CCW PUMP HOUSE
|
STG BUILDING
|
CWPH AND COOLING TOWER
|
ROAD
|
HRSG
|
GBC BUILDING
|
GT BUILDING
|
STG Insulation application completed.
|
Kota stone laying on STG floor.
|
STG Governing rack and its piping completedd.
|
STG EOT crane erection and commissioning completed
|
STG WORK STARTED
|
STG WORK STARTED
|
STG ROOF STRUCTURE
|
STG ROOF STRUCTURE
|
STG ROOF STRUCTURE
|
House keeping works at Namrup
|
House keeping works at Namrup
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Stuctural works for Roof strengthening
|
Removing of GTG water proofing roof layer
|
Removing of GTG water proofing roof layer
|
Removing of GTG water proofing roof layer
|
Removal of Water proofing layer from GTG roof
|
Removal of Water proofing layer from GTG roof
|
Removal of Water proofing layer from GTG roof
|
Removal of water proofing layer at GTG building
|
Removal of water proofing layer at GTG building
|
GT Building roof treatment layer removal under progress
|
Removal of water proofing layer in GTG
|
Removal of water proofing layer in GTG
|
Structure job for Temporary strengthening in GTG
|
Bus Bar erection uder progress
|
Bus Bar erection uder progress
|
Bus Bar erection uder progress
|
Bus Bar erection uder progress
|
Bus Bar erection uder progress
|
Bus Bar erection uder progress
|
Bus Bar erection uder progress
|
GTG Roof temporary strengthening. Tower crane
|
GTG Roof temporary strengthening
|
GTG Roof temporary strengthening
|
Removing of roof water proofing layers at GTG buil
|
Removing of roof water proofing layers at GTG buil
|
BC Bay roof treatment layer removal under progress
|
Debris removal at TG floor under progress
|
Debris removal at TG floor under progress
|
Man lift under operation at site.
|
Clarified Water supply terminal point ready
|
Gas Station Modification Piping Work
|
Clarified water supply terminal point piping is in progress
|
Centrifugal fan at 0 mtrs in position
|
Side Stream Filtration Foundation ready
|
Passenger Elevator commissioning completed
|
Gas Turbine exhaust upper casing erection complete
|
chlorination building MCC on position.
|
Chlorination building pumps and motor erected
|
Piping work of chiller under progress
|
Admin Building
|
GT rotor unloaded in GT Hall
|
CCW-2 Pump assembly under progress
|
Load Gear Box erection under progress
|
Clarified Water Pump House ready
|
Deaerator insulation completed
|
BFP Building flooring completed
|
DM plant- Acid and resin filling completed
|
Side Stream Filtration Foundation ready
|
Road construction to CWPH under progress
|
Feed control station insulation
|
C&I instrument erection in DM plant
|
Deaerator insulation work completed
|
Paver Block erection infront of STG Building
|
Road construction to CWPH under progress
|
Deaerator insulation work under progress
|
Paver block erection completed along GT & GBC road
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|