Placement of PCC Unit 5 Module/PROGRESS
|
Placement of PCC Unit 5 Module/PROGRESS
|
Placement of PCC Unit 5 Module/PROGRESS
|
Generator #3/placed on foundation
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
Stack Foundation # 7/
|
/
|
/
|
DM plant/ In progress
|
GOOGLE EARTH SATELLITE VIEW/PROGRESS
|
TRANSFORMER YARDS/PROGRESS
|
TRANSFORMER YARDS/PROGRESS
|
TRANSFORMER YARDS/PROGRESS
|
TRANSFORMER YARDS/PROGRESS
|
TRANSFORMER YARDS/PROGRESS
|
SWITCH GEAR BLDG 1
|
SWITCH GEAR BLDG 1
|
SWITCH GEAR BLDG 1
|
RW
|
RODM TANK/PROGRESS
|
RODM BLDG/PROGRESS
|
PIPE RACK 1
|
PIPE RACK 1
|
Oil Pit/PROGRESS
|
MCC/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Material Storage/PROGRESS
|
Housing/PROGRESS
|
Housing/PROGRESS
|
Housing/PROGRESS
|
GT HALL/PROGRESS
|
GT HALL/PROGRESS
|
GT HALL/PROGRESS
|
GT HALL/PROGRESS
|
gcb
|
gcb
|
gcb
|
gcb
|
bore well /PROGRESS
|
bore well /PROGRESS
|
AVB # 4/PROGRESS
|
AVB # 4/PROGRESS
|
Director(Power)/
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Switch Gear Building wall/PROGRESS
|
Switch Gear Building wall/PROGRESS
|
Switch Gear Building wall/PROGRESS
|
UAT and Gen Transformer foundation/PROGRESS
|
UAT and Gen Transformer foundation/PROGRESS
|
Raw Water Tanks/PROGRESS
|
RODM/PROGRESS
|
Fire water tank and Pump House/PROGRESS
|
Pipe Rack foundation/PROGRESS
|
Switch Gear bldg 3/PROGRESS
|
Switch Gear bldg 2/PROGRESS
|
Switch Gear bldg 1/PROGRESS
|
RW
|
RW
|
RODM BLDG./PROGRESS
|
MCC bldg/PROGRESS
|
housing bldg 3/PROGRESS
|
GTG Hall 1,2,3/PROGRESS
|
GTG Hall 1,2,3/PROGRESS
|
GTG Hall 1,2,3/PROGRESS
|
GTG 4,5,6
|
GTG 4,5,6
|
GTG 4,5,6
|
GTG 4,5,6
|
GTG 7/casting
|
GT
|
GT
|
Generator/Arrived at site
|
GCB 7/PROGRESS
|
GCB
|
GCB
|
GCB
|
Air ventilation bldg 4/shuttering
|
Air ventilation bldg #3/column shuttering is in progress
|
Air Compressor bldg/Back filling
|
GT # 7/Turbine foundation
|
GT # 7 /Generator foundation
|
GT-6 /Foundation (3rd Foundation) completed on 26th May
|
GT-6 /Foundation (3rd Foundation) completed on 26th May
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|
CIVIL WORKS PROGRESS/CIVIL WORKS ACTIVITIES
|