UNIT#4, STG FLOOR
|
UNIT#4 FRONT SIDE
|
Unit#4, Initial Trial Run Operation Is going on
|
Unit#4, Emitting frame erection ESP-D-Pass in prog
|
Hopper for ESP#4 D-pass Assembly in Progress
|
Boiler from Left Side, Unit-04
|
Feeder Str Status, Unit-04
|
ESP Pass-A & B I/L Ducting, Unit-4
|
FD fan- A, Unit-04
|
Mill Erection, Unit-04
|
Condenser Tube Insertion, Unit-04
|
Underground ACW Piping, Unit-04
|
ESP Pass-A & B Outlet side, Unit-4
|
ID O/L Duct to Chimney, Unit-04
|
Unit#04 Boiler from Right Side
|
ESP Pass-A & B Inlet Side, Unit-4
|
MILL BUNKER STR STATUS, UNIT#04
|
Boiler from Right Side, Unit-04
|
ID O/L Duct to Chimney, Unit-04
|
MILL BUNKER STR STATUS, UNIT#04
|
ESP Pass-A Inlet Side, Unit-4
|
TG Floor, Unit-04
|
Boiler from Left Side, Unit-04
|
MILL BUNKER STR STATUS, UNIT#04
|
ESP Pass-A & B & P&Q Row Str Ern. Unit-4
|
ECW PIPING & PUMPS UNIT-04
|
Condenser erection U#4
|
TG Building without roofsheeting, U#4
|
HRH & BFD line passing over PRDS floor, Unit-04
|
|
|
|
Condenser erection U#4
|
MILL BUNKER STR STATUS, UNIT#04
|
ESP Pass- A,B & C Erection, Unit#4
|
ID fan & Duct Erection Unit#4
|
MILL BUNKER STR STATUS, UNIT#04
|
IMPELLER SHAFT ASSY, ID FAN-4B.
|
ESP Pass-A & B, Unit-4
|
Unit#04 Condenser
|
Unit-4 Mill-D
|
ESP Pass-A & B, Unit-4
|
TG Building without roofsheeting, U#4
|
LP Heaters U#4
|
Incomplete PRDS floor, U#4
|
LP Heaters U#4
|
ESP, Unit-4
|
Condenser erection U#4
|
TG Bearing pedestal U#4
|
Unit-4 Mill-A Erection Started
|
ID-4B O/L Duct erection
|
ESP Pass-A Unit-4
|
Unit#04 Boiler
|
|
|
|
|
Unit 4 MIll Grouting work in progress
|
Unit 4 ESP pass A erection work
|
Unit 4 HP DFT positioned
|
Unit 4 Condenser Left wall erection work
|
Unit 4 ID Fan B erection work
|
Unit IV ESP Column Erection work in progress
|
Unit 4 TG ECW Canal piping work
|
Unit IV ESP Column Erection work in progress
|
Unit 4 Mill foundation
|
Unit IV ID Fan -Chimney Ducting
|
Unit IV ESP Column Erection work in progress
|
Unit 4 Generation Base Plate Gringing work
|
Unit 4 Seal Air Fan Foundation
|
Unit 4 ESP pass A erection work
|
Unit 4 ID Fan A Erection work
|
Unit 4 Generator Foundation Plate Blue Matching
|
Unit 4 Water Chamber Hole Cleaning
|
Unit 4 Padestal 4 Hole Blue matching work
|
Unit 4 CW (L) Piping work in progress
|
Unit 4 Condenser Bottom Plate Erection work
|
Unit IV ESP Column Erection work in progress
|
Unit 4 CW Line(L) Concreting work
|
Unit 4 ESP pass A erection work
|
Unit 4 Mill Column Erection work in progress
|
Unit 4 Boiler to APH Duct lifting work
|
Unit 4 Generator Foundation Plate Blue Matching
|
Unit 4 Condenser Side Wall pre-erection work
|
Unit 4 ESP pass A erection work
|
Unit 4 Water Box Tube Hole cleaning
|
Unit 4 CW (Right pass) erection work is in pro
|
Unit IV ESP Column Erection work in progress
|
Unit 4 CST lifting to 35m is in progress
|
Unit 4 CW (Right pass) pre erection work is in pro
|
Unit 4 Condenser Bottom Plate erection work
|
Unit 4 ID Fan A Rotor shaft erection
|
Unit 4 ESP Column lifting in progress
|
Unit 4 Condenser Bottom Plate positioned on deck
|
Unit 4 ESP pass A erection work
|
Unit 4 FD fan Foundation plate Blue matching work
|
Unit 4 Boiler Chute erection work
|
Unit 4 Boiler Burner erection work
|
Unit 4 Condenser Bottom Plate erection work
|
Unit 4 ID Fan A Rotor shaft erection
|
Unit 4 Condenser Hotwell assembly
|
Unit 4 FD Fan Motor erection
|
Unit 4 Hotwell pre-erection work in progress
|
Unit 4 Chimney ID fan Duct work
|
Unit 4 CW (L) Piping erection work
|
Unit 4 FD Fan Impeller Casing erection work in pro
|
Unit 4 Condenser bottom plate assembly
|
Unit 4 CW line Pipe erection work
|
Unit 4 ESP Ash Hopper work
|
Unit 4 CW line Piping work in progress
|
Unit 4 Condenser bottom plate assembly
|
Unit 4 Air Pre Heater Support structure lifting
|
Unit 4 CW line Piping work in progress
|
Unit 3 PA Fan Monorail erection work
|
U 4 Condenser Bottom Plate pre-erection work
|
U 3 Deareator Floor Scrap removal work
|
U 3 Bunker G drain Chute Erection Work
|
Unit 3 PG Test preparation work
|
Unit 4 Condenser bottom plate assembly Bad ern
|
Unit 4 TG ECW line Canal work in progress
|
Unit 4 CW line Piping work in progress
|
Unit 4 ESP Column Erection work in progress
|
Unit 3 Bunker Drain Chute Erection
|
Unit 4 Mill pit work for Foundation
|
Unit 4 Mill Column Erection work in progress
|
Unit 4 Condenser bottom plate assembly Bad ern
|
UNit 4 APH duct lifting
|
Unit 3 BFP C Insulation work completed
|
Unit-3 Hot PA Insulation Work in progress
|
Unit 4 CW line Piping work in progress
|
Unit-4 ESP Column Erection work in progress
|
Unit-4 FD Fan Foundation work in progress
|
Unit-4 ESP Control Panel Room Erection in progress
|
Unit- 4 FD Fan B Foundation work in progress
|
Unit 4 FD Fan B Foundation work in progress
|
Unit- 3 Mill G Coupled trial run taken
|
Unit 4 FD Fan A Foundation Work in progress
|
Unit 4 ESP Column Erection work in progress
|
Unit 3 Wall Blower Commissioning in progress
|
Unit- 3 Hot PA Insulation(Sheeting) work in progress
|
Unit 4 PA Fan Foundation work in progress
|
Unit 4 grouting work for Mill Foundation
|
Unit- 3 Mill G Cone Welding in progress
|
Mill F Roller Spring Setting work in progress
|
Unit-4 ESP Column Erection work in progress
|
Unit 3 Hot PA Duct lagging work in progress
|
Unit 3 Work on Wall Blower alignment in progress
|
Unit 3 Wall Deslagger alignment is in progress
|
Unit 4 ESP Column lifting in progress
|
Unit 3 BFP C readiness is in progress
|
Unit-3 CEP Discharge Orifice plate fixing
|
Unit-3 DCS Panel Installation in Control Room
|
Unit- 3 ESP Ash Hopper Erection work
|
Unit- 4 ESP Column Erection work
|
Unit- 3 Attending ATT Leakage
|
Unit-3 ESP Insulation work
|
Unit-3 TG House Keeping work
|
Unit-4 PA Fan Foundation Work
|
Unit-3 Governing Rack Charging
|
Unit-4 PA Fan and FD Fan Foundation work
|
Unit-3 PA line Support Work in progress
|
Unit-3 Insulation Work in TG Area
|
Unit-3 steam line insulation work in progress
|
Unit-3 Control room readiness
|
Seal air fan line erection work in progress
|
Unit-4 ESP column erection work in progress
|
Unit-3 ESP insulation and cladding in progress
|
Unit#3 TG deck adjacent floor
|
Unit#4 Furnace to ESP duct
|
Unit#4 ID Fan A foundation status
|
Unit#4 ESP foundation status
|
Unit-3 Mill- F & G readiness
|
Unit-3 Seal air fan motor alignment work
|
Unit-3 Insulation in duct from ID fan B to chimney
|
Unit-4 ESP control room status
|
Unit#4 Condenser foundation status
|
Unit#4 TG AB bay status
|
Unit#4 Mill A, B, C foundation status
|
Unit#3 Insulation work in LP Heater
|
Unit-3 ID Fan A duct erection
|
Unit-3 & 4 Control room
|
Unit-3 Swing check and CRO check of generator shaft
|
Unit#4 Turbine floor status
|
Unit#4 FD fan- A foundation status
|
Unit#4 Mill - A, B, C & D foundation status
|
Unit#3 Boiler to ESP inlet duct
|
Unit#4 Mill- E, F & G foundation status
|
Unit# 3 Status of ID fan - A
|
Unit#3 Insulation work from ESP O/L to ID fan- B
|
Unit# 3 PA Fan- A work progress
|
Unit-3 Duct from Mill to ESP inlet
|
Unit-3 ESP- C & D outlet Insulation work
|
Unit-3 Hot PA Duct erection
|
Unit-3 ID Fan-A rotor erection work
|
Unit-3 Hot PA Duct erection
|
U#3 TG Deck Floating compeleted
|
U#3 Right side Duct Support structure
|
U#3 Hot PA Duct erection
|
Unit-3 ID Fan-A Rotor assembly work progress
|
Unit-3 ID Fan-A Spiral casing erection done
|
Unit-3 Duct Insulation from ID Fan-A to Chimney
|
Unit-3 Duct from Mill to ESP inlet
|
Unit-3 Hot PA Duct erection
|
Unit-3 Duct from Mill to ESP inlet
|
Unit-3 Duct Insulation from ID Fan-B to Chimney
|
Unit-3 Duct from ESP outlet to ID fans
|
Unit-3 Duct Insulation from ESP outlet to ID Fan-B
|
Unit-3 Hot PA Duct erection
|
Unit-4 ESP Control room readiness
|
Unit-4 Mill foundation readiness
|
Unit-3 FD Fan-A & PA Fan-A readiness
|
Unit-3 Hot PA Duct erection
|
Unit-3 Duct Insulation from ID Fan-B to Chimney
|
Unit-3 Duct from Mill to ESP inlet
|
Unit-3 Hot PA Duct erection
|
U#3 Duct Insulation from ESP outlet to ID Fan-B
|
U#3 Hot PA Duct erection
|
U#3 Duct from Mill to ESP inlet
|
U#3 Duct and Insulation from ESP oulet to ID fans
|
Unit-3 Duct Insulation from ID Fan-B to Chimney
|
Unit-3 Mill Motor readiness
|
Unit-3 Coal pipe erection
|
Unit-3 Hot PA Duct erection
|
Unit-3 Hopper erection ESP Pass-A
|
Unit-3 Duct Insulation from BOF to Mill
|
Unit-3 Duct Insulation from ID Fan-B to Chimney
|
Unit-3 Duct from ESP outlet to ID fans
|
Unit-4 Mill A & B motor coupled trial readiness
|
Unit-3 Duct Insulation from BOF to Mill
|
Unit-3 Hot PA Duct erection
|
U#3 CENTRAL CONTROL ROOM READINESS
|
U#3 FD Fan-A & PA Fan-A readiness
|
U#3 MS, CRH, HRH INSULATION READINESS
|
Unit-4 PA Duct readiness
|
Unit-4 BFPs readiness
|
Unit-3 MS,CRH,HRH Insulation Readiness
|
Unit-3 Programmer room readiness
|
Unit-3 Central Control Room Rreadiness
|
Unit-3 TG Deck readiness
|
Unit-3 BFP-A readiness
|
Unit-3 Duct Insulation from ID Fan-B to Chimney
|
Unit-3 Duct from ESP outlet to ID fans
|
Unit-3 Control room readiness
|
Unit-3 TG readiness
|
Unit-3 ID Fan-A motor erection done
|
Unit-3 Duct Insulation from ID Fan-B to Chimney
|
Unit-3 ESP-A pass hopper plate erection
|
Unit-3 Duct from ESP oulet to ID fans
|
Unit-3 Duct from Mill to ESP inlet
|
Unit-3 Coal pipe erection
|
Unit-3 Hot PA Duct erection
|
Unit-3 BFP-A Coupled trial under progress
|
Unit-3 ID Fan-A motor erection done
|
Unit-3 Bunker hopper area
|
Unit-3 VFD Transformer foundation (right side)
|
Unit-3 TG Deck readiness
|
Unit-3 CER room readiness
|
Unit-3 Control room readiness
|
Unit-3 FD Fan-A & PA Fan-A area
|
Unit-3 Duct Insulation from FD Fan to APH
|
Unit-3 Mill Motor readiness
|
Unit-3 Duct erection from Mill to ESP Inlet
|
Unit-3 Coal pipe erection & PA Duct erection
|
Unit-3 Duct Insulation from BOF to Mill
|
Unit-3: 0 meter SG ECW motor area
|
Unit-3 seal air area foundation
|
Unit -3 battery room area
|
Unit-3 & 4 control desk room area
|
Unit-4 ESP Pass-B,C,D area
|
Unit-3 Mill area 3.5 meter
|
Unit -3 mills area
|
Unit-4 VFD Building
|
Unit-4 Boiler and Mill area
|
Unit-3 ESP pass C and D area
|
Unit-3 Seal Air fan-A Foundation area
|
Unit-3 VFD Building area
|
Unit-4 DCS Panel Room
|
Unit-4 TG Floor 13.5 Meter
|
Unit-3 TG ECW Area
|
Unit-3 BFP-C area
|
Unit-3 BFP-A area
|
Unit-4 Mill area
|
Unit-4 Boiler
|
Unit-3 Mill area
|
Unit-3 Feeder Floor area
|
Unit-4 ESP Control Room
|
Unit-4 TG Deck Foundation
|
Unit-3 Control Room
|
Unit-3 ESP Outlet
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|