beam reinforcement works in progress
|
STG Building C row plastering in progress
|
GBC B row cladding works in progress
|
ETP Southeast corner Wall raft work in progress
|
DG PMCC Panels erection
|
Deaerator painting under progress
|
LP Turbine outer casing fit up under progress
|
Cooling tower pump house
|
GBC east side cladding works in progress
|
LP Turbine to generator alignment in progress
|
Cable tray work in CWPH MCC
|
BFP Suction Piping supports in progress
|
RWPH MCC building wall plastering in progress
|
ETP Wall deshuttering works in progress
|
CWTP Tie beam RCC in progress
|
STG Building B row brickworks in progress
|
UPS Room gypsum false ceiling work in progress
|
GT GT & GT UAT in charged condition
|
SEE room brickworks in progress
|
STG Building grid 1-2 plastering in progress
|
Compressor building brickworks in progress
|
Plinth beam de shuttering works in progress in ozonisation
|
Computer room MFB
|
STG transformer fire protection line erection
|
Ozonisation building plinth beam works in progress
|
Plastering in GCB east side
|
DG Building monorail finally alignment in progress
|
Lighting work for transformer yard in progress
|
Main tray from compressor house to CWPH
|
Compressor house brickworks in progress
|
GHC West side cladding in progress
|
CEP B leveling & alignment in progress
|
Cable tray work at compressor west side trench in progress
|
LP Turbine boxup completed
|
DG Building monorail alignment in progress
|
DMCW Pump Piping
|
RWPH MCC room brickworks in progress
|
Compressor building brickworks in progress
|
CWPH Service transformer-2 placed in foundation
|
Cooling tower cell 1 eliminator beam casting in progress
|
CWPH Service Transformer radiators erection
|
Cable tray work along compressor pipe rack in progress
|
Brickworks in progress in RWPH MCC room
|
Plastering works in progress in GCB
|
ACW piping to vaccum pump
|
Plinth beam bitumen painting in Service building
|
STG Building C row 5-6 grid brick works in progress
|
Cable tray support works along compressor pipe rack
|
DM transfer pump piping works in progress
|
Plastering works in progress in GCB
|
DMCW Motor blue matching in progress
|
Seal steam line erection
|
STG A row ventilation duct erection in progress
|
IBH Pipe insulation in progress
|
Cable tray support erection in progress from compressor to CWPH
|
LP BFP Suction Piping
|
DMCW Piping for MOT
|
Excitation room brickwork i/p
|
Cable tray work completion upto RWPH
|
Raw water reservoir chamber 1
|
STG Building C row plastering i/p
|
STG unloading bay concreting
|
CW Outlet channel walkway slab preparatory work in progress
|
STG Zero meter unloading bay reinforcement & shuttering work
|
Luxalon false ceiling in Control room panel area
|
GBC side cladding works in progress
|
GTG Roof slab reinforcement work in progress
|
Firefighting trench shuttering in progress
|
CCR light alignment works in progress
|
GTG Staircase pedestal deshuttering work in progress
|
MOT Lube oil cooling water piping in progress
|
Flash box drain header erection in progress
|
2nd CEP Pit shuttering work in progress
|
LP Casing cleaning in progress
|
CEP Pit wall shuttering in progress
|
HT Cable laying for CW Motor in progress
|
CW Pipe pedestal raft reinforcement work in progress
|
Cooling tower cell 1 east side wall shuttering in progress
|
STG GT Fire barrier wall works completion
|
GBC Wall cladding in progress
|
STG Building C row plastering in progress
|
ETP Wall south side final lift shuttering in progress
|
Column shuttering in progress in CW Ozonization building
|
Wall cladding in progress in GBC Building
|
CWPH Monorail beam alignment in progress
|
Insulation works on IBH Pipe
|
Vaccum pumps placed on foundation
|
LP Inner guide ring fixing in progress
|
Condenser wall deshuttering under progress
|
STG Building 3.5 mt level brick work under progress
|
3rd DMCW pump foundation reinforcement under progress
|
Cooling Tower Sludge pit raft
|
Soling works under progress for STG unloading bay
|
Power cabling of MOT drives
|
Vacuum pump foundation reinforcement in progress
|
Roof sheeting in progress in GBC Building
|
IBH Pipeline insulation
|
Plastering works in progress along C row of STG Building
|
STG A Row grid cladding runner erection in progress
|
ETP Wall 2nd lift shuttering in progress
|
STG GT IPBD Inspection cover fixing
|
Sludge pit raft reinforcement work in progress
|
Brick masonary under progress
|
Switchgear room
|
Cable tray work along CWPH east side
|
CBD & IBD Tanks interconnection sheeting work
|
LP Turbine roll check
|
Slipring Shaft placement & prealignment checks
|
Plate fixing in progress for grade near DMCW Pit
|
CW Outlet channel wall works in progress
|
Transformer Yard
|
ETP Southside wall shuttering in progress
|
Grade slab reinforcement of LAVT & SPVT foundation
|
GT Hall lighting works in progress
|
STG Vapour Exhaust Piping work
|
BFP Building
|
Raw water reservoir & RWPH
|
GBC Building & Gas Conditioning Skid
|
Cooling Tower, CWPH & RODM Building
|
AC Building
|
FG line erection in road crossing pipe rack
|
CPHRC Pump suction piping
|
CW Outlet channel wall final lift reinforcement
|
ETP North side Wall 2nd lift shuttering in progress
|
Compressor building roof screed concreting
|
BFP 14 mt roof slab insert plate fixing in progress
|
CW Outlet channel wall shuttering in progress
|
Luxalon false ceiling in Control room panel area
|
STG IPBD Wall frame fixing
|
CBD Tank sheeting in progress
|
CW Pipe encasing
|
STG Generator Box up in progress
|
DG Plant parapet wall shuttering i/p
|
LT Bus duct alignment in CWPH
|
BFP-B Pneumatic test preparation
|
CPHRC pump discharge piping
|
Air guide ring erection u/p in STG
|
Inspection chamber encasing
|
Turbine compartment vent duct erection
|
Cable tray interconnection works near GBC
|
ETP Wall reinforcement works in progress
|
Generator Rotor to LP alignment checking under progress
|
DG building slab reinforcement
|
STG Cross around pipe erection
|
Steam blowing pipeline erection
|
Alignment of SPBD for STG UAT
|
GTG Gable end cladding welding works in progress
|
Gypsum board fixing at Control Room
|
GBC Building
|
Polycarbonate sheet fixing at STG Roof
|
Compressor building destaging completion
|
STG UAT Firewall brickwork in progress
|
Brickworks in progress at AHU Room
|
Cleaning in progress on TG Deck raft
|
CPHRC pump discharge piping
|
DG building slab beam shuttering
|
30 mt roof slab deshuttering works
|
HW Pipeline inspection chamber shuttering
|
GT BC Bay gable end wall cladding sheeting
|
RODM MB tank AR Tile fixing
|
GTG Gable end B to C Cladding erection
|
ETP Pipeline wrapping coating test under progress
|
Cable trench wall near RWPH
|
Control Room
|
LP Rotor to Generator Rotor alignment
|
CEP Pit area grade slab reinforcement fixing
|
GTG Gable end sag rod fixing
|
ACW Piping
|
DMCW Discharge Piping
|
Assembly of vent duct load compartment
|
Erection of CWPH MCC
|
SEE Panel erection
|
BFP Building 14 mt slab shuttering
|
23 mt parapet wall concreting
|
BFP-B lube oil piping
|
LCI HT Cable terminations
|
CWPH MCC Building roof screeding
|
ETP Raft reinforcement works
|
AC Plant roof water treatment paint works
|
STG Roof Slab Reinforcement works
|
Drain header insulation in progress
|
HRSG MOV Cabling
|
DV Shed at GT north
|
Compressor House Roof slab shuttering
|
Cable tray supports along GBC to CWPH Piperack
|
Enclosures welding in GT GT IPBD
|
STG Lube Oil drain piping
|
GBC Lube Oil Flushing in progress
|
GT Turbine compartment CO2 piping
|
CW Pump discharge piping in progress
|
CW Outlet Channel reinforcement work in progress
|
Compressor Building
|
LCI DM water system flushing
|
Erection of STG UAT Radiators
|
LP MS Drains insulation
|
LP Rotor Placement
|
Reinforcement work near DMCW tank
|
GT Fire fighting system flushing
|
GTG Exciter side end shield fixing
|
Duct bank deshuttering at RODM
|
LP BFP-B Grouting
|
Slab shuttering in Compressor Building
|
GBC Building & Gas Conditioning Skid
|
STG Rotor Insertion
|
Cooling Water Pump House
|
CWTP & CWPH MCC Building
|
STG Building
|
Cooling Tower, CWPH & RODM Building
|
Raw Water Reservoir Chamber 1
|
Deaerator placed over FST
|
STG Roof Slab Reinforcement works
|
CPHRC Pump frame alignment
|
Ventilation duct erection in 19 Meter
|
HRSG Filling Pipes work
|
HRH & CRH Piping
|
SH & RH Drain Insulation
|
Compressor Building Roof slab shuttering
|
Gas Conditioning Skid
|
GT IBH Pipeline erection
|
Fuel Gas Pipeline normalisation
|
HP Desuperheater Insulation in progress
|
Deck sheeting of CW Pump house
|
LP Rotor taken out for clearance checking
|
TG Operating floor reinforcement work
|
LP BFP Foundations
|
CO2 Building Foundation Concreting
|
GT South side Grade Slab Reinforcement
|
Pumps erection in AC Plant
|
GT IBH piping fit up
|
Oil Canal Wall reinforcement
|
ACW Piping
|
STG Gable end piperack structure erection
|
CWPH MCC Building
|
LCI Skid placement on foundation
|
ACW Pipe preassembly works
|
Cooling Tower Cell 3 Fan casting
|
Ventilation duct erection in GTG area
|
Erection of STG UAT Radiators
|
Cladding Post Erection in STG Building
|
Bitumen painting in partition wall of Cooling Tower
|
Static Excitation Room Slab supports work
|
GT South side Grade Slab
|
Piperack gallery erection along STG Staircase
|
Insert cover assembly erection in GTG
|
Cable tray work alongwith BFP building
|
GT GT metal soling filling
|
Reinforcement work for CO2 rack foundation
|
GT Exhaust Compartment Enclosure works
|
DG Building Staging works
|
Piping works in front of RWPH
|
Cable tray along inter plant trench
|
Duct Bank 8 shuttering
|
CWPH Drop Wall Beam Shuttering
|
AC Building
|
GBC MCC Building
|
Cooling Tower & Compressor Building
|
Raw Water Reservoir Chamber 1
|
Cable gallery at STG Building 0Meter
|
Compressor Building
|
Shuttering work in STG Operating Floor
|
Reheater header sheeting
|
Cable tray work between BFP & HRSG Pipe Rack
|
Erection of IPBD Permanent Supports
|
Transformer Yard (GTG side)
|
Transformer Yard (STG side)
|
GT Area (South Side)
|
GT Inlet Air Filter Duct
|
Condenser & CW Pipes
|
STG Critical Piping
|
MOT & Lube Oil Coolers
|
Placement of RODM Service Transformer
|
STG Building
|
Cooling Tower, CWPH & RODM Building
|
GBC Building & Gas Conditioning Skid
|
Raw Water Reservoir Chamber 1
|
Raw Water Pump House
|
Gas Booster Compressor Building
|
GT and Auxiliaries
|
Cooling Water Pump House
|
HRSG & Chimney
|
BFP & STG Building
|
STG Lube Oil Duplex Filter Erection
|
Fencing Post erection
|
Cable trench in BFP Building
|
AC Plant slab pedestals
|
Lintel beam concreting in Compressor building
|
Cable tray work
|
LCI Floor Reinforcement
|
CW Outlet Channel
|
Raw Water Reservoir Chamber-1 Water Filling
|
DMCW Monorail erection
|
CW Ozonisation Building Excavation Work
|
ST UAT Fire Barrier Wall
|
Runner Channel Erection in STG A-row
|
GT Inlet Duct Erection
|
Slab Ready for concreting in AC Plant
|
GBC MCC Building
|
CW Pipe Encasing
|
Silencer Panel erection in progress
|
TG operating floor slab reinforcement works
|
Interplant Cable Trench
|
AC Building
|
GBC Building
|
CWPH MCC Building
|
Raw Water Pump House
|
AC Ducting in Control Room
|
Cooling Tower
|
Condenser Rear Water Box Erection
|
Cooling Water Piping
|
APU Skid
|
FFU Enclosure Erection
|
Aluminium partition in Control Room
|
Fire barrier wall in STG UAT area
|
Cable Tray supports for GBC MCC
|
Transformer Yard
|
AC Building area
|
Raw Water Pump House
|
Raw Water Reservoir Chamber 2
|
Road near Raw Water Reservoir
|
Vent duct to 0 meter cable gallery
|
IBD & CBD Tanks
|
Cooling Tower Riser Pipes
|
GBC MCC Building
|
Cooling Water Pump House
|
IP Eco Feed Insulation
|
GT Exhauat Compartment Roof Erection
|
EOT placement in RWPH
|
Piperack Erection near BFP
|
Control Room Floor tiling work under progress
|
3.5 Meter Switchgear Room
|
Crane Girder Erection in CWPH
|
GT Exhaust Compartment Vent Fan
|
Raw Water Pump House MCC area
|
CW Forebay
|
Transformer Yard
|
GT Inlet Aie Filter Transition Duct
|
Riser Pipe Encasement
|
WPH Inlet Header Insulation
|
CW Pipe Encasing
|
CWPH Roof Assembly Erection
|
CW Forebay area
|
CBD & IBD Foundation
|
Pipe Rack between HRSG & BFP
|
Gas Conditioning Skid
|
Boiler- HP,IP & LP Drum area
|
GBC MCC Building area
|
RODM MCC Room
|
Cooling Tower
|
AC Building area
|
3.5 Meter Switchgear Room
|
Ventilation Ducting
|
BFP Building area
|
DMCW Pipe erection
|
GT & Auxiliaries
|
RWPH MCC Room area
|
Raw Water Reservoir Chamber 2
|
CW Pipe Encasing
|
Effluent Treatment Plant area
|
Raw Water Pump House area
|
Hot Water Pipe Encasing
|
RODM plant Area
|
STG IP Bus Ducts
|
Pipe Pedestals
|
AC Building area
|
GT & Auxiliaries
|
Inlet Air Filter Module Erection
|
Cooling Water Pump House
|
HRSG North Side View
|
GBC Building
|
Cooling Tower
|
Pipe Rack
|
Effluent Treatment Plant
|
RODM Dosing Skid
|
Raw Water Reservoir Ch.2
|
Raw Water Pump House
|
Raw Water Pump House MCC Building
|
Raw Water Reservoir
|
Road near raw water reservoir
|
GT Accessories
|
Seal Oil Pit
|
Cooling Water Pump House
|
BFP Building & HRSG
|
Ventilation Ducts in STG Building
|
Transformer Yard
|
GCS Drain Pit
|
Gas Conditioning Skid
|
RODM Bulk Chemical Tanks
|
GBC MCC Building
|
DM Water Tanks
|
CW Pipes
|
Transformer Yard
|
Effluent Treatment Plant
|
Generator Transformer
|
Switchgear Room
|
Raw Water Pump House
|
GT Superstructure
|
GT Accessory Base
|
GBC Building
|
BFP Building
|
STG Superstructure
|
Cooling Tower
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|