Home   

CHHABRA TPS UNIT - 4


Capacity Addition/FY 2014-15

COMMISSIONED UNIT/DEDICATED TO NATION

COMMISSIONED UNIT/DEDICATED TO NATION

COMMISSIONED UNIT/DEDICATED TO NATION

COMMISSIONED UNIT/DEDICATED TO NATION

COMMISSIONED UNIT/DEDICATED TO NATION

Feeder 4 EF/PROGRESS

Mill 4 EF/PROGRESS

Boiler # 4/PROGRESS

Boiler # 4/PROGRESS

CW PUMP HOUSE/UNDER PROGRESS

BATTERY ROOM/UNDER PROGRESS

MILL E

SECOND STREAM WORK/NOT YET STARTED

TRIPPER FLOOR CONVEYOR SYSTEM/WORK IN PROGRESS

BOTTOM ASH DISPOSAL SYSTEM/SLOW PROGRESS

CLINKER CONVEYOR/JUNCTION POINT CONDITION

GAS ROOM AREA/CIVIL WORKS IN PROGRESS: NO WAY TO SHIFT GAS CYLINDERS OR MOVEMENT OF MEN

GAS ROOM/NO APPROACH TO GAS ROOM: CIVIL WORKS IN PROGRESS

GAS ROOM/APPROACH TO GAS ROOM:GAS CYLINDERS THROWN AROUND BY CIVIL AGENCY

MILL E

MILL E

MILL E

MILL EF/TRAY WORK YET TO BE TAKEN UP

MILL EF/POWER AND CONTROL CABLING NOT DONE