Front for service bldg elevator not avlble
|
Unit 1 TG : Handed over
|
TG Unit 2: Synchrinised on 26/8/20
|
Unit 2 : Synchronised on 26.8.20
|
TG Unit 2: LPT - 2 replacement done
|
U2 BLR LHS Overview
|
u2 esp overview
|
U2 ESP Control room
|
u2 mrs : silo erection completed
|
plant overview
|
Control room overview
|
Control room overview
|
front for service bldg elevator erection not avlbl
|
U2 BLR : All fans commissioned
|
Compresser house
|
HGP : Storage sheds
|
Unit-2 control room
|
Compressed Air system: PG test completed
|
TG Unit-1 overview
|
HGP : Storage sheds
|
Power suply upto HGP MCC Incomer not given by NTPC
|
HGP Building: Erection completed
|
HGP Building: Erection completed
|
HGP Building: Erection completed
|
HGP Building: Erection completed
|
HGP Building: Erection completed
|
U2 BLR LHS Overview
|
TG2 : LP2 rotor replacement u/p
|
TG2 : LP2 rotor replacement u/p
|
BLR 2 LHS Mills: MRS erection u/p
|
Front for service bldg elevator not avlble
|
Unit 2 TG : Front for elevator erection not avlble
|
Unit 2 BLR: LHS Mills commissioned
|
Unit 2 TG : Front for elevator erection not avlble
|
Front for service bldg elevator not avlble
|
Unit 2 MRS : Front for LHS Air receiver not avlble
|
Unit 2 TG : Front for elevator erection not avlble
|
Front for service bldg elevator not avlble
|
Hydrogen plant MCC erected
|
Front for service bldg elevator not avlble
|
Hydrogen generation plant erection u/p
|
BLR -2 : steam blowing u/p
|
Unit 2 TG : Front for elevator erection not avlble
|
BLR 2 LHS Mills: MRS front not available
|
FGD erection U/p by NTPC
|
Unit 2 ESP control room elevator erection u/p
|
1st coal rake entered NTPC Gadarwara on 27.11.191
|
BLR 2 LHS Mills: MRS front not available
|
Railway line work u/p outside the plant
|
HGP erection under progress
|
BLR 2: Insulation work u/p
|
BLR -2 : Repair work u/p for RH & SH joints
|
Unit 2 MRS : Silo erection under progress
|
Unit 2: FGD erection u/p by NTPC
|
Unit 2: FGD erection u/p by NTPC
|
Unit 2 ESP: Pass E&F commissioned
|
Unit 2 ESP control room: All cabling completed
|
u2 blr insulation u/p
|
u2 blr: lhs mills commg u/p
|
Unit 2 MRS : silo erection u/p
|
U1 TG elevator load test u/p
|
Front for TG Unit2 elevator erection not available
|
Front for Adm Bldg elevator erection not available
|
Front for service bld elevator erection not avlble
|
BLR unit 2: MRS front for LHS mills not available
|
Hydrogen generation plant erection started
|
Hydrogen generation plant erection started
|
plant overview
|
BLR -2 : Mill 2J erection u/p
|
Front for Adm Bldg elevator erection not available
|
Railway line work u/p
|
BLR -2 : Repair work u/p for RH & SH joints
|
BLR 2: LO skid foundation not available for Mill J
|
BLR 2 LHS Mills: MRS front not available
|
Unit 2 TG : Front for elevator erection not avlble
|
Front for service bldg elevator not avlble
|
Unit 1 TG elevator erection under progresss
|
BOP overview
|
BLR 2 LHS Mills: MRS front not available
|
Esp unit 2: Cabling under progress in Pass A,B,C
|
Unit 2 BLR: Mill J erection under progress
|
Unit 2 TG: TDBFP commissioning u/p
|
Unit 2 MRS : Silo erection under progress
|
Unit 1 TG elevator erection under progresss
|
unit 2: Generator transformer overview
|
Front for service bldg elevator not avlble
|
Unit 2 TG : All 3 CEPs commissioned
|
Unit 1 Boiler : Goods elevator commissioned
|
Unit-1 TG elevator erection under progresss
|
U2 MRS : silo erection under progress
|
Hydrogen plant building ready
|
Railway line work u/p inside the plant
|
Railway line work u/p outside the plant
|
U2 BLR : All RHS Mills trial completed
|
U2 BLR LHS Mills:LO skid fdn & MRS front not avlbl
|
Unit 2 TG : Front for elevator erection not avlble
|
Hydrogen plant building under construction by NTPC
|
TG Unit 2: Enclosure for elevator erectn not avlbl
|
U 2 BLR : Mill 2J erection u/p
|
Unit 2 Generator transformer overview
|
U2 MRS:Silo erection heldup due to trench excavatn
|
Unit 2 TG : Deareator floor
|
U 2 BLR : MRS erection Front for Mill 2A not avlbl
|
Unit 2 BLR: LHS feeder floor
|
Unit 2 BLR: LHS trippler floor
|
TG Unit 1: Flow nozzle erected for PG test
|
Unit 2: Cable laying u/p in ESP Pass A,B,C
|
H2 generation plant building under const. by NTPC
|
BLR 2 LHS Mills: LO skid foundation not available
|
Front for service bldg elevator not avlble
|
TG1 elevator shaft plastering u/p by NTPC
|
Hydrogen plant building under construction by NTPC
|
Hydrogen plant building under construction by NTPC
|
Unit 2 TG : Deareator floor
|
Unit 1 TG Floor
|
Unit 1: TG elevator shaft plastering u/p by NTPC
|
U2 BLR : RHS feeders trial completed
|
Front for service bldg elevator not avlble
|
TG1 elevator shaft plastering u/p by NTPC
|
U2 BLR : LHS mills LO skid fdn not avlble
|
U2 BLR : Front for MRS erection nor avlble
|
TG2 put on barring gear
|
Hydrogen plant building under construction by NTPC
|
Front for admin bldg elevator not avlble
|
TG1 elevator shaft plastering u/p by NTPC
|
plant Overview
|
CHP overview
|
plant Overview
|
Front for service bldg elevator not avlble
|
AHP overview
|
Unit 2 BLR : ID fans overview
|
Unit 2 ESP control room overview
|
Unit 2 Boiler RHS Mills overview
|
Hydrogen plant building under construction by NTPC
|
Unit-2 Boiler : Front for MRS erection nor available
|
FD fan-2B & PA fan-2B overview
|
FD fan-2A & PA fan-2A Fan overview
|
plant Overview
|
Unit 2 Boiler LHS Mills overview
|
CHP overview
|
Unit 2 TG floor
|
Hydrogen plant building under construction by NTPC
|
plant Overview
|
Unit 2 Boiler 0meter overview
|
Unit 2 CPU: Service area HT completed
|
Unit-2 Boiler : ID Fan 2A overview
|
BOP overview
|
BOP overview
|
Unit-2 ESP RHS cabling under progress
|
Unit 2 Boiler LHS overview
|
Unit-2 MRS : Silo erection started
|
Unit-2 Boiler : LHS Mills overview
|
Unit 2 Boiler : RHS MRS front not available by customer
|
Unit 2 TG: TDBFP erection under progress
|
Unit 2 TG erection under progress
|
Unit 2 ESP control room overview
|
CHP overview
|
Hydrogen plant building under construction by NTPC
|
unit 2 TG elevator front not available
|
Unit-2 Boiler: RHS overview
|
unit 2 blr : LHS feeder floor
|
Unit-2 TG floor
|
Unit-2 Boiler: Mill 2G side assembly erected
|
FD 2A & PA 2A Fan overview
|
Unit 2 :BFD piping HT completed
|
plant Overview
|
Unit 2 boiler chemical cleaning under progress
|
Unit 2 BLR RHS : MRS trench excavation under progress by NTPC
|
Unit 2 : CD bay excavated by NTPC
|
Hydrogen plant building under construction by NTPC
|
Unit 2 Boiler Lighted up on 31.12.18
|
Unit 2 ESP overview
|
Unit 2 Boiler Lighted up on 31.12.18
|
Unit- 2 Boiler : LHS overview
|
unit 2 BLR RHS : feeder erection u/p
|
Unit 2 MRS : Silo foundation handed over by NTPC
|
Hydrogen plant building under construction by NTPC
|
Unit-2 TG : CEPs erected
|
Mill 2F : Foundation yet to be handed over by customer
|
Mill 2J : Foundation yet to be handed over by customer
|
Unit-2 ESP: LHS cable trestle not available
|
Unit-2 MRS : Silo foundation under construction by Customer
|
CPU : Regen area overview
|
Unit-2 Boiler : chemical cleaning setup erected
|
Unit-2 TG : Deaerator insulation under progress
|
Unit 2 CPU : service area piping under progress
|
Unit 2 MRS : Silo foundation not available
|
Unit 2 Boiler : LHS feeder floor not yet handed over by customer
|
Unit-2 Boiler: RHS trippler floor not yet casted
|
Unit-2 Boiler: LHS Mills foundation not handed over by customer
|
U#2 SADC cylinder erection under progress
|
U#2 TDBFP-A alignment work under progress
|
U#2 CEP pump/motor coupling under progress
|
Mill 2H: Baseplate levelling work under progress
|
Unit 2 CPU : service area piping under progress
|
Hydrogen plant building under construction by NTPC
|
Hydrogen plant building under construction by NTPC
|
Unit 2 Boiler : LHS mills foundation under construction by NTPC
|
Unit 2 MRS : Silo Foundation under construction by NTPC
|
Unit 2 BLR RHS : MRS front not available
|
unit 1 TG: elevator machine room not ready
|
Unit 2 TG: CW piping under progress
|
Unit 1: 72 hrs full load trial completed
|
Unit 2 TG: CW piping under progress
|
Unit 2 Boiler : 0meter overview
|
Unit 2 TG: erection under progress
|
Unit 2 TG: 0mtr floor casting under progress by NTPC
|
Unit 1 : 72 hrs full load (COD) operation under progress
|
Unit 2 TG: Condenser overview
|
Unit 2 Boiler: 0Meter overview
|
Unit 2 Boiler : LHS mills foundation not available
|
BOP overview
|
Unit 2 TG: CEP erection u/p
|
Unit 2 BLR: FD fan 2A erection u/p
|
Unit 2 TG: 0mtr floor casting u/p by NTPC
|
Switchyard overview
|
Unit 2: Boiler RHS overview
|
BOP overview
|
TG floor overview
|
Unit 2 : RHS tripler floor not casted
|
Unit 2 : LHS feeder floor not avaialble
|
Unit 1: 72 hrs full load trial under progress
|
Unit 2 PRDS floor piping under progress
|
Unit 2: chemical cleaning erection work under progress
|
Unit 1: running at 450 MW
|
Unit 2 TG: Deareator erection under progress
|
Unit 2 ESP Control room panel shifting under progress
|
CPU :DM Storage tank 2 painting under progress
|
Unit 2 TG erection under progress
|
Unit 1 TG: elevator machine room not ready
|
Unit 1 TG: elevator enclosure not ready
|
Unit 2 ESP: Control room building under construction
|
Unit 2 ESP: Cable trestle under construction by customer (NTPC)
|
Unit 2 TG: CEP erection under progress
|
Unit 2 TG: 0Meter floor casting not yet done by Customer (NTPC)
|
Hydrogen plant building under construction by Customer(NTPC)
|
Unit 2 TG: CEP erection u/p
|
U2 TG BC BAY 32 Mtr: Piping U/P
|
U2 : Generator Trafo erection u/p by ntpc
|
Switchyard overview
|
U2 BLR: LHS Mills foundation under const by NTPC
|
U2 BLR: LHS overview
|
UNIT-1 CAPACITY ADDITION ACHIEVED ON 13/10/18
|
U2 BLR: Erection work for chemical cleaning u/p
|
U2 TG: BC BAY 32 mtr floor overview
|
unit 1 TG: elevator front not available
|
BOP overview
|
U2 TG : Deareator erection u/p
|
Unit-2 Boiler: LHS Feeder floor
|
Unit-2 Boiler: RHS Feeder floor
|
Unit-2 Boiler: ID fan 2A erection under progress
|
Unit-2 Boiler: ID Fan 2B motor trial completed
|
Unit 2 ESP: Control room panel erection u/p
|
Unit 2: RHS Tripler floor not yet casted
|
Unit 2 ESP: Cable tray laying in RHS trestle u/p
|
Unit 2 ESP: LHS cable trestle under const. by NTPC
|
U2 BLR: Erection work for Chemical cleaning u/p
|
Unit 2 TG: 0mtr floor not yet casted by NTPC
|
Unit 2 TG: CEP erection u/p
|
Unit-2 : LHS mills foundation not yet handed over by customer
|
Unit-2 ESP Control room under construction by NTPC
|
Unit-1 TG elevator front not available
|
Hydrogen plant building under construction by NTPC
|
CPU : Erection of both DM Storage tank completed
|
Unit-2 Boiler:RHS APH air receiver tank foundation work
|
U2 :Cable trestle from ESP control room not ready
|
U2 :Cable trestle from ESP control room not ready
|
Hydrogen plant building under construction by customer (NTPC)
|
Unit-2 Boiler: MRS front for RHS Mills not available (Customer)
|
Unit 2 TG :LP2 outer casing erected for COP assembly
|
Unit-2 TG floor overview
|
Unit-2 TG: MDBFP C hydraulic coupling erection under progress
|
Unit-2 Boiler: Mill E reinforcement work under progress by NTPC
|
CHP: stacker slew drive commissioning under progress by NTPC
|
Hydrogen plant building not available(Customer scope)
|
Unit 2 TG: HYD test device in HP valves assembled
|
Unit 2 TG : MDBFP D erection under progress
|
Unit-2 :Boiler LHS Mills foundation casting (by NTPC)
|
Unit-2 Turbine crossover pipe erection under progress
|
Unit-2 MDBFP C foundation work under progress
|
Unit-1 Elevator Machine room under progress
|
Unit 2 TG: LP 2 GBC Final assembly completed
|
Unit 2 TG: MDBFP D hydrolic coupling erected
|
Unit 2 BLR LHS : BOF to ESP duct erection under progress
|
Unit-2 Boiler: SADC JB & LIR erection under progress
|
Unit-2 Boiler: FD Fan 2A Erection under progress
|
Unit-2 TG:MDBFP C Foundation preparation work under progress
|
CPU Regenration Area overview
|
Unit-2 Boiler -BOF duct erection under progress
|
Unit-2 Boiler: RHS Bunker overview
|
Unit-1 : TG Elevator front not available
|
Unit 2 TG Floor Overview
|
Unit 2 TG: MDBFP D Hydrolic coupling erection under progress
|
Unit-2 Boiler: Mill 2F shuttering under progress by NTPC
|
U2 BLR: BOF to ESP duct erection u/p
|
Main control room overview
|
Unit 2 CPU: Floor partially casted by NTPC
|
Unit 1 : LHS bunker overview
|
Unit 2 : RHS bunker overview
|
Unit 2 TG: TDBFP B erection under progress
|
Unit-2 TG: LP1 rotor final Placement completed
|
Unit 2 TG: MDBFP D booster pump erected.
|
Unit 2 ESP: Control room building under construction.
|
Unit 2 TG:LPT2 rotor cleaning under progress
|
Unit 2 TG: MDBFP D motor erected.
|
Unit-2 Boiler : Mill 2G foundation casting done
|
Hydrogen plant building not available(Customer scope)
|
Unit 2 TG: TDBFP B erection under progress
|
Unit 2 TG: MDBFP D cooler erected.
|
Unit 2 TG:CEP foundation ring positioned
|
Unit-2 TG: Exciter placed on its foundation
|
Unit-2 Boiler: Mill 2G precast inspection under progress
|
Unit-2 Boiler: Seal Air Fan 2A erection under progress
|
Unit-1 : Coal firing done with Mill A,B,C,D
|
Unit-1 synchronised on 30/8/18
|
Unit-2 Boiler: Seal air fan 2B foundation casted by NTPC
|
Unit-2 TG: CW piping erection under progress
|
Unit 1 rolled to 3000 rpm for synchronization
|
Unit 1 Boiler lighted up for synchronisation
|
Unit 1 ESP: IOS panel commissioning under progress
|
Unit-2 TG: Oil Supply header erection completed
|
Unit-2 TG: MDBFP-2D base plate positioning under progress.
|
Unit 2 BLR: PAPH gas outlet duct erection u/p
|
Unit 2 BLR: coal piping erection u/p
|
Unit 2 TG: Condenser Flax box erection u/p
|
Unit-2 ESP : Insulation work under progress
|
Unit 2 Boiler: FD to SAPH duct insulation under progress
|
Unit-2 ESP Control room building under construction.
|
Unit-1 ESP IOS Panel Commissioning under progress
|
Unit 2 TG: MOT room piping under progress
|
Unit 2 TG: Overload piping to HP turbine under progress
|
Unit 1 TG: TDBFP-A rolling completed
|
Unit 1 Boiler: HWL1 valve calibration under progress
|
Unit 2 TG: CRH NRV erection completed
|
Unit-2 TG: seal steam piping erection under progress
|
Unit 2 TG: Overload piping under progress
|
Unit 2 TG: Oil piping under progress
|
Unit-1 Boiler: Koso valve rectification work under progress
|
Unit-2 Boiler: RHS SAPH to BOF Gas duct hopper erection
|
Unit-2 Boiler:BOF Duct elbow preassembly under progress
|
Unit-2 Boiler: Storage Tank insulation under progress
|
Unit-2 Boiler: T23 Joint under progress
|
Unit-1 ESP: Repair of HVR Transformer under progress
|
Unit-2 Boiler: LHS Mills foundation not available(Customer)
|
Unit-2 CPU:Service area piping foundations not available
|
Unit-2 TG: TDBFP-B Erection under progress
|
Unit-2: 1st LT SWBD Charged by NTPC
|
Unit-1 : TG Floor overview
|
CPU: DM Tank-2 erection Under progress
|
Unit-1 TG Enclosure for elevator installation not available
|
Unit-2 TG: Piping in oil canal under progress
|
unit 2 Bunker: Last gallery erected from TP10
|
Unit-1 MRS: Silo erection under progress
|
Unit-2 CPU:Service area piping foundations not available
|
Unit-1 MRS: Work heldup due to rain
|
Unit-2 Boiler: Work heldup due to rain
|
Unit-2: work heldup due to rain falling on TG deck
|
Unit-1 TG Floor overview
|
Unit-2 ESP Control room under construction ( NTPC)
|
Unit-2 ESP Control room under construction(NTPC)
|
Unit 2 TG: CEP foundations not available
|
Unit-1 Boiler: RHS Overview
|
Service Building:Front for elevator erection not available
|
Unit 2: LHS Mills Foundation not available (Customer scope)
|
Unit-2 CPU:Service area piping foundations not available.
|
Unit-2 TG floor over view
|
Unit-1 TG Floor over view
|
Unit-2 TG: BC Bay 32 Meter floor not available(Customer)
|
Unit-2 TG: TDBFP Foundation not yet handed over(customer)
|
U2 TG: IP Turbine work heldup due to rain
|
U2 TG: LP Turbine work heldup due to rain
|
Unit-2:41 Meter floor overview
|
Unit-1 Boiler: LHS Feeder floor overview
|
Coal Handling system overview
|
Unit-2 TG: Deareator erection under progress
|
Unit-2 Boiler RHS Overview
|
Unit-1 Boiler : LHS Overview
|
Unit-2 Boiler : LHS Over view
|
Unit-2: TG Floor overview
|
Unit-1 TG floor over view
|
Unit-2 Boiler: LHS Feeder floor not available(Customer)
|
Unit-2 Generator transformer erection under progress
|
Unit-1 Generator transformer area
|
Unit-2 TG Floor Overview
|
Unit-2 Boiler: ID Fan 2B erection completed
|
Unit-2 Boiler: ID Fan 2A erection under progress
|
Unit-2 TG: Erection work hampered due to rain
|
Unit-2 Main control room not ready for DCS Charging
|
Unit-2 ESP Control Room not available(Customer scope)
|
Unit-1 TG Floor overview
|
Unit-1 MRS: Front for sump pump erection not available
|
Coal Handling system overview
|
Unit-2 Boiler: LHS Mills foundation not available
|
Unit-2: LHS Bunker erection completed
|
Unit-2 Boiler: RHS approach blocked due to rain
|
Unit-2 Boiler- ID Fan erection affected due to rain
|
Unit-2 Boiler: Material feeding approach blocked
|
Unit-2 CD BAY: Material feeding approach blocked
|
Service Building:Front for elevator erection not available
|
Unit 1 MRS: Silo erection under progress
|
site overview
|
Unit-1 Boiler: Construction Elevator to be removed by NTPC.
|
Coal Handling system overview
|
site overview
|
H2 generation plant building not available(Customer scope)
|
Unit-2 TG: MDBFP foundation not available(Customer scope)
|
Unit-2 TG: Generator cooling piping erection under progress
|
Unit-2 TG:Generator seal oil vapour exhauster fan erection
|
Unit-2 TG:TDBFP A foundation not available (Customer scope)
|
Unit-2 TG:LP1 rotor placed on bearing for flow path check
|
Unit-2 Boiler:Seal Air Fan 2A Foundation casted
|
Unit-2 Boiler: RHS Air receiver tank foundation casted
|
Unit 2: LHS Bunker erection under progress
|
Unit-1 : Boiler RHS overview
|
Site overview
|
Unit-2 TG Hall:Side cladding,gabble end closing in progress
|
Site Overview
|
Unit-2 TG: CEP foundations not avaialble
|
Unit-2 TG: Condenser front side water box erected
|
Unit-2 TG: LP1 rotor work under progress
|
Unit 1 MRS: Silo erection Under progress
|
Unit 2 :ESP Erection under progress
|
Unit-2 TG: Primary water piping erection under progress
|
Unit-2 TG: LPH4 alignment completed
|
Compressor House EOT Crane: Load test completed
|
Unit-2 TG: MDBFP deck & floor not available from customer
|
Unit-2 TG: Erection of seal oil rack done
|
Unit-2 TG:Fabrication of LP2 Outer casing completed.
|
Unit-2 TG: Oil canal not available(Customer scope)
|
Unit-2 Boiler:FD 2A Foundation work under progress(Customer)
|
Unit-2 boiler- MRS Front for RHS Mills not available
|
Unit-2 Boiler: MTM erection work started
|
Unit 2: All work in TG & CCR heldup due to rain
|
Unit-1 Boiler: Scrap removal & area cleaning under progress
|
CPU: DM Tank-2 erection Under Progress
|
Unit-1 Mill Reject System: Mill J front not available
|
Unit-2 TG:MOT Room erection affected due to rain
|
Unit-2 TG:Work affected due to rain falling over equipment
|
Unit-2 TG: Oil canal not avaialble (customer scope)
|
Unit 2 Bunker: Last shell fitup under Progress.
|
Unit-2 Bunker:gallery assembly under progress
|
Unit-2 TG: TDBFP-2A Foundation not available(Customer scope)
|
Unit-2 Bunker: TP-9 Erection under progress
|
Unit-2 RHS Bunker: Erection under progress
|
Unit-2 ESP: Erection under progress
|
Unit-1 MRS: Silo erection Under Progress
|
Unit-2 Boiler: PA-2A Silencer support structure foundation
|
Unit-2 Boiler: FD-2A Foundation work under progress
|
Unit-2 Boiler: LHS Mills foundation not available(Customer)
|
Unit-2 TG: Oil canal not avaialble(Customer scope)
|
Unit-2 TG Primary water skid alignment completed
|
Unit-2 TG: MOT Room water piping under progress
|
Unit 2 TG Erection work held up due to rain
|
Unit-2 Boiler Pent house plate fit up work under progress
|
Unit-2 TG: MOT oil cooling piping erection & welding
|
Unit-2 TG: CEP foundations not avaialble
|
Unit-1 Mill Reject System: Erected in Mill F&G
|
Unit 2 Boiler:ID Outlet duct erection under progress.
|
Unit-1 Boiler: MRS front for Mill 1H& 1J not available
|
Unit-2 TG: All 4 vacuum pumps erected
|
Unit-2 Boiler Inside chimney duct erection
|
Unit-2 TG: LPT1 outer top assembly completed
|
Unit-2 TG:Generator primary water skid erection
|
Unit-1 MRS: Air Receiver for LHS Mills erected
|
Unit-1 MRS: Silo Fitup completed
|
Unit-1 MRS: Silo erection under progress
|
Unit2 TG: Erection work in MOT room under progress
|
Unit-2: Generator rotor threading completed
|
U2 TG:CPU Service area piping foundations not available
|
Unit-2 Boiler Column erection & Bracing work
|
Unit- 2 : Turbine erection under progress
|
Unit-2 Control room not ready for DCS Charging
|
Unit-2 LPT-1 outer casing top half erection
|
Unit-2 ID Outlet to Chimney Duct pre-assembly
|
Unit-2 ESP Outlet duct insulation started
|
Unit-2 Piping: MS Joint@45mtr in CD Bay
|
Unit-2 Bunker Gallery from TR3 to TP10 erected
|
Unit-2 TG- MDBFP foundation not available
|
Unit-1 TG-TDBFP-B put on Barring Gear
|
Unit-2 TG PCP: HRH Fit up@17mtrs Under Progress
|
Unit 2 TG: MOT Tank erected
|
Unit-2 : Trestle not ready for cable tray erection
|
Unit-1 MRS: Silo erection
|
Bunker-2: Gallery from TP9 to TR3
|
U-2 Generator:Rotor Flux monitoring probe
|
U-2 Generator:End winding probe
|
Unit#2 TG Piping-HRH pipe assembly
|
Unit#2 Piping- BFD line
|
CPU: DM Tank-2
|
Unit#1 Mill Reject System
|
Unit-2 ESP: Erection under progress
|
Unit-2 TG Floor: erection under progress
|
UNIT- 2 TG: 8.5 mtr floor not available
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|