GADARWARA (2X800 MW)


Front for service bldg elevator not avlble

Unit 1 TG : Handed over

TG Unit 2: Synchrinised on 26/8/20

Unit 2 : Synchronised on 26.8.20

TG Unit 2: LPT - 2 replacement done

U2 BLR LHS Overview

u2 esp overview

U2 ESP Control room

u2 mrs : silo erection completed

plant overview

Control room overview

Control room overview

front for service bldg elevator erection not avlbl

U2 BLR : All fans commissioned

Compresser house

HGP : Storage sheds

Unit-2 control room

Compressed Air system: PG test completed

TG Unit-1 overview

HGP : Storage sheds

Power suply upto HGP MCC Incomer not given by NTPC

HGP Building: Erection completed

HGP Building: Erection completed

HGP Building: Erection completed

HGP Building: Erection completed

HGP Building: Erection completed

U2 BLR LHS Overview

TG2 : LP2 rotor replacement u/p

TG2 : LP2 rotor replacement u/p

BLR 2 LHS Mills: MRS erection u/p

Front for service bldg elevator not avlble

Unit 2 TG : Front for elevator erection not avlble

Unit 2 BLR: LHS Mills commissioned

Unit 2 TG : Front for elevator erection not avlble

Front for service bldg elevator not avlble

Unit 2 MRS : Front for LHS Air receiver not avlble

Unit 2 TG : Front for elevator erection not avlble

Front for service bldg elevator not avlble

Hydrogen plant MCC erected

Front for service bldg elevator not avlble

Hydrogen generation plant erection u/p

BLR -2 : steam blowing u/p

Unit 2 TG : Front for elevator erection not avlble

BLR 2 LHS Mills: MRS front not available

FGD erection U/p by NTPC

Unit 2 ESP control room elevator erection u/p

1st coal rake entered NTPC Gadarwara on 27.11.191

BLR 2 LHS Mills: MRS front not available

Railway line work u/p outside the plant

HGP erection under progress

BLR 2: Insulation work u/p

BLR -2 : Repair work u/p for RH & SH joints

Unit 2 MRS : Silo erection under progress

Unit 2: FGD erection u/p by NTPC

Unit 2: FGD erection u/p by NTPC

Unit 2 ESP: Pass E&F commissioned

Unit 2 ESP control room: All cabling completed

u2 blr insulation u/p

u2 blr: lhs mills commg u/p

Unit 2 MRS : silo erection u/p

U1 TG elevator load test u/p

Front for TG Unit2 elevator erection not available

Front for Adm Bldg elevator erection not available

Front for service bld elevator erection not avlble

BLR unit 2: MRS front for LHS mills not available

Hydrogen generation plant erection started

Hydrogen generation plant erection started

plant overview

BLR -2 : Mill 2J erection u/p

Front for Adm Bldg elevator erection not available

Railway line work u/p

BLR -2 : Repair work u/p for RH & SH joints

BLR 2: LO skid foundation not available for Mill J

BLR 2 LHS Mills: MRS front not available

Unit 2 TG : Front for elevator erection not avlble

Front for service bldg elevator not avlble

Unit 1 TG elevator erection under progresss

BOP overview

BLR 2 LHS Mills: MRS front not available

Esp unit 2: Cabling under progress in Pass A,B,C

Unit 2 BLR: Mill J erection under progress

Unit 2 TG: TDBFP commissioning u/p

Unit 2 MRS : Silo erection under progress

Unit 1 TG elevator erection under progresss

unit 2: Generator transformer overview

Front for service bldg elevator not avlble

Unit 2 TG : All 3 CEPs commissioned

Unit 1 Boiler : Goods elevator commissioned

Unit-1 TG elevator erection under progresss

U2 MRS : silo erection under progress

Hydrogen plant building ready

Railway line work u/p inside the plant

Railway line work u/p outside the plant

U2 BLR : All RHS Mills trial completed

U2 BLR LHS Mills:LO skid fdn & MRS front not avlbl

Unit 2 TG : Front for elevator erection not avlble

Hydrogen plant building under construction by NTPC

TG Unit 2: Enclosure for elevator erectn not avlbl

U 2 BLR : Mill 2J erection u/p

Unit 2 Generator transformer overview

U2 MRS:Silo erection heldup due to trench excavatn

Unit 2 TG : Deareator floor

U 2 BLR : MRS erection Front for Mill 2A not avlbl

Unit 2 BLR: LHS feeder floor

Unit 2 BLR: LHS trippler floor

TG Unit 1: Flow nozzle erected for PG test

Unit 2: Cable laying u/p in ESP Pass A,B,C

H2 generation plant building under const. by NTPC

BLR 2 LHS Mills: LO skid foundation not available

Front for service bldg elevator not avlble

TG1 elevator shaft plastering u/p by NTPC

Hydrogen plant building under construction by NTPC

Hydrogen plant building under construction by NTPC

Unit 2 TG : Deareator floor

Unit 1 TG Floor

Unit 1: TG elevator shaft plastering u/p by NTPC

U2 BLR : RHS feeders trial completed

Front for service bldg elevator not avlble

TG1 elevator shaft plastering u/p by NTPC

U2 BLR : LHS mills LO skid fdn not avlble

U2 BLR : Front for MRS erection nor avlble

TG2 put on barring gear

Hydrogen plant building under construction by NTPC

Front for admin bldg elevator not avlble

TG1 elevator shaft plastering u/p by NTPC

plant Overview

CHP overview

plant Overview

Front for service bldg elevator not avlble

AHP overview

Unit 2 BLR : ID fans overview

Unit 2 ESP control room overview

Unit 2 Boiler RHS Mills overview

Hydrogen plant building under construction by NTPC

Unit-2 Boiler : Front for MRS erection nor available

FD fan-2B & PA fan-2B overview

FD fan-2A & PA fan-2A Fan overview

plant Overview

Unit 2 Boiler LHS Mills overview

CHP overview

Unit 2 TG floor

Hydrogen plant building under construction by NTPC

plant Overview

Unit 2 Boiler 0meter overview

Unit 2 CPU: Service area HT completed

Unit-2 Boiler : ID Fan 2A overview

BOP overview

BOP overview

Unit-2 ESP RHS cabling under progress

Unit 2 Boiler LHS overview

Unit-2 MRS : Silo erection started

Unit-2 Boiler : LHS Mills overview

Unit 2 Boiler : RHS MRS front not available by customer

Unit 2 TG: TDBFP erection under progress

Unit 2 TG erection under progress

Unit 2 ESP control room overview

CHP overview

Hydrogen plant building under construction by NTPC

unit 2 TG elevator front not available

Unit-2 Boiler: RHS overview

unit 2 blr : LHS feeder floor

Unit-2 TG floor

Unit-2 Boiler: Mill 2G side assembly erected

FD 2A & PA 2A Fan overview

Unit 2 :BFD piping HT completed

plant Overview

Unit 2 boiler chemical cleaning under progress

Unit 2 BLR RHS : MRS trench excavation under progress by NTPC

Unit 2 : CD bay excavated by NTPC

Hydrogen plant building under construction by NTPC

Unit 2 Boiler Lighted up on 31.12.18

Unit 2 ESP overview

Unit 2 Boiler Lighted up on 31.12.18

Unit- 2 Boiler : LHS overview

unit 2 BLR RHS : feeder erection u/p

Unit 2 MRS : Silo foundation handed over by NTPC

Hydrogen plant building under construction by NTPC

Unit-2 TG : CEPs erected

Mill 2F : Foundation yet to be handed over by customer

Mill 2J : Foundation yet to be handed over by customer

Unit-2 ESP: LHS cable trestle not available

Unit-2 MRS : Silo foundation under construction by Customer

CPU : Regen area overview

Unit-2 Boiler : chemical cleaning setup erected

Unit-2 TG : Deaerator insulation under progress

Unit 2 CPU : service area piping under progress

Unit 2 MRS : Silo foundation not available

Unit 2 Boiler : LHS feeder floor not yet handed over by customer

Unit-2 Boiler: RHS trippler floor not yet casted

Unit-2 Boiler: LHS Mills foundation not handed over by customer

U#2 SADC cylinder erection under progress

U#2 TDBFP-A alignment work under progress

U#2 CEP pump/motor coupling under progress

Mill 2H: Baseplate levelling work under progress

Unit 2 CPU : service area piping under progress

Hydrogen plant building under construction by NTPC

Hydrogen plant building under construction by NTPC

Unit 2 Boiler : LHS mills foundation under construction by NTPC

Unit 2 MRS : Silo Foundation under construction by NTPC

Unit 2 BLR RHS : MRS front not available

unit 1 TG: elevator machine room not ready

Unit 2 TG: CW piping under progress

Unit 1: 72 hrs full load trial completed

Unit 2 TG: CW piping under progress

Unit 2 Boiler : 0meter overview

Unit 2 TG: erection under progress

Unit 2 TG: 0mtr floor casting under progress by NTPC

Unit 1 : 72 hrs full load (COD) operation under progress

Unit 2 TG: Condenser overview

Unit 2 Boiler: 0Meter overview

Unit 2 Boiler : LHS mills foundation not available

BOP overview

Unit 2 TG: CEP erection u/p

Unit 2 BLR: FD fan 2A erection u/p

Unit 2 TG: 0mtr floor casting u/p by NTPC

Switchyard overview

Unit 2: Boiler RHS overview

BOP overview

TG floor overview

Unit 2 : RHS tripler floor not casted

Unit 2 : LHS feeder floor not avaialble

Unit 1: 72 hrs full load trial under progress

Unit 2 PRDS floor piping under progress

Unit 2: chemical cleaning erection work under progress

Unit 1: running at 450 MW

Unit 2 TG: Deareator erection under progress

Unit 2 ESP Control room panel shifting under progress

CPU :DM Storage tank 2 painting under progress

Unit 2 TG erection under progress

Unit 1 TG: elevator machine room not ready

Unit 1 TG: elevator enclosure not ready

Unit 2 ESP: Control room building under construction

Unit 2 ESP: Cable trestle under construction by customer (NTPC)

Unit 2 TG: CEP erection under progress

Unit 2 TG: 0Meter floor casting not yet done by Customer (NTPC)

Hydrogen plant building under construction by Customer(NTPC)

Unit 2 TG: CEP erection u/p

U2 TG BC BAY 32 Mtr: Piping U/P

U2 : Generator Trafo erection u/p by ntpc

Switchyard overview

U2 BLR: LHS Mills foundation under const by NTPC

U2 BLR: LHS overview

UNIT-1 CAPACITY ADDITION ACHIEVED ON 13/10/18

U2 BLR: Erection work for chemical cleaning u/p

U2 TG: BC BAY 32 mtr floor overview

unit 1 TG: elevator front not available

BOP overview

U2 TG : Deareator erection u/p

Unit-2 Boiler: LHS Feeder floor

Unit-2 Boiler: RHS Feeder floor

Unit-2 Boiler: ID fan 2A erection under progress

Unit-2 Boiler: ID Fan 2B motor trial completed

Unit 2 ESP: Control room panel erection u/p

Unit 2: RHS Tripler floor not yet casted

Unit 2 ESP: Cable tray laying in RHS trestle u/p

Unit 2 ESP: LHS cable trestle under const. by NTPC

U2 BLR: Erection work for Chemical cleaning u/p

Unit 2 TG: 0mtr floor not yet casted by NTPC

Unit 2 TG: CEP erection u/p

Unit-2 : LHS mills foundation not yet handed over by customer

Unit-2 ESP Control room under construction by NTPC

Unit-1 TG elevator front not available

Hydrogen plant building under construction by NTPC

CPU : Erection of both DM Storage tank completed

Unit-2 Boiler:RHS APH air receiver tank foundation work

U2 :Cable trestle from ESP control room not ready

U2 :Cable trestle from ESP control room not ready

Hydrogen plant building under construction by customer (NTPC)

Unit-2 Boiler: MRS front for RHS Mills not available (Customer)

Unit 2 TG :LP2 outer casing erected for COP assembly

Unit-2 TG floor overview

Unit-2 TG: MDBFP C hydraulic coupling erection under progress

Unit-2 Boiler: Mill E reinforcement work under progress by NTPC

CHP: stacker slew drive commissioning under progress by NTPC

Hydrogen plant building not available(Customer scope)

Unit 2 TG: HYD test device in HP valves assembled

Unit 2 TG : MDBFP D erection under progress

Unit-2 :Boiler LHS Mills foundation casting (by NTPC)

Unit-2 Turbine crossover pipe erection under progress

Unit-2 MDBFP C foundation work under progress

Unit-1 Elevator Machine room under progress

Unit 2 TG: LP 2 GBC Final assembly completed

Unit 2 TG: MDBFP D hydrolic coupling erected

Unit 2 BLR LHS : BOF to ESP duct erection under progress

Unit-2 Boiler: SADC JB & LIR erection under progress

Unit-2 Boiler: FD Fan 2A Erection under progress

Unit-2 TG:MDBFP C Foundation preparation work under progress

CPU Regenration Area overview

Unit-2 Boiler -BOF duct erection under progress

Unit-2 Boiler: RHS Bunker overview

Unit-1 : TG Elevator front not available

Unit 2 TG Floor Overview

Unit 2 TG: MDBFP D Hydrolic coupling erection under progress

Unit-2 Boiler: Mill 2F shuttering under progress by NTPC

U2 BLR: BOF to ESP duct erection u/p

Main control room overview

Unit 2 CPU: Floor partially casted by NTPC

Unit 1 : LHS bunker overview

Unit 2 : RHS bunker overview

Unit 2 TG: TDBFP B erection under progress

Unit-2 TG: LP1 rotor final Placement completed

Unit 2 TG: MDBFP D booster pump erected.

Unit 2 ESP: Control room building under construction.

Unit 2 TG:LPT2 rotor cleaning under progress

Unit 2 TG: MDBFP D motor erected.

Unit-2 Boiler : Mill 2G foundation casting done

Hydrogen plant building not available(Customer scope)

Unit 2 TG: TDBFP B erection under progress

Unit 2 TG: MDBFP D cooler erected.

Unit 2 TG:CEP foundation ring positioned

Unit-2 TG: Exciter placed on its foundation

Unit-2 Boiler: Mill 2G precast inspection under progress

Unit-2 Boiler: Seal Air Fan 2A erection under progress

Unit-1 : Coal firing done with Mill A,B,C,D

Unit-1 synchronised on 30/8/18

Unit-2 Boiler: Seal air fan 2B foundation casted by NTPC

Unit-2 TG: CW piping erection under progress

Unit 1 rolled to 3000 rpm for synchronization

Unit 1 Boiler lighted up for synchronisation

Unit 1 ESP: IOS panel commissioning under progress

Unit-2 TG: Oil Supply header erection completed

Unit-2 TG: MDBFP-2D base plate positioning under progress.

Unit 2 BLR: PAPH gas outlet duct erection u/p

Unit 2 BLR: coal piping erection u/p

Unit 2 TG: Condenser Flax box erection u/p

Unit-2 ESP : Insulation work under progress

Unit 2 Boiler: FD to SAPH duct insulation under progress

Unit-2 ESP Control room building under construction.

Unit-1 ESP IOS Panel Commissioning under progress

Unit 2 TG: MOT room piping under progress

Unit 2 TG: Overload piping to HP turbine under progress

Unit 1 TG: TDBFP-A rolling completed

Unit 1 Boiler: HWL1 valve calibration under progress

Unit 2 TG: CRH NRV erection completed

Unit-2 TG: seal steam piping erection under progress

Unit 2 TG: Overload piping under progress

Unit 2 TG: Oil piping under progress

Unit-1 Boiler: Koso valve rectification work under progress

Unit-2 Boiler: RHS SAPH to BOF Gas duct hopper erection

Unit-2 Boiler:BOF Duct elbow preassembly under progress

Unit-2 Boiler: Storage Tank insulation under progress

Unit-2 Boiler: T23 Joint under progress

Unit-1 ESP: Repair of HVR Transformer under progress

Unit-2 Boiler: LHS Mills foundation not available(Customer)

Unit-2 CPU:Service area piping foundations not available

Unit-2 TG: TDBFP-B Erection under progress

Unit-2: 1st LT SWBD Charged by NTPC

Unit-1 : TG Floor overview

CPU: DM Tank-2 erection Under progress

Unit-1 TG Enclosure for elevator installation not available

Unit-2 TG: Piping in oil canal under progress

unit 2 Bunker: Last gallery erected from TP10

Unit-1 MRS: Silo erection under progress

Unit-2 CPU:Service area piping foundations not available

Unit-1 MRS: Work heldup due to rain

Unit-2 Boiler: Work heldup due to rain

Unit-2: work heldup due to rain falling on TG deck

Unit-1 TG Floor overview

Unit-2 ESP Control room under construction ( NTPC)

Unit-2 ESP Control room under construction(NTPC)

Unit 2 TG: CEP foundations not available

Unit-1 Boiler: RHS Overview

Service Building:Front for elevator erection not available

Unit 2: LHS Mills Foundation not available (Customer scope)

Unit-2 CPU:Service area piping foundations not available.

Unit-2 TG floor over view

Unit-1 TG Floor over view

Unit-2 TG: BC Bay 32 Meter floor not available(Customer)

Unit-2 TG: TDBFP Foundation not yet handed over(customer)

U2 TG: IP Turbine work heldup due to rain

U2 TG: LP Turbine work heldup due to rain

Unit-2:41 Meter floor overview

Unit-1 Boiler: LHS Feeder floor overview

Coal Handling system overview

Unit-2 TG: Deareator erection under progress

Unit-2 Boiler RHS Overview

Unit-1 Boiler : LHS Overview

Unit-2 Boiler : LHS Over view

Unit-2: TG Floor overview

Unit-1 TG floor over view

Unit-2 Boiler: LHS Feeder floor not available(Customer)

Unit-2 Generator transformer erection under progress

Unit-1 Generator transformer area

Unit-2 TG Floor Overview

Unit-2 Boiler: ID Fan 2B erection completed

Unit-2 Boiler: ID Fan 2A erection under progress

Unit-2 TG: Erection work hampered due to rain

Unit-2 Main control room not ready for DCS Charging

Unit-2 ESP Control Room not available(Customer scope)

Unit-1 TG Floor overview

Unit-1 MRS: Front for sump pump erection not available

Coal Handling system overview

Unit-2 Boiler: LHS Mills foundation not available

Unit-2: LHS Bunker erection completed

Unit-2 Boiler: RHS approach blocked due to rain

Unit-2 Boiler- ID Fan erection affected due to rain

Unit-2 Boiler: Material feeding approach blocked

Unit-2 CD BAY: Material feeding approach blocked

Service Building:Front for elevator erection not available

Unit 1 MRS: Silo erection under progress

site overview

Unit-1 Boiler: Construction Elevator to be removed by NTPC.

Coal Handling system overview

site overview

H2 generation plant building not available(Customer scope)

Unit-2 TG: MDBFP foundation not available(Customer scope)

Unit-2 TG: Generator cooling piping erection under progress

Unit-2 TG:Generator seal oil vapour exhauster fan erection

Unit-2 TG:TDBFP A foundation not available (Customer scope)

Unit-2 TG:LP1 rotor placed on bearing for flow path check

Unit-2 Boiler:Seal Air Fan 2A Foundation casted

Unit-2 Boiler: RHS Air receiver tank foundation casted

Unit 2: LHS Bunker erection under progress

Unit-1 : Boiler RHS overview

Site overview

Unit-2 TG Hall:Side cladding,gabble end closing in progress

Site Overview

Unit-2 TG: CEP foundations not avaialble

Unit-2 TG: Condenser front side water box erected

Unit-2 TG: LP1 rotor work under progress

Unit 1 MRS: Silo erection Under progress

Unit 2 :ESP Erection under progress

Unit-2 TG: Primary water piping erection under progress

Unit-2 TG: LPH4 alignment completed

Compressor House EOT Crane: Load test completed

Unit-2 TG: MDBFP deck & floor not available from customer

Unit-2 TG: Erection of seal oil rack done

Unit-2 TG:Fabrication of LP2 Outer casing completed.

Unit-2 TG: Oil canal not available(Customer scope)

Unit-2 Boiler:FD 2A Foundation work under progress(Customer)

Unit-2 boiler- MRS Front for RHS Mills not available

Unit-2 Boiler: MTM erection work started

Unit 2: All work in TG & CCR heldup due to rain

Unit-1 Boiler: Scrap removal & area cleaning under progress

CPU: DM Tank-2 erection Under Progress

Unit-1 Mill Reject System: Mill J front not available

Unit-2 TG:MOT Room erection affected due to rain

Unit-2 TG:Work affected due to rain falling over equipment

Unit-2 TG: Oil canal not avaialble (customer scope)

Unit 2 Bunker: Last shell fitup under Progress.

Unit-2 Bunker:gallery assembly under progress

Unit-2 TG: TDBFP-2A Foundation not available(Customer scope)

Unit-2 Bunker: TP-9 Erection under progress

Unit-2 RHS Bunker: Erection under progress

Unit-2 ESP: Erection under progress

Unit-1 MRS: Silo erection Under Progress

Unit-2 Boiler: PA-2A Silencer support structure foundation

Unit-2 Boiler: FD-2A Foundation work under progress

Unit-2 Boiler: LHS Mills foundation not available(Customer)

Unit-2 TG: Oil canal not avaialble(Customer scope)

Unit-2 TG Primary water skid alignment completed

Unit-2 TG: MOT Room water piping under progress

Unit 2 TG Erection work held up due to rain

Unit-2 Boiler Pent house plate fit up work under progress

Unit-2 TG: MOT oil cooling piping erection & welding

Unit-2 TG: CEP foundations not avaialble

Unit-1 Mill Reject System: Erected in Mill F&G

Unit 2 Boiler:ID Outlet duct erection under progress.

Unit-1 Boiler: MRS front for Mill 1H& 1J not available

Unit-2 TG: All 4 vacuum pumps erected

Unit-2 Boiler Inside chimney duct erection

Unit-2 TG: LPT1 outer top assembly completed

Unit-2 TG:Generator primary water skid erection

Unit-1 MRS: Air Receiver for LHS Mills erected

Unit-1 MRS: Silo Fitup completed

Unit-1 MRS: Silo erection under progress

Unit2 TG: Erection work in MOT room under progress

Unit-2: Generator rotor threading completed

U2 TG:CPU Service area piping foundations not available

Unit-2 Boiler Column erection & Bracing work

Unit- 2 : Turbine erection under progress

Unit-2 Control room not ready for DCS Charging

Unit-2 LPT-1 outer casing top half erection

Unit-2 ID Outlet to Chimney Duct pre-assembly

Unit-2 ESP Outlet duct insulation started

Unit-2 Piping: MS Joint@45mtr in CD Bay

Unit-2 Bunker Gallery from TR3 to TP10 erected

Unit-2 TG- MDBFP foundation not available

Unit-1 TG-TDBFP-B put on Barring Gear

Unit-2 TG PCP: HRH Fit up@17mtrs Under Progress

Unit 2 TG: MOT Tank erected

Unit-2 : Trestle not ready for cable tray erection

Unit-1 MRS: Silo erection

Bunker-2: Gallery from TP9 to TR3

U-2 Generator:Rotor Flux monitoring probe

U-2 Generator:End winding probe

Unit#2 TG Piping-HRH pipe assembly

Unit#2 Piping- BFD line

CPU: DM Tank-2

Unit#1 Mill Reject System

Unit-2 ESP: Erection under progress

Unit-2 TG Floor: erection under progress

UNIT- 2 TG: 8.5 mtr floor not available