COD COMPLETION/progress
|
COD COMPLETION/progress
|
Plant view/progress
|
Plant view/progress
|
Plant view/progress
|
Plant view/progress
|
Plant view/progress
|
Plant view/progress
|
Unit #3‐LP Turbine Erection/Under progress
|
Unit #3‐ID Fan‐B Erection/ Under Progress
|
Unit #3‐ID Fan‐A Erection /Under progress
|
Unit #3‐HP Turbine Insulation /Completed
|
Unit #3‐Generator Erection/In progress
|
Unit #3‐Front released for Bottom Ash Hopper/In progress
|
Unit #3‐Coal Pipe Erection/In progress
|
Unit #2‐TDBFP‐B erection/In progress
|
Unit #2‐TDBFP‐A erection/In progress
|
Unit #2 Generator Erection/In progress
|
Unit #2 Coal piping erection/In progress
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function/20th September, 2015
|
Inauguration Function /20th September, 2015
|
Inauguration Function /20th September, 2015
|
Inauguration Function /20th September, 2015
|
Inauguration Function /20th September, 2015
|
Inauguration Function /20th September, 2015
|
Inauguration Function /20th September, 2015
|
Inauguration Function /20th September, 2015
|
Unit#3 DMCW Pump Frame Erection/In progress
|
Unit #3‐ Stator Unloading/In progress
|
Unit #3 MDBFP Motor Erection/In progress
|
Unit #3‐ Condenser Dome Wall Erection/In progress
|
Unit # 3 HP Heater Alignment/In progress
|
Unit #2‐LPBP Line Balance 3 joints – Welding/In progress
|
Unit #2‐Erection of IP valve spring support/In progress
|
Unit #2‐Erection of HP valve spring support ( Left
|
Unit #2‐CRH to Deaerator Pegging line Work/In progress
|
/
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unit # 3/progress
|
Unit # 3/progress
|
Unit # 3/progress
|
Unit # 3/progress
|
Unit # 3/progress
|
Unit # 3/progress
|
unit#2/progress
|
unit#2/progress
|
unit#2/progress
|
unit#2/progress
|
unit#2/progress
|
Unit#1/progress
|
Unit#1/progress
|
Unit#1/progress
|
Unit#1/progress
|
Unit#1/progress
|
TG # 2/progress
|
TG# 1/progress
|
TG# 1/progress
|
TG# 1/progress
|
ESP #2
|
ESP #2
|
ESP #2
|
boiler # 3/progress
|
boiler # 3/progress
|
Boiler # 2/progress
|
Boiler # 2/progress
|
Boiler #1/progress
|
ESP 2-Insulation Under Progress/
|
ESP 2-Insulation Under Progress/
|
Unit 2- APH Erection Completed/
|
Unit 1- Turbine Insulation Completed/
|
Unit 1- CEP Erection Completed/
|
Unit 1- ESP Pass ‘D’ Insulation Under Progress/
|
ESP 3-Insulation Under Progress/
|
ESP 2-Insulation Under Progress/
|
Boiler 2-APH Erection Under Progress/
|
Unit‐1: TG Piping insulation/In Progress
|
Unit‐1: EDTA Cleaning Set Up/
|
UNIT 1- ASH HANDLING SYSTEM ERECTION IN PROGRESS (LPGCL SCOPE)/ In progress
|
UNIT 1- ID FAN TO CHIMNEY DUCT/In Progress
|
ACW CONTINGENCY ARRANGMENT BY LPGCL/
|
UNIT 1- COAL PIPING IN PROGRESS/ In progress
|
UNIT 1- SA DUCT INSULATION IN PROGRESS/ In progress
|
UNIT 1-RHS BUNKER SHELLS/In Progress
|
UNIT 1-RHS FEEDER FLOOR CIVIL WORKS COMPLETED (LPGCL SCOPE)/In Progress
|
CHP GALLERRIES ERECTION IN PROGRESS (LPGCL SCOPE)/In Progress
|
UNIT 1-CHP GALLERY FOR FEEDING BUNKERS (LPGCL SCOPE)/In Progress
|
CW SYSTEM (LPGCL SCOPE)/In Progress
|
UNIT1-BOILER INSULATION /In Progress
|
RAW WATER RESERVOIR, DM PLANT, WTP, CW PUMP HOUSE (LPGCL SCOPE)/ In progress
|
GT AREA
|
UNIT 1- PA
|
LDO
|
Light Up of Boiler Unit#1/
|
Wagon trippler (LPGCL scope)/In Progress
|
Erection of stacker reclaimers (LPGCL scope)/In Progress
|
Overview of AHP pump house (LPGCL scope)/In Progress
|
Overview of AHP pump house (LPGCL scope)/In Progress
|
Overview of CHP galleries and JNT erection (LPGCL scope)/In Progress
|
Overview of CHP galleries and JNT erection (LPGCL scope)/In Progress
|
Generator transformers/In Progress
|
Cooling towers/In Progress
|
CW Pump house and forebay/In Progress
|
DM Plant/In Progress
|
Main plant control room/In Progress
|
UNIT‐2: APH column foundation work/In Progress
|
UNIT‐3: TG Building /In Progress
|
UNIT‐3: Boiler Pass 1/In Progress
|
UNIT‐2: TG erection/In Progress
|
UNIT‐2: Condenser erection/In Progress
|
UNIT‐2: Boiler Erection/In Progress
|
UNIT‐1: MCC panel erection/In Progress
|
UNIT‐1: DCS panel erection/
|
UNIT‐1: TG erection/In Progress
|
UNIT‐1: RHS Mills/In Progress
|
UNIT‐1: LHS Mills/In Progress
|
UNIT‐1: RHS bunker Erection/In Progress
|
UNIT‐1: LHS bunker Erection/In Progress
|
UNIT‐1: Pipe Rack erection/In Progress
|
UNIT‐1: Pipe Rack erection /In Progress
|
UNIT‐1: ID fan B/In Progress
|
UNIT‐1: ID fan A /In Progress
|
UNIT‐1: FD fan A/In Progress
|
UNIT‐1: FD fan B/In Progress
|
UNIT‐1: Coal piping /In Progress
|
UNIT‐1:ESP erection/In Progress
|
UNIT‐1:Boiler Pass 2 insulation/In Progress
|
Unit‐1: Boiler Pass 1 insulation/In Progress
|
UNIT # 1 STG/LP box up
|
U # 2 BOILER/PROGRESS
|
U #1 FAN ERECTION/PROGRESS
|
BUNKER #1/PROGRESS
|
PLANT VIEW/PROGRESS
|
TG HALL/PROGRESS
|
TG HALL/PROGRESS
|
TG HALL/PROGRESS
|
TG HALL/PROGRESS
|
ESP #1/PROGRESS
|
U # 1 BOILER/PROGRESS
|
BOILER1/COAL PIPE COUPLING NOT AVAILABLE
|
BOILER1/WALL BLOWER SLEEVES NOT AVAILABLE PGMA-20204 DU-001
|
BOILER 1/SAFETY VALVE FOR MS LINE
|
TG 1/BFP foundation bolts are pending, Alignment held-up
|
TG 1/TDBFP Drive turbine foundation bolts
|
TG 1/ PIPING/TWIN COOLER FOR TDBFP-A PENDING
|
BOILER 3/ESP to ID fan Duct erection /WORK HELD UP DUE TO MATERIAL
|
BOILER 3/65 Nos Hanger and Screen assembly erected only One DU:07-223-006- 1qty required MDR:058, dated-21-11-13)
|
BOILER 3/Machine room approach platform Stairs
|
BOILER3/Headers are on lashing from 5 months , VLH Turnbuckle/Split pin/Locknut (against MDR) and Tie rod Turnbuckle for Imported VLH required (PG-MA:12-954-001 TO 013, 902, 903)
|
BOILER3/Tie rod of CLH req. (MDR-171)
|
BOILER3/WORK HELD UP DUE TO MATERIAL
|
ESP and ESP outlet to Chimney ducting Progress Image/PROGRESS
|
unit 3/Eco Coils preassembly under progress: PGMADU:19-814- 005: 1 qty is not available
|
unit 3/LTRH Coils preassembly under progress: PGMADU:16-235-001-1 qty is not available(MDR- 125, dated:11-03-14)
|
unit 3/Lift Structure along with purlins complete- 1. For Pit room and Machine room Civil drawing req. 2. Machine room approach platform Stairs: 38-820-All Du’s not available. 3. Metapoly sheets(PGMA:38-611-All Dus) not available.
|
unit 3/39-141: ESP Outlet Duct Support Structure; for approach platforms stairs are not available(39-820-AllDu’s)
|
Unit 3/39-101: ESP Inlet Duct Support Structure; for approach platforms stairs are not available(39-820-AllDu’s)
|
unit 1 boiler/Flash tank erection
|
unit 1 boiler/ID Fan to chimney ducting up-to terminal point(BHEL scope) completed
|
unit 1 boiler/P92 welding started for HRH piping- 1st time in Lalitpur
|
Unit 1 Boiler/Vertical roof enclosure work under progress
|
Unit 1 Boiler/CRH LINE-ERECTION WORK IN “CD” BAY
|
Mineral wool for pressure parts insulation not available at site/constraints
|
Hanger angle (256 nos.) holes wrongly drilled- Rework/Hanger angle (256 nos.) holes wrongly drilled- Rework
|
Castable
|
Flash tank exhaust pipe/work under hold for material(PGMA 80455)
|
UNIT 3/BOILER
|
UNIT 3/BOILER
|
UNIT 3/BOILER
|
UNIT 2/BOILER
|
UNIT 2/BOILER
|
UNIT 2/BOILER
|
UNIT 1/BOILER
|
UNIT 1/BOILER
|
UNIT 1/BOILER
|
UNIT 1/BOILER
|
MISC/PROGRESS
|
MISC/PROGRESS
|
MISC/PROGRESS
|
MISC/PROGRESS
|
MISC/PROGRESS
|
MISC/PROGRESS
|
UNIT 3 TG DECK/ERECTION WORKS
|
UNIT 1/CONDENSER
|
UNIT 1/CONDENSER
|
UNIT 3/BOILER
|
UNIT 3/BOILER
|
UNIT 2/SECOND PASS PP
|
UNIT 2/FIRST PASS PRESSURE PARTS
|
AHP
|
AHP
|
Unit 1 Boiler /Pressure parts erection
|
Unit 1 Boiler /Pressure parts erection
|