Unit 2 / Capacity Added in FY 2014-15
|
Shree Singaji TPP/Zero Coal Stock
|
CEPs Motor/Trial Completed, Trial Run After Condenser Flood Test
|
Condensers/Ready for Flood Test
|
Generator /Ready for ATT, Awaiting Seal Body from HWR
|
GTs /Ready for backcharging, switchyard side cabling and hardware fixing in final stages
|
Hot PA Duct Insulation/In Progress
|
MDBFP /Ready in all respects for Trial Run
|
RHS Bunker/Ready in all respects
|
RHS Feeders/Ready in all respects
|
RHS Mills/Ready in all respects
|
TDBFP-B/Oil Flushing Started
|