Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 1/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Unit # 2/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
TG/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
Bldgs/progress
|
BOILER#1/progress
|
Plant/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
TG # 1/progress
|
CW System/progress
|
Compressor BLDG/progress
|
Boiler U # 1/progress
|
Boiler U # 1/progress
|
Boiler U # 1/progress
|
Boiler U # 1/progress
|
Boiler U # 1/progress
|
Boiler U # 1/progress
|
Boiler U # 1/progress
|
Boiler U# 2/progress
|
Boiler U# 2/progress
|
Boiler U# 2/progress
|
Boiler U# 2/progress
|
Boiler U# 2/progress
|
Aux. Boiler/progress
|
Unit # 2 ESP Pass-D, E
|
Unit 2 Boiler LHS vertical water wall erection/Under Progress
|
Unit # 1 ID Fan-A erection/Under Progress
|
Unit-1: IP/HP Turbine erection/Under Progress
|
Unit-1: RHS Mill-A foundation/Not ready, scope customer
|
Unit-1 Super critical piping pre. Assambaly/Under Progress
|
ESP Unit 1 – Transformer placement/Under Progress
|
Unit #1 Boiler Pass -2 pressure part erection/Under Progress
|
pipe rack/progress
|
FWPH/progress
|
boiler #1 /final super heater coil
|
boiler #1 /final super heater coil
|
boiler #1 /final super heater coil
|
Boiler U # 1/progress
|
CHIMNEY HEIGHT REACHED 269M BY NTPC/BYGGING/PROGRESS
|
ESP#1 FRONT VIEW/PROGRESS
|
TG UNIT # 1 TG EOT CRANE PRE ASSY U/P /PROGRESS
|
Boiler#1 – APH WORK U/P /PROGRESS
|
Boiler#1 –FINAL SUPER HEATER COIL ERECTION /PROGRESS
|
Boiler#1 – 1st PASS
|
Boiler#1 – FINAL SUPER HEATER COIL PREASSY/PROGRESS
|
Boiler#1 – SEPERATOR
|
Boiler#1 – PRESSURE PART ERECTION ABOVE ROOF/PROGRESS
|
Boiler#1 – PRESSURE PART SUSPENSION ERECTION ABOVE ROOF/PROGRESS
|
Boiler#1 – BURNER ERECTION WORK/PROGRESS
|
Boiler#1 – FLESH TANK ERECTION COMPLETED/PROGRESS
|
BOILER-1 PRESSURE PART ERECTION ABOVE ROOF/PROGRESS
|
BOILER #1 DUCT ERECTION /PROGRESS
|
BOILER U # 1 REAR VIEW/PROGRESS
|
PLANT VIEW/PROGRESS
|
TG # 1/progress
|
BOILER U # 1/progress
|
BOILER u# 2/progress
|
ESP 2 Foundations/progress
|
ESP 1/progress
|
Boiler #1
|
Boiler #1
|
ESP #1
|
ESP #1
|
TG # 1 Deck/progress
|
TG Unit‐2/progress
|
ESP‐2/progress
|
Boiler U # 2/progress
|
TG‐1/progress
|
ESP‐1/progress
|
Boiler Unit‐I/progress
|
Boiler Unit‐I/progress
|
ESP U # 1/PROGRESS
|
Boiler U# 2 foundations/PROGRESS
|
Boiler U #1/PROGRESS
|
STORES/PROGRESS
|
BLR#1 FIFTH TIER ERECTION/PROGRESS
|
BLR#1 CEILING GDR PLACED FOR PRE-ASSEMBLY/PROGRESS
|
BLR#2 FDNS STATUS/PROGRESS
|
ESP#1 PASS D
|
ESP U#1, PASS D E F/PROGRESS
|
ESP U2 PILING WORK/PROGRESS
|
ESP U1, PASS A B C/PROGRESS
|
BOILER U2 FOUNDATION (2)/PROGRESS
|
BOILER U2 FOUNDATION (2)/PROGRESS
|
Boiler U 1/foundation casting
|
Boiler U 1/foundation casting
|
Boiler U 1/foundation casting
|