Unit # 5 Unit Cabling Area/Erection of CableTrays
|
Unit# 5: MIV Inlet Pipe
|
Unit # 4 CW Motor Pump
|
Unit # 4 Unit Cabling Area
|
Unit # 3 Unit Cabling Area
|
Unit# 3- MIV Platform Erection
|
Unit # 2 Unit Cabling Area
|
Unit#2: Unit Cabling
|
Common- HV AC Pump
|
Unit # 1 Unit Cabling Area
|
U# 1- Dowelling of GV Servomotor
|
Unit-4: Motor Alignment of CW Pump
|
Unit-2: Cable Termination Check at ASE- EP2 Panel
|
U# 5-Welding of Inlet Pipe & MIV
|
Unit # 3- Erection of IPBD
|
Unit# 1- Cable Glanding at RTU-TF
|
Unit# 1- Cable Glanding at RTU-GF
|
Unit# 3 - MIV Area -Oil Pipeline Erection
|
Unit # 3: Unit Cabling Area
|
Unit#2: CW Area- Motor Pump Alignment
|
Unit#2: Unit Cabling
|
Unit # 1 Field Efficiency Pipelines
|
Unit # 1 Unit Cabling Area
|
Unit # 1 Unit Cabling Area
|
Unit # 6 Unit Cabling Area
|
Unit# 5 Welding of Inlet Pipe of MIV with Penstock
|
Unit# 4- Painting of CW Pipelines
|
Unit # 3: Erection of Cable Trays.
|
Unit #3: Oil and Water Pipelines in MIV Area
|
Unit#2: Alignment of CW Motor Pumps
|
Unit # 2 Painting of Generator CW Pipelines
|
Unit # 1: Pipeline Erection in MIV Area
|
Unit # 1 Unit Cabling Area
|
Unit # 1 Unit Cabling Area
|
U#6: Cable Termination Works under progress.
|
U#6: Painting of CW Pipelines
|
U# 5-Welding of Inlet Pipe of MIV with Penstock
|
U#4: Cable Termination Works under progress
|
U#3: Installation of Oil Pipelines of MIV
|
U#3: Erection of Cable Trays in Bus Duct Gallery
|
U#3: Installation of AUX/Bypass Valve of MIV
|
U#3: Erection of Cable Trays below Turbine Floor
|
Unit#2: Alignment of Motor for CW Pumps
|
Unit#2: Painting of Generator CW Pipelines
|
Unit# 1- Erection of Platform of MIV
|
Unit# 1- Cable Termination at GMB
|
Unit# 1: Unit Cabling
|
U# 6- Cable Termination at SEE Panel
|
U# 6- Painting of CW Pipelines
|
U# 5-Preparation for Welding of Inlet Pipe & MIV
|
Unit# 4- Cable Termination at MCP for Top Cvr Drng
|
Unit# 4- Cable Termination of Governor OPU Pump
|
Unit# 3- Erection of Cable Trays below Turbine Flr
|
Unit#1: Pressure Test of Field Efficiency Pipeline
|
Unit# 3- Erection of Drain Pipelines of MIV
|
Unit-2: Motor Alignment of CW Pump
|
Unit# 1- Cable Glanding at RTU-GF
|
Unit#6- Cable Termination at SEE Panel
|
Unit#6- Painting of CW Pipelines
|
Unit# 6- Cable Termination Turbine Junction Boxes
|
Unit #6- Cable Termination at RTU-TF
|
Unit # 6- Cable Glanding at MCP for Raw CW System
|
Unit # 4- Painting of CW Pipelines
|
Unit # 3- Stroke Checking of MIV Servomotor
|
Unit # 2- Painting of CW Pipelines
|
Unit# 2- Painting of Pipelines
|
Unit#1- Cable Glanding & Termination at CW Pump
|
Unit#1- Clamping of CW Water Pipelines
|
Unit# 1- Cable Termination @RTU-Trubine Floor
|
U#2:- Penstock Drain Valve and Pipe Assy.
|
U#4:- Painting of CW Water Pipe Lines
|
U#4:- Painting of MIV Oil Pipe lines
|
U#2:- Painting of Oil & Water Pipes (Turbine Pit)
|
View of Machine Hall as seen from S/B Area.
|
Unit#5: Installation of CW Pipelines
|
Unit# 5- Instrumentation of Stator
|
Unit# 4: Cable Termination at RTU-Turbine Floor
|
Unit#4- Cable Dressing & Glanding at ASE Panels
|
Unit#2: Installation of Drain Pipeline of Penstock
|
Unit# 2: Installation of N2 Pipelines of MIV
|
Unit # 2: Erection of Cable Trays at Bus Duct Area
|
Unit#2: Cable Glanding & Termination at GMB
|
Unit# 1: Installation of Cable Trays .
|
Unit# 1: Installation of Cable Trays .
|
Unit# 3- Installation of Bottom Air Guide Assembly
|
Unit# 3- Erection of TGB Coolers CW Pipelines.
|
Unit# 3 Cooling Water Pipeline Erection
|
Unit# 3 Cooling Water Pipeline Erection
|
Pre-Erection Test of Dry Type Transformer in BD-2
|
Unit#5: Oil Filling of LGB under progress.
|
Unit#5: Installation of Generator-CW Pipelines
|
Unit #4: Cabling of UCS/ ASE
|
Unit# 2: Installation of MIV Counterwight
|
Unit # 3: Final Assy. of DT Cone
|
Unit #6: Laying of Cables for CW System
|
Unit#6: CW Pipelines- Clamping under progress.
|
Unit #5: Raw CW Pipelines
|
Unit#5: Regulating Ring
|
Unit# 3: Cable Tray Erection- Generator Floor
|
Unit # 2- Cable Glanding-RTU TF
|
Unit # 1: Instrumentation of Stator
|
Unit # 5- Installation of CW Pipelines
|
Unit# 2:Stroke Checking of MIV Servomotor
|
Unit # 5: Installation of LGB Oil Coolers
|
Unit#5: Installation of Air Guide & Air Baffle
|
Unit#5: Bearing Box Up
|
Unit # 6: Pressure Test of CW Pipelines
|
Unit #4: Laying of Cables running below Gen. Floor
|
U#2: Installation of Excitation Transformer
|
U#6: Trays for Cable Running Below MH Floor
|
Unit # 5- Lowering of Top Bracket Assy. on Stator
|
Unit # 6- Cable Tray Below Turbine Floor
|
Unit # 5- Top Bracket Assembly
|
Unit # 5- Lowering Generator Top Shaft
|
Service Bay Area
|
Service Bay - Repainting of Dry Type Transformers
|
Unit # 4- Cable Tray Below Turbine Floor
|
Unit # 5- Alignment of Shafts under Progress
|
U#VI:-Oil Pipe lines for MIV seal, By pass Valves
|
U#III:- Welding and DPT on CW pipe lines
|
U#VI:- Erection of MIV Seal OPU Pipe Lines
|
U#VI:- Erection of MIV Platform
|
Unit # 4- Cable Tray Below in MIV Floor
|
Unit # 6- Generator Air Guide Assembly
|
Lowering of U # 5- Generator- Rotor on 29-12-2021
|
Unit # 5- Generator Bottom Shaft Lowered in Pit.
|
Lowering of Unit # 5- Generator Bottom Shaft
|
Bust Duct Gallery # 2 Area
|
Bust Duct Gallery # 1 Area
|
U#2- Erection of Shaft seal primary filter arrangement
|
U#1- Installation of MIV servomotors
|
U#4- Final assy of pivot ring Pr. balancing pipes
|
CW system common header for all units
|
U#6:- MIV servo base plate leveling and centering
|
U#3:- Erection of Gov.HMC oil pipe lines
|
U#VI:- Welding on 125NB CW header
|
U#IV:- Dowelling on TGB Housing
|
U#I:- Levelling, centering of MIV servo base plate
|
Unit # 4- Cable Tray Below Machine Hall Floor
|
Unit # 1 MIV- Servomotor Area
|
U#2- Transformer coolers CW Pipe erection
|
Bust Duct Gallery # 2 Area
|
Unit # 4- Cable Tray Below Machine Hall Floor
|
Unit # 4- Turbine Pit
|
S/B Area- Assembly of U#5- Spring Plate Assembly
|
View of Machine Hall from Service Bay
|
Installation of U#4- Shaft Seal Cooling Water Pipe
|
Installation of R,Y and B Phase-HV Bushings
|
Installation of U# 6- GV Servomotor Pipelines
|
Unit-1,2,4 boxed up
|
View of Ongoing Works in U#5- Bottom Bracket Assy.
|
Installation of Cable Tray below U # 6-Generator Floor
|
Oil Filling of U#3 LGB Housing Completed.
|
Inst. of Cable Tray below U # 4-Generator Floor
|
Installation of Servo Motor of U#6 MIV
|
Installation of GT CW Piplines in Bust Duct # 2
|
Unit#5-View of Machine Hall Floor
|
Unit # 4- View of Machine Hall Floor
|
Unit # 2- View of Machine Hall Floor
|
Unit # 1- View of Machine Hall Floor
|
Opening of Door of BFV# 2
|
ICTs in Pothead Yard
|
Ext. of CW Pipelines of GTs in Bus Duct Galle
|
Unit #2 - Erection of Cable Trays
|
Unit #4 - Erection of Cable Trays
|
Oil Filling of U# 3-TGB Housing Completed
|
Post Weld Heat Treatment of U#6 MIV & Penstock
|
Unit # 3- Oil Filling of LGB Under Progress
|
Machine Hall View from Service Bay Area
|