SHREE SINGAJI (MALWA) TPP STAGE-1 (2X600 MW)


Unit 2 / Capacity Added in FY 2014-15

Shree Singaji TPP/Zero Coal Stock

CEPs Motor/Trial Completed, Trial Run After Condenser Flood Test

Condensers/Ready for Flood Test

Generator /Ready for ATT, Awaiting Seal Body from HWR

GTs /Ready for backcharging, switchyard side cabling and hardware fixing in final stages

Hot PA Duct Insulation/In Progress

MDBFP /Ready in all respects for Trial Run

RHS Bunker/Ready in all respects

RHS Feeders/Ready in all respects

RHS Mills/Ready in all respects

TDBFP-B/Oil Flushing Started