Mill reject system compressors Ern I/P
|
U2 FD fan 2B lube oil flushing I/P
|
U2 LHS Mills Duct erection I/P
|
U2 Seal air fan erection work started
|
U2 BOF to ESP Duct in completion stage
|
U1 RHS lift sheeting and guide channel I/P
|
U1 RHS lift sheeting and guide channel I/P
|
U-1 LHS view, Painting I/P in coal pipes
|
U-2 BOF to ESP Duct Erection
|
U-2 PA 2B fdn status- NTPC
|
U-2 FD fan 2 B
|
Compressor ACW supply line upto strainer flushing
|
U-1 Safety valves floating completed on 11.11.19
|
Approach to Unloading bay TG2- NTPC
|
Approach to “A” Row, TG-2 - NTPC
|
U2 CD bay approach - NTPC
|
U2 ESP control room status -NTPC
|
U2 PA -B fdn status - NTPC
|
U2 FD B area water logged and not backfilled/NTPC
|
U1 Silo fdn area full with water -NTPC
|
U-2 ID fan A Boxed up for readiness of fan trial
|
U1 LHS bunker roof sheet completed, side sheet I/P
|
U-1 Full load achieved on 02.10.19
|
U-1 LHS mills duct insulation (Mill J only balance
|
U-1 PAPH LHS hot duct insulation
|
U1 LHS Coal feeders
|
U1 RHS bunker side sheeting work
|
U1 RHS bunker side sheeting work
|
U-1 Boiler painting with airless sprayer M/c
|
U2 PA B FDN STATUS BY NTPC
|
U2 FD B FDN STATUS BY NTPC
|
U1 LHS Mill duct insulation
|
U1 RHS Bunker side roof sheeting
|
U-2 BOF to ESP (ABC pass) welding i/p
|
U-2 CD bay approach -NTPC
|
U-1 LHS PA hot Bus duct insulation in completion
|
U-2 FD A to SAPH A insulation
|
U-2 PA 2B fdns status by NTPC
|
U-1 LHS mills Duct insulation I/P
|
U-1 RHS Bunker shell painting
|
U-1 RHS bunker roof
|
U-2 FD B silencer preassy I/p
|
U-2 Boiler NDHT done on 24.08.19
|
U-2 CD bay approach -NTPC
|
U-2 CD bay approach -NTPC
|
U-1 LHS mill duct insulation
|
U-1 LHS mills
|
U-2 ESP outlet insulation
|
Unit -2 BOF to ESP duct status
|
Unit -2 ESP to ID duct insulation completed
|
Unit -2 ESP control room building - NTPC scope
|
Approach road to Untit-2
|
Unit -1 LHS bunker view
|
Approach from "A" row side
|
Unit -2 CD bay approach
|
Unit-2 RHS FD and PA fdns status
|
Unit-2 RHS FD and PA fdns status
|
RHS Hot PA Bus insulation
|
Unit-1 BOF to ESP insulation started
|
Unit-1 LHS Bunker bottom hopper preassembly in progress
|
Unit-1 BOF to ESP pass D,E,F ATT completed
|
Unit-2 FD and PA fan A silencer erected
|
Unit-1 LHS Bunker bottom hopper reassembly in progress
|
Unit-1 RHS-Last PA duct erection In Progress
|
Unit-1 Mill-A Lube oil flushing started
|
U-2 FD fan A silencer ern
|
Unit-1 LHS mill duct connection
|
Unit -1 PA fan B
|
Unit-2 FD fan A lube oil flushing started
|
Unit-1 FD TO APH Insulation
|
Unit-1 MILL -B lube oil flushing in progress
|
Unit-2 FD A Lube oil piping In progress
|
Unit-2 Pass AB BOF to ESP Structure Erection
|
Unit-1 LHS Mill Bus duct
|
Unit-1 PA 1B Discharge Duct Scaffolding in progress
|
Unit-2 RHS Bunker Hopper Bottom erection
|
Unit-2 RHS LIFT sheeting started, Pit& M/c room
|
UNIT-1 PA FAN B MOTOR 8 hr TRIAL UNDER PROGRESS
|
Unit-1 LHS bunker last mill tipper floor balance erection
|
U1 front&Rear bottom enclouser insulation complete
|
Unit-1 front&Rear bottom enclouser insulation complete
|
Unit-1 Seal Air header & Seal air fan
|
U1 FD 1A discharge duct Insulation pin fixing I/P
|
Unit-1 Mills A,B,C Lube oil piping work in progress
|
Unit-2 Pass A Hopper Insulation In Progress
|
Unit-2, Pass-D balance hopper erection In Progress
|
Unit-2 FD fan A silencer pre assembly in progress
|
ESP-2, F pass roof purlin str work I/P
|
Unit-1 SAPH-A BOX-UP work In Progress
|
Unit-1 RHS Tempering duct to mill duct In Progress
|
Unit-1 Seal air to mill connection In Progress
|
Unit-1 Seal air header completion In Progress
|
Unit-1 PA FAN B motor termination and testing In Progress
|
Unit-1 RHS mills lube oil piping In Progress
|
Unit-1 RHS Hot PA Ducts to MIlls area
|
Unit-1 LHS last bunker shell erected
|
Unit-1 LHS Bunker, feeder floor front handed over
|
Unit-1 ESP Outlet bottom insulation &sheeting work in progress
|
Unit-2 ESP Outlet D,E,F scaffolding In Progress for ATT
|
Unit-1 Seal Air fans
|
Unit-1 FD FAN 1A
|
Unit-1 LHS lift work started by M/s Techno
|
Unit-1 ESP to ID Insulation
|
Unit-2 ESP Outlet insulation started
|
Unit-2 ID FAN A Lube oil flushing I/P
|
Unit-2 ESP D PASS balance hopper preassy and ern
|
Unit-2, TP 10 Outside landing platform erection work in progress
|
U2 BOF AB pass BOF to ESP Duct structure frames erection
|
Unit-2 ESP to ID Duct ABC Pass ATT completed
|
Unit-2 BLR HT with IBR done on 04.12.18
|
Unit-1 LHS cable trestle foundation work by NTPC
|
Unit-1 LHS cable trestle foundation work by NTPC
|
ESP -2 control room status by NTPC
|
Unit-1 PA fan A Impeller housing blue matching In Progress
|
Unit-2 BOF to ESP AB Pass Duct support frame erection
|
Unit-2 BAH foundation excavation started by NTPC
|
Unit-2 BAH foundation excavation started by NTPC
|
Unit-2 PA Header LHS erection
|
Unit-2 ESP Pass-A side wall and hopper insulation in progress
|
Unit-2 ESP Pass-D balance hopper erection in progress
|
Unit-1 FD A LOP erection and fan alignment work In progress
|
Unit-1 PA fan B LOP is ready for flushing
|
Unit-1 PA Fan A
|
Unit-2 ESP outlet scaffolding and Pin fixing in progress
|
Unit-1 LHS last bunker shell per-assembly In progress
|
Unit-1 LHS Bunker view
|
Unit-2 Bottom Ash hopper Foundation work started by NTPC
|
Unit-2 PAPH B Axial seal in progress
|
Unit-2 SAPH A Support bearing LOP
|
Unit-2 ID fan 2A LOP work started
|
Unit-1 rear side bottom enclouser insulation
|
Unit-1 LHS lift sheeting
|
Unit-1 Boiler chemical cleaning completed
|
Unit-1 chemical cleaning, citric acid addition start
|
Unit-1 alkali boil out with hot and cold rinsing completed
|
Unit-2 critical pipe support structure column erection
|
Unit-1 BLU for chemical cleaning on 20.11.18
|
Unit-1 Boiler insulation
|
Unit-1 Boiler insulation
|
Unit-1 Boiler insulation
|
Unit-1 Boiler insulation
|
Unit-1 Boiler insulation
|
Unit-1 ESP
|
Unit-1 ESP
|
Unit-1 ESP
|
Unit-1 ESP
|
Unit-1 ESP
|
Unit-1 ESP Last inlet funnel Pass #A insulation in progress
|
Unit-1 SAPH B Insulation in progress
|
U1 LHS last Bunker ring beam erected
|
Unit-2 Bunker bottom part hopper pre assy in progress
|
U1 chemical cleaning, cold rinsing is planned today
|
Unit-1 LHS last Bunker roof structure column erection
|
U2 SAPH A Bottom Duct ereted
|
Unit-2 D row MS Line support cantilever frame erection
|
Unit-1 BRP Trial run for 4 hrs in progress
|
U1 MS Line insulation
|
U1 CRH Line insulation
|
U1 CRH Line insulation
|
Unit-2 TPs side platform str pre assembly In Progress
|
Unit-2 LHS Cable Trestle foundation civil work by NTPC
|
Unit-2 SAPH B Pin Rack Alignment in progress
|
Unit-2 PAPH -A bottom Duct pre assembly
|
Unit-1 auxiliary steam system insulation started
|
Unit-1 auxiliary steam system insulation started
|
Unit-2 FD A and PA fan A grouting
|
Unit-1 Drain oil tank and Pump Foundation
|
Unit-2 D row pipe support cantilever Preassembly in progress
|
Chemical cleaning N-Pit civil work completed
|
Unit-2 BOF to ESP Foundation Str frames preassembly in progress
|
Unit-1 BRP Commissioning In Progress- vendor available at site
|
Unit-2 RHS Coal Pipes erection
|
Unit-2 RHS Coal Pipes erection
|
Unit-1 PA header interconnection Duct In progress
|
Unit-1 RHS Mills Seal Air Piping work in progress
|
Unit-1 LHS last Bunker Ring beam support erected
|
Unit-2 PAPH bottom ducts Pre assembly in progress
|
Unit-2 PAPH bottom ducts erection in progress
|
Unit-1 BOF to ESP bottom part Scaffolding pipes
|
Unit-1 Boiler bottom enclosure insulation
|
Unit-2 Bunker bottom hopper pre assembly
|
Unit-1 FD fan 1A
|
Chemical cleaning drain pipe to Pit work in progress
|
Unit-1 chemical cleaning system,motor trial is planned
|
Unit-1 HPSU commissioning work, vendor available
|
Unit-1 LHS lift sheeting work
|
Unit-1 Boiler Gun trial carried out on 28.10.18
|
Unit-1 FD fan 1A
|
Unit-1 Chemical cleaning preparatory work.
|
Unit-1 Furnace insulation completion
|
Unit-1 Furnace bottom enclouser insulation
|
U2 LHS mills seal air piping work in progress
|
Unit-1 RHS Duct to Mills
|
Unit-1 LHS Mills and coal piping
|
Unit-2 Bunker bottom hopper pre assembly
|
Unit-1 LHS lift sheeting work
|
Unit-1 SAPH to Hot interconnection duct insulation
|
Unit-1 BOF to ESP duct welding in progress
|
Unit-1 BOF to ESP duct welding in progress
|
Unit-1 ESP Top view
|
Unit-1 Eco Hopper scaffolding completed
|
Unit-1 FD fan 1A
|
Unit-1 FD discharge interconnection duct completed
|
Unit-1 last bunker ring beam post Preassembly in progress
|
Unit-1 CRH along with RH HT in progress
|
Unit-1 Furnace insulation completion
|
Unit-2 RHS Bunker roof stair work
|
Chemical cleaning N-pit work status
|
FOPH Pump Alignment and cleaning work
|
Unit-1 chemical cleaning preparatory work
|
Unit-2 PAPH Hot Air inlet preassy in progress
|
Unit-1 LHS Bunker
|
Unit-1 FD discharge interconnection duct completion
|
Unit-1 Last Bunker ring beam and hopper preassy
|
Unit-1 Last Bunker ring beam and hopper preassy
|
Unit-1 ESP inlet funnel insulation
|
Unit-1 ESP inlet funnel insulation
|
Unit-1 PA Fan -A Foundation not handed over by NTPC
|
FD Fan 1A
|
PA 1B Lube oil piping started
|
Unit-2 LHS Bunker
|
Unit-1 RHS Bunker
|
Unit-2 Piping cantilever frame preassy in CD bay
|
Unit-2 RHS Mills
|
Unit-2 Bunker RHS View
|
Unit-1 RHS MILLS LOP FDN WORK STARTED BY NTPC
|
Unit-2 PIPING SUPPORT STR FDN BY NTPC
|
Unit-1 LHS LIFT SHEETING WORK
|
Unit-1 BOF TO ESP scaffolding work
|
ESP 1 Inlet funnel insulation
|
ESP 1 Inlet funnel insulation
|
Unit 1 FD FAN A WORK STARTED
|
UNIT 1 LHS BUNKER
|
Unit 2 RHS BUNKER VIEW
|
Unit 1 PA fan B LOP Skid and piping work
|
Unit 1 chemical cleaning preparatory work
|
Unit 2 RHS Mills seal air piping work
|
Unit 2 RHS Mills seal air piping work
|
Unit-2 ESP
|
Unit -1 outlet funnel insulation completed
|
Unit 1 seal air piping work
|
Unit 1 Furnace insulation in finishing stage
|
Unit-1 SAPH B Air motor decoupled trial done
|
Unit #2 RHS Mills
|
Unit #2 FD A work in progress
|
Unit #2 ESP Outlet duct ATT in progress
|
ESP #1 Outlet Funnel Insualation
|
ESP #1 Outlet Funnel Insualation
|
ESP #1 Outlet Funnel Insualation
|
ESP #1 Outlet Funnel Insualation
|
Unit -1 wind box Duct insulation and sheeting
|
Unit-1 LHS bunker erection
|
Unit-1 ID fan B- trial done
|
Unit-1 BOF to ESP LHS Duct erection completed
|
Unit-1 LHS Lift Sheeting work
|
Unit-1 LHS Bunker
|
Unit-1 LHS BOF to ESP
|
Unit-2 RHS Bunker shell erection
|
Unit-1 LHS Lift Sheeting Work started
|
Unit-1 LHS Mills area
|
Unit 1 LHS BOF to ESP
|
Unit-2 RHS Bunker view
|
Hot secondary air interconnection Duct insulation
|
UNIT 1 MILLS H & J erection
|
UNIT 1 LHS BUNKER
|
Unit 1 ID Fan B Motor Bump Trial Taken
|
Unit 1 LHS BOF TO ESP
|
Unit 2 ESP to ID Duct area
|
Fuel oil pump house
|
Fuel oil pump house
|
Last gallery from Unit 2 RHS Bunker to TP11 erected
|
Unit-1 LHS BOF to ESP
|
Unit-2 RHS Bunker to TP-11 gallery pre- assembly
|
Compressors commissioning in progress
|
Unit-2 RHS Bunker
|
Unit 1 LHS Bunker and Mills
|
Unit-2 gallery erection in between TP11 and TR3
|
Unit 1 LHS BUNKER and MILL-H
|
Unit 1 BOF TO ESP LHS Duct area
|
Unit-1 BOF to ESP LHS Duct structure in progress
|
Unit-1 BOF to ESP LHS Duct structure in progress
|
Unit #2 gallery erection in between TP10 and TR3
|
Unit #2 gallery erection in between TP10 and TR3
|
Unit #1 BOF to ESP
|
TP-9 floor completion work
|
Unit #1 Mill H
|
Unit#1 Seal air fan
|
Unit-2 ESP
|
Unit-1 Seal air fans erection started
|
Unit-1 LHS lift painting work
|
Unit-1 LHS lift pit work by civil agency
|
Mill-1H erection work started
|
Unit-1 RHS Mills
|
Unit-2 LHS mills
|
Unit -2 ESP outlet Duct
|
Unit -2 ESP outlet Duct
|
Unit-1 LHS BOF to ESP Duct structure
|
Furnace lower LHS insulation
|
Unit-2 RHS Bunker
|
Unit-1 BOF to ESP
|
Unit-1 LHS bunker
|
SG - DMCW system
|
Unit-1 PA header Duct preassembly & erection
|
Unit-1 LHS BOF to ESP
|
Unit-2 TP 11 structure
|
Unit-2 RHS Bunker
|
Unit-1 BOF to ESP
|
Unit-1 PA header Pre-assembly
|
Unit-1 LHS Stream BOF to ESP duct
|
Unit-1 PA 1A Silencer erection
|
Unit#1 BOF to ESP
|
Unit#2 ID outlet Ducting
|
Unit #1 LHS Bunker
|
Unit#1 LHS FD and PA fans Silencer erection
|
Unit #1 ID outlet insulation
|
Unit #2 TR-3 Erection
|
Unit#2 TP-11 Structure
|
Unit#2 RHS Bunker
|
unit #1 LHS bunker str erection
|
Unit#2 ESP to Chimney
|
Unit-2 ESP to ID Duct area
|
Unit-1 ESP to ID Duct- ATT completed
|
Unit-1 BOF to ESP
|
Unit-2 TP gallery pre-assembly under progress
|
Unit-2 RHS Mills
|
Unit-2 RHS bunker Hopper assembly in progress
|
Unit-1 RHS stream BOF to ESP
|
Unit-1 Left stream ESP inlet
|
Unit-1 ESP outlet ducting - ATT in progress
|
Unit-1 ESP outlet ducting - ATT in progress
|
Unit-2 BOF to ESP Pass-AB duct foundation
|
Unit-1 LHS stream fan foundation
|
Unit-1 ID to Chimney insulation
|
Unit-1 BOF to ESP Ducting area
|
Unit-1 BOF to ESP Ducting area
|
Unit-2 RHS bunker and TP-11 area
|
Unit-2 Boiler Erection under progress
|
FD fan- 1B area
|
Unit-1 SG DMCW system
|
Unit-1 LHS Bunker area
|
ESP-2 and BOF to ESP Pass AB area
|
Unit-2 RHS mills and Coal Piping work
|
Unit-1 ID fan to Chimney insulation work
|
Unit-1 ESP to ID duct- ATT in progress
|
Unit-1 LHS bunker erection
|
LHS Fan foundation
|
Unit-1 LHS Stream Boiler outlet flange(BOF) to ESP duct
|
Unit-1 ESP insulation and sheeting work
|
Unit#2 APH and Connecting Ducts
|
Unit#1 BOF to ESP, Pass A&B
|
Unit #2 RHS View
|
Hopper & insulation work of ESP1
|
Insulation & Sheeting work of ESP-1
|
Unit-2 ESP outlet Duct
|
Unit-2 ID fan to Chimney Duct
|
Boiler# 2 - RHS Bunker
|
Boiler #2 LHS view
|
Unit #1 RHS Mills
|
Unit #1 RHS Bunker
|
FD Fan 1B
|
ESP#1 outlet to chimney duct
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|