Home   

NABINAGAR (4X250 MW )


UNIT#4, STG FLOOR

UNIT#4 FRONT SIDE

Unit#4, Initial Trial Run Operation Is going on

Unit#4, Emitting frame erection ESP-D-Pass in prog

Hopper for ESP#4 D-pass Assembly in Progress

Boiler from Left Side, Unit-04

Feeder Str Status, Unit-04

ESP Pass-A & B I/L Ducting, Unit-4

FD fan- A, Unit-04

Mill Erection, Unit-04

Condenser Tube Insertion, Unit-04

Underground ACW Piping, Unit-04

ESP Pass-A & B Outlet side, Unit-4

ID O/L Duct to Chimney, Unit-04

Unit#04 Boiler from Right Side

ESP Pass-A & B Inlet Side, Unit-4

MILL BUNKER STR STATUS, UNIT#04

Boiler from Right Side, Unit-04

ID O/L Duct to Chimney, Unit-04

MILL BUNKER STR STATUS, UNIT#04

ESP Pass-A Inlet Side, Unit-4

TG Floor, Unit-04

Boiler from Left Side, Unit-04

MILL BUNKER STR STATUS, UNIT#04

ESP Pass-A & B & P&Q Row Str Ern. Unit-4

ECW PIPING & PUMPS UNIT-04

Condenser erection U#4

TG Building without roofsheeting, U#4

HRH & BFD line passing over PRDS floor, Unit-04




Condenser erection U#4

MILL BUNKER STR STATUS, UNIT#04

ESP Pass- A,B & C Erection, Unit#4

ID fan & Duct Erection Unit#4

MILL BUNKER STR STATUS, UNIT#04

IMPELLER SHAFT ASSY, ID FAN-4B.

ESP Pass-A & B, Unit-4

Unit#04 Condenser

Unit-4 Mill-D

ESP Pass-A & B, Unit-4

TG Building without roofsheeting, U#4

LP Heaters U#4

Incomplete PRDS floor, U#4

LP Heaters U#4

ESP, Unit-4

Condenser erection U#4

TG Bearing pedestal U#4

Unit-4 Mill-A Erection Started

ID-4B O/L Duct erection

ESP Pass-A Unit-4

Unit#04 Boiler





Unit 4 MIll Grouting work in progress

Unit 4 ESP pass A erection work

Unit 4 HP DFT positioned

Unit 4 Condenser Left wall erection work

Unit 4 ID Fan B erection work

Unit IV ESP Column Erection work in progress

Unit 4 TG ECW Canal piping work

Unit IV ESP Column Erection work in progress

Unit 4 Mill foundation

Unit IV ID Fan -Chimney Ducting

Unit IV ESP Column Erection work in progress

Unit 4 Generation Base Plate Gringing work

Unit 4 Seal Air Fan Foundation

Unit 4 ESP pass A erection work

Unit 4 ID Fan A Erection work

Unit 4 Generator Foundation Plate Blue Matching

Unit 4 Water Chamber Hole Cleaning

Unit 4 Padestal 4 Hole Blue matching work

Unit 4 CW (L) Piping work in progress

Unit 4 Condenser Bottom Plate Erection work

Unit IV ESP Column Erection work in progress

Unit 4 CW Line(L) Concreting work

Unit 4 ESP pass A erection work

Unit 4 Mill Column Erection work in progress

Unit 4 Boiler to APH Duct lifting work

Unit 4 Generator Foundation Plate Blue Matching

Unit 4 Condenser Side Wall pre-erection work

Unit 4 ESP pass A erection work

Unit 4 Water Box Tube Hole cleaning

Unit 4 CW (Right pass) erection work is in pro

Unit IV ESP Column Erection work in progress

Unit 4 CST lifting to 35m is in progress

Unit 4 CW (Right pass) pre erection work is in pro

Unit 4 Condenser Bottom Plate erection work

Unit 4 ID Fan A Rotor shaft erection

Unit 4 ESP Column lifting in progress

Unit 4 Condenser Bottom Plate positioned on deck

Unit 4 ESP pass A erection work

Unit 4 FD fan Foundation plate Blue matching work

Unit 4 Boiler Chute erection work

Unit 4 Boiler Burner erection work

Unit 4 Condenser Bottom Plate erection work

Unit 4 ID Fan A Rotor shaft erection

Unit 4 Condenser Hotwell assembly

Unit 4 FD Fan Motor erection

Unit 4 Hotwell pre-erection work in progress

Unit 4 Chimney ID fan Duct work

Unit 4 CW (L) Piping erection work

Unit 4 FD Fan Impeller Casing erection work in pro

Unit 4 Condenser bottom plate assembly

Unit 4 CW line Pipe erection work

Unit 4 ESP Ash Hopper work

Unit 4 CW line Piping work in progress

Unit 4 Condenser bottom plate assembly

Unit 4 Air Pre Heater Support structure lifting

Unit 4 CW line Piping work in progress

Unit 3 PA Fan Monorail erection work

U 4 Condenser Bottom Plate pre-erection work

U 3 Deareator Floor Scrap removal work

U 3 Bunker G drain Chute Erection Work

Unit 3 PG Test preparation work

Unit 4 Condenser bottom plate assembly Bad ern

Unit 4 TG ECW line Canal work in progress

Unit 4 CW line Piping work in progress

Unit 4 ESP Column Erection work in progress

Unit 3 Bunker Drain Chute Erection

Unit 4 Mill pit work for Foundation

Unit 4 Mill Column Erection work in progress

Unit 4 Condenser bottom plate assembly Bad ern

UNit 4 APH duct lifting

Unit 3 BFP C Insulation work completed

Unit-3 Hot PA Insulation Work in progress

Unit 4 CW line Piping work in progress

Unit-4 ESP Column Erection work in progress

Unit-4 FD Fan Foundation work in progress

Unit-4 ESP Control Panel Room Erection in progress

Unit- 4 FD Fan B Foundation work in progress

Unit 4 FD Fan B Foundation work in progress

Unit- 3 Mill G Coupled trial run taken

Unit 4 FD Fan A Foundation Work in progress

Unit 4 ESP Column Erection work in progress

Unit 3 Wall Blower Commissioning in progress

Unit- 3 Hot PA Insulation(Sheeting) work in progress

Unit 4 PA Fan Foundation work in progress

Unit 4 grouting work for Mill Foundation

Unit- 3 Mill G Cone Welding in progress

Mill F Roller Spring Setting work in progress

Unit-4 ESP Column Erection work in progress

Unit 3 Hot PA Duct lagging work in progress

Unit 3 Work on Wall Blower alignment in progress

Unit 3 Wall Deslagger alignment is in progress

Unit 4 ESP Column lifting in progress

Unit 3 BFP C readiness is in progress

Unit-3 CEP Discharge Orifice plate fixing

Unit-3 DCS Panel Installation in Control Room

Unit- 3 ESP Ash Hopper Erection work

Unit- 4 ESP Column Erection work

Unit- 3 Attending ATT Leakage

Unit-3 ESP Insulation work

Unit-3 TG House Keeping work

Unit-4 PA Fan Foundation Work

Unit-3 Governing Rack Charging

Unit-4 PA Fan and FD Fan Foundation work

Unit-3 PA line Support Work in progress

Unit-3 Insulation Work in TG Area

Unit-3 steam line insulation work in progress

Unit-3 Control room readiness

Seal air fan line erection work in progress

Unit-4 ESP column erection work in progress

Unit-3 ESP insulation and cladding in progress

Unit#3 TG deck adjacent floor

Unit#4 Furnace to ESP duct

Unit#4 ID Fan A foundation status

Unit#4 ESP foundation status

Unit-3 Mill- F & G readiness

Unit-3 Seal air fan motor alignment work

Unit-3 Insulation in duct from ID fan B to chimney

Unit-4 ESP control room status

Unit#4 Condenser foundation status

Unit#4 TG AB bay status

Unit#4 Mill A, B, C foundation status

Unit#3 Insulation work in LP Heater

Unit-3 ID Fan A duct erection

Unit-3 & 4 Control room

Unit-3 Swing check and CRO check of generator shaft

Unit#4 Turbine floor status

Unit#4 FD fan- A foundation status

Unit#4 Mill - A, B, C & D foundation status

Unit#3 Boiler to ESP inlet duct

Unit#4 Mill- E, F & G foundation status

Unit# 3 Status of ID fan - A

Unit#3 Insulation work from ESP O/L to ID fan- B

Unit# 3 PA Fan- A work progress

Unit-3 Duct from Mill to ESP inlet

Unit-3 ESP- C & D outlet Insulation work

Unit-3 Hot PA Duct erection

Unit-3 ID Fan-A rotor erection work

Unit-3 Hot PA Duct erection

U#3 TG Deck Floating compeleted

U#3 Right side Duct Support structure

U#3 Hot PA Duct erection

Unit-3 ID Fan-A Rotor assembly work progress

Unit-3 ID Fan-A Spiral casing erection done

Unit-3 Duct Insulation from ID Fan-A to Chimney

Unit-3 Duct from Mill to ESP inlet

Unit-3 Hot PA Duct erection

Unit-3 Duct from Mill to ESP inlet

Unit-3 Duct Insulation from ID Fan-B to Chimney

Unit-3 Duct from ESP outlet to ID fans

Unit-3 Duct Insulation from ESP outlet to ID Fan-B

Unit-3 Hot PA Duct erection

Unit-4 ESP Control room readiness

Unit-4 Mill foundation readiness

Unit-3 FD Fan-A & PA Fan-A readiness

Unit-3 Hot PA Duct erection

Unit-3 Duct Insulation from ID Fan-B to Chimney

Unit-3 Duct from Mill to ESP inlet

Unit-3 Hot PA Duct erection

U#3 Duct Insulation from ESP outlet to ID Fan-B

U#3 Hot PA Duct erection

U#3 Duct from Mill to ESP inlet

U#3 Duct and Insulation from ESP oulet to ID fans

Unit-3 Duct Insulation from ID Fan-B to Chimney

Unit-3 Mill Motor readiness

Unit-3 Coal pipe erection

Unit-3 Hot PA Duct erection

Unit-3 Hopper erection ESP Pass-A

Unit-3 Duct Insulation from BOF to Mill

Unit-3 Duct Insulation from ID Fan-B to Chimney

Unit-3 Duct from ESP outlet to ID fans

Unit-4 Mill A & B motor coupled trial readiness

Unit-3 Duct Insulation from BOF to Mill

Unit-3 Hot PA Duct erection

U#3 CENTRAL CONTROL ROOM READINESS

U#3 FD Fan-A & PA Fan-A readiness

U#3 MS, CRH, HRH INSULATION READINESS

Unit-4 PA Duct readiness

Unit-4 BFPs readiness

Unit-3 MS,CRH,HRH Insulation Readiness

Unit-3 Programmer room readiness

Unit-3 Central Control Room Rreadiness

Unit-3 TG Deck readiness

Unit-3 BFP-A readiness

Unit-3 Duct Insulation from ID Fan-B to Chimney

Unit-3 Duct from ESP outlet to ID fans

Unit-3 Control room readiness

Unit-3 TG readiness

Unit-3 ID Fan-A motor erection done

Unit-3 Duct Insulation from ID Fan-B to Chimney

Unit-3 ESP-A pass hopper plate erection

Unit-3 Duct from ESP oulet to ID fans

Unit-3 Duct from Mill to ESP inlet

Unit-3 Coal pipe erection

Unit-3 Hot PA Duct erection

Unit-3 BFP-A Coupled trial under progress

Unit-3 ID Fan-A motor erection done

Unit-3 Bunker hopper area

Unit-3 VFD Transformer foundation (right side)

Unit-3 TG Deck readiness

Unit-3 CER room readiness

Unit-3 Control room readiness

Unit-3 FD Fan-A & PA Fan-A area

Unit-3 Duct Insulation from FD Fan to APH

Unit-3 Mill Motor readiness

Unit-3 Duct erection from Mill to ESP Inlet

Unit-3 Coal pipe erection & PA Duct erection

Unit-3 Duct Insulation from BOF to Mill

Unit-3: 0 meter SG ECW motor area

Unit-3 seal air area foundation

Unit -3 battery room area

Unit-3 & 4 control desk room area

Unit-4 ESP Pass-B,C,D area

Unit-3 Mill area 3.5 meter

Unit -3 mills area

Unit-4 VFD Building

Unit-4 Boiler and Mill area

Unit-3 ESP pass C and D area

Unit-3 Seal Air fan-A Foundation area

Unit-3 VFD Building area

Unit-4 DCS Panel Room

Unit-4 TG Floor 13.5 Meter

Unit-3 TG ECW Area

Unit-3 BFP-C area

Unit-3 BFP-A area

Unit-4 Mill area

Unit-4 Boiler

Unit-3 Mill area

Unit-3 Feeder Floor area

Unit-4 ESP Control Room

Unit-4 TG Deck Foundation

Unit-3 Control Room

Unit-3 ESP Outlet