Home   

Punatsangchhu-I(Hyrdo), BHUTAN


Unit # 5 Unit Cabling Area/Erection of CableTrays

Unit# 5: MIV Inlet Pipe

Unit # 4 CW Motor Pump

Unit # 4 Unit Cabling Area

Unit # 3 Unit Cabling Area

Unit# 3- MIV Platform Erection

Unit # 2 Unit Cabling Area

Unit#2: Unit Cabling

Common- HV AC Pump

Unit # 1 Unit Cabling Area

U# 1- Dowelling of GV Servomotor

Unit-4: Motor Alignment of CW Pump

Unit-2: Cable Termination Check at ASE- EP2 Panel

U# 5-Welding of Inlet Pipe & MIV

Unit # 3- Erection of IPBD

Unit# 1- Cable Glanding at RTU-TF

Unit# 1- Cable Glanding at RTU-GF

Unit# 3 - MIV Area -Oil Pipeline Erection

Unit # 3: Unit Cabling Area

Unit#2: CW Area- Motor Pump Alignment

Unit#2: Unit Cabling

Unit # 1 Field Efficiency Pipelines

Unit # 1 Unit Cabling Area

Unit # 1 Unit Cabling Area

Unit # 6 Unit Cabling Area

Unit# 5 Welding of Inlet Pipe of MIV with Penstock

Unit# 4- Painting of CW Pipelines

Unit # 3: Erection of Cable Trays.

Unit #3: Oil and Water Pipelines in MIV Area

Unit#2: Alignment of CW Motor Pumps

Unit # 2 Painting of Generator CW Pipelines

Unit # 1: Pipeline Erection in MIV Area

Unit # 1 Unit Cabling Area

Unit # 1 Unit Cabling Area

U#6: Cable Termination Works under progress.

U#6: Painting of CW Pipelines

U# 5-Welding of Inlet Pipe of MIV with Penstock

U#4: Cable Termination Works under progress

U#3: Installation of Oil Pipelines of MIV

U#3: Erection of Cable Trays in Bus Duct Gallery

U#3: Installation of AUX/Bypass Valve of MIV

U#3: Erection of Cable Trays below Turbine Floor

Unit#2: Alignment of Motor for CW Pumps

Unit#2: Painting of Generator CW Pipelines

Unit# 1- Erection of Platform of MIV

Unit# 1- Cable Termination at GMB

Unit# 1: Unit Cabling

U# 6- Cable Termination at SEE Panel

U# 6- Painting of CW Pipelines

U# 5-Preparation for Welding of Inlet Pipe & MIV

Unit# 4- Cable Termination at MCP for Top Cvr Drng

Unit# 4- Cable Termination of Governor OPU Pump

Unit# 3- Erection of Cable Trays below Turbine Flr

Unit#1: Pressure Test of Field Efficiency Pipeline

Unit# 3- Erection of Drain Pipelines of MIV

Unit-2: Motor Alignment of CW Pump

Unit# 1- Cable Glanding at RTU-GF

Unit#6- Cable Termination at SEE Panel

Unit#6- Painting of CW Pipelines

Unit# 6- Cable Termination Turbine Junction Boxes

Unit #6- Cable Termination at RTU-TF

Unit # 6- Cable Glanding at MCP for Raw CW System

Unit # 4- Painting of CW Pipelines

Unit # 3- Stroke Checking of MIV Servomotor

Unit # 2- Painting of CW Pipelines

Unit# 2- Painting of Pipelines

Unit#1- Cable Glanding & Termination at CW Pump

Unit#1- Clamping of CW Water Pipelines

Unit# 1- Cable Termination @RTU-Trubine Floor

U#2:- Penstock Drain Valve and Pipe Assy.

U#4:- Painting of CW Water Pipe Lines

U#4:- Painting of MIV Oil Pipe lines

U#2:- Painting of Oil & Water Pipes (Turbine Pit)

View of Machine Hall as seen from S/B Area.

Unit#5: Installation of CW Pipelines

Unit# 5- Instrumentation of Stator

Unit# 4: Cable Termination at RTU-Turbine Floor

Unit#4- Cable Dressing & Glanding at ASE Panels

Unit#2: Installation of Drain Pipeline of Penstock

Unit# 2: Installation of N2 Pipelines of MIV

Unit # 2: Erection of Cable Trays at Bus Duct Area

Unit#2: Cable Glanding & Termination at GMB

Unit# 1: Installation of Cable Trays .

Unit# 1: Installation of Cable Trays .

Unit# 3- Installation of Bottom Air Guide Assembly

Unit# 3- Erection of TGB Coolers CW Pipelines.

Unit# 3 Cooling Water Pipeline Erection

Unit# 3 Cooling Water Pipeline Erection

Pre-Erection Test of Dry Type Transformer in BD-2

Unit#5: Oil Filling of LGB under progress.

Unit#5: Installation of Generator-CW Pipelines

Unit #4: Cabling of UCS/ ASE

Unit# 2: Installation of MIV Counterwight

Unit # 3: Final Assy. of DT Cone

Unit #6: Laying of Cables for CW System

Unit#6: CW Pipelines- Clamping under progress.

Unit #5: Raw CW Pipelines

Unit#5: Regulating Ring

Unit# 3: Cable Tray Erection- Generator Floor

Unit # 2- Cable Glanding-RTU TF

Unit # 1: Instrumentation of Stator

Unit # 5- Installation of CW Pipelines

Unit# 2:Stroke Checking of MIV Servomotor

Unit # 5: Installation of LGB Oil Coolers

Unit#5: Installation of Air Guide & Air Baffle

Unit#5: Bearing Box Up

Unit # 6: Pressure Test of CW Pipelines

Unit #4: Laying of Cables running below Gen. Floor

U#2: Installation of Excitation Transformer

U#6: Trays for Cable Running Below MH Floor

Unit # 5- Lowering of Top Bracket Assy. on Stator

Unit # 6- Cable Tray Below Turbine Floor

Unit # 5- Top Bracket Assembly

Unit # 5- Lowering Generator Top Shaft

Service Bay Area

Service Bay - Repainting of Dry Type Transformers

Unit # 4- Cable Tray Below Turbine Floor

Unit # 5- Alignment of Shafts under Progress

U#VI:-Oil Pipe lines for MIV seal, By pass Valves

U#III:- Welding and DPT on CW pipe lines

U#VI:- Erection of MIV Seal OPU Pipe Lines

U#VI:- Erection of MIV Platform

Unit # 4- Cable Tray Below in MIV Floor

Unit # 6- Generator Air Guide Assembly

Lowering of U # 5- Generator- Rotor on 29-12-2021

Unit # 5- Generator Bottom Shaft Lowered in Pit.

Lowering of Unit # 5- Generator Bottom Shaft

Bust Duct Gallery # 2 Area

Bust Duct Gallery # 1 Area

U#2- Erection of Shaft seal primary filter arrangement

U#1- Installation of MIV servomotors

U#4- Final assy of pivot ring Pr. balancing pipes

CW system common header for all units

U#6:- MIV servo base plate leveling and centering

U#3:- Erection of Gov.HMC oil pipe lines

U#VI:- Welding on 125NB CW header

U#IV:- Dowelling on TGB Housing

U#I:- Levelling, centering of MIV servo base plate

Unit # 4- Cable Tray Below Machine Hall Floor

Unit # 1 MIV- Servomotor Area

U#2- Transformer coolers CW Pipe erection

Bust Duct Gallery # 2 Area

Unit # 4- Cable Tray Below Machine Hall Floor

Unit # 4- Turbine Pit

S/B Area- Assembly of U#5- Spring Plate Assembly

View of Machine Hall from Service Bay

Installation of U#4- Shaft Seal Cooling Water Pipe

Installation of R,Y and B Phase-HV Bushings

Installation of U# 6- GV Servomotor Pipelines

Unit-1,2,4 boxed up

View of Ongoing Works in U#5- Bottom Bracket Assy.

Installation of Cable Tray below U # 6-Generator Floor

Oil Filling of U#3 LGB Housing Completed.

Inst. of Cable Tray below U # 4-Generator Floor

Installation of Servo Motor of U#6 MIV

Installation of GT CW Piplines in Bust Duct # 2

Unit#5-View of Machine Hall Floor

Unit # 4- View of Machine Hall Floor

Unit # 2- View of Machine Hall Floor

Unit # 1- View of Machine Hall Floor

Opening of Door of BFV# 2

ICTs in Pothead Yard

Ext. of CW Pipelines of GTs in Bus Duct Galle

Unit #2 - Erection of Cable Trays

Unit #4 - Erection of Cable Trays

Oil Filling of U# 3-TGB Housing Completed

Post Weld Heat Treatment of U#6 MIV & Penstock

Unit # 3- Oil Filling of LGB Under Progress

Machine Hall View from Service Bay Area