Yeramarus Unit -1 (2 x 800 MW BTG+CIVIL)


ESP/In Progress

BAH Unit-1/In Progress

PRIMARY CRUSHER HOUSE-2/In Progress

BUNKER MCC/In Progress

SR MCC/In Progress

BCN 13A/B TR 16/ In progress

BCN-14A/B – TR4 /In Progress

STACKER RECLAIMER AREA FOUNDATION WORKS/In Progress

VACUUM PUMP HOUSE CUM COMPRESSOR HOUSE UNIT-1/In Progress

HT SWITCH GEAR ROOM/In Progress

ASH WATER PUMP HOUSE /In Progress

ASH SLURRY PUMP HOUSE /In Progress

WAGON TIPPLER -3/

WAGON TIPPLER -2/

WAGON TIPPLER -1/

JNT 9/In Progress

JNT 8/In Progress

JNT 7/In Progress

JNT 6/In Progress

JNT 5/In Progress

JNT 4/In Progress

JNT 3/ In progress

JNT 2/In Progress

JNT1/In Progress

Cooling Water Pump House/In Progress

Compressor House/In Progress

CWPH Electrical Annex Building/In Progress

DG Building/In Progress

FOPH Dyke area/In Progress

FOPH Unloading Area/In Progress

Common Control Room status at 17 Meter/In Progress

Common Control Room Battery Room/In Progress

Condensate Storage Tank Pump House/In Progress

CPU Building/In Progress

FO Pump house area/In Progress

Cooling Water Channeling Work/In Progress

Feed Water Pump House/In Progress

Fuel Oil Pump House/In Progress

Auxiliary cooling water Pump House/ In progress

Generator Stator Lifting/Lifting in Progress

Generator Stator Lifting/Lifting in Progress

Generator Stator Lifting/Lifting in Progress

Generator Stator Lifting/Lifted to Position