ESP/In Progress
|
BAH Unit-1/In Progress
|
PRIMARY CRUSHER HOUSE-2/In Progress
|
BUNKER MCC/In Progress
|
SR MCC/In Progress
|
BCN 13A/B TR 16/ In progress
|
BCN-14A/B – TR4 /In Progress
|
STACKER RECLAIMER AREA FOUNDATION WORKS/In Progress
|
VACUUM PUMP HOUSE CUM COMPRESSOR HOUSE UNIT-1/In Progress
|
HT SWITCH GEAR ROOM/In Progress
|
ASH WATER PUMP HOUSE /In Progress
|
ASH SLURRY PUMP HOUSE /In Progress
|
WAGON TIPPLER -3/
|
WAGON TIPPLER -2/
|
WAGON TIPPLER -1/
|
JNT 9/In Progress
|
JNT 8/In Progress
|
JNT 7/In Progress
|
JNT 6/In Progress
|
JNT 5/In Progress
|
JNT 4/In Progress
|
JNT 3/ In progress
|
JNT 2/In Progress
|
JNT1/In Progress
|
Cooling Water Pump House/In Progress
|
Compressor House/In Progress
|
CWPH Electrical Annex Building/In Progress
|
DG Building/In Progress
|
FOPH Dyke area/In Progress
|
FOPH Unloading Area/In Progress
|
Common Control Room status at 17 Meter/In Progress
|
Common Control Room Battery Room/In Progress
|
Condensate Storage Tank Pump House/In Progress
|
CPU Building/In Progress
|
FO Pump house area/In Progress
|
Cooling Water Channeling Work/In Progress
|
Feed Water Pump House/In Progress
|
Fuel Oil Pump House/In Progress
|
Auxiliary cooling water Pump House/ In progress
|
Generator Stator Lifting/Lifting in Progress
|
Generator Stator Lifting/Lifting in Progress
|
Generator Stator Lifting/Lifting in Progress
|
Generator Stator Lifting/Lifted to Position
|