U#4 Top air guide installation
|
U#4 Impeller nut guard final assembly and levellin
|
U#2 & 3 CW pipeline instrumentation
|
U#3 Turbine oil cooler water piping
|
U#4 Machine centering and locking ocmpleted
|
U#3 Field efficiency pipeline routing in progress
|
U#6 spiral casing welding in progress
|
U#3 Cyclone separator drain pipeline routing
|
U#3 UGB oil retainer installation in progress
|
U#3 GV pressure receiver air pipeline routing i/p
|
U#4 HP, LP compressed air pipeline routing in prog
|
U#1&2 Busduct CT`s pre erection testing
|
U#3 MDV penstock makeup piece installation
|
U#2 Temporary CW line routing is completed
|
U#3 Compressed air pipeline routing in progress
|
U#3 Impeller band drain valve
|
U#3 Top oil vapour piping
|
U#3 Bottol oil vapour seal piping
|
U#3 Water depression pipeline routing in progress
|
U#1 GV Air receiver leak test in progress
|
U#3 Unit oil manifold pipeline routing in progress
|
U#3 Impeller band drain pipeline routing completed
|
U#5 HS pipeline routing and testing completed
|
U#3 MDV inlet pipe welding in progress
|
U#3 servooperated valve 10nb pipeline routing i/p
|
U#4 Pit air seal installation in progress
|
U#3 LGB vapour seal installation completed
|
U#6 spiral segments backstrip welding in progress
|
U#5 rotor rim building in progress
|
U#5 brake jack hydraulic testing in progress
|
U#5 Spring plate assy on bracket completed
|
U#5 bottom shaft lowered into barell
|
U#3 WDS pipeline routing in progress
|
U#3 PGB coolers assy on housing
|
U#3 pgb oil cooler hydraulic testing in progress
|
U#3 mdv inlet pipe welding in progress
|
U#3 GV oil pipelines acid cleaning in progress
|
U#4 mdv base plates erection in progress
|
U#6 spiral segments positioning in progress
|
U#5 spring plate assy around shaft in progress
|
U-3 LGB coolers final assy in progress
|
U-3 gv oil pipelines testing completed
|
U-3 MDV inlet pipe alignment completed
|
U-6 spiral segments positioning in progress
|
U-5 Bottom bracket lowered into barell
|
U-5 Sole plates levelling completed
|
U#10 spiral casing pedestals casting
|
U#6 stay ring halves welding
|
U#2 Discahrge valve pipelines
|
U#3 Water and air pipelines inside turbine pit
|
U#3 spiral casing outlet pipe installation
|
U#3 spiral casing outlet pipe installation
|
U#2 MDV Servomotor secondary concreting completed
|
U#1 MDV push pull bolt rework
|
U#2 10nb pipelines acid cleaningdone reassembly ip
|
U#10 spiral casing pedestal casting in progress
|
U#3 Turbine bearing gap setting completed
|
U#3 Brake jack pipeline routing
|
U#2 Water pipelines inside turbine pit
|
U#2 MDV Servomotor alignment completed
|
U#6 stay ring levelling and joining
|
U#5 bottom shaft cleaning
|
U#3 spiral makeup piece edge preparation
|
U#3 UGB Pads installation
|
U#3 PGB Housing leak test
|
U#2 GV Servomotor oil pipelines
|
U#2 MDV Servomotor alignment
|
U#2 bypass valve 300nb pipeline
|
400NB Dewatering header pipeline routing
|
U#5 Stator winding cap filling
|
U#3 UGB Pads assembly
|
U#3 PGB Housing assembly
|
U#1 Stator Dowelling
|
U#2 Shaft seal CW pipeline routing
|
U#2 Ejector pipeline routing
|
U#2 GV Servomotor oil pipeline routing
|
U#1 Water depression header pipeline hydrotesting
|
U#1 GV Servomotor LVDT Installed
|
D&D Sump-2 VT pump installation inprogress
|
D&D sump-1 VT Pump installed
|
U#1 Auxiliary panel cable termination
|
U#5 Stator bus bar joints brazing
|
U#3 PGB oil sump assembly
|
U#2 MDV and Servomotor
|
U#2 stator sole plate doweliing
|
U#2 LP air line tapping to brake panel
|
U#1 Auxiliaries cable termination
|
U#1 MDV Base plates secondary concreting
|
U#1 MDV Base plates secondary concreting
|
water depression system main air header routing
|
Starion air and WDS compressor system in service b
|
U#3 Bottom air guide installation in progress
|
U#2 ET LAVT positioned at ground level
|
U#2 Carbon brush assembly completed
|
U#2 GV Servomotor oil pipelines hydraulic testing
|
U#1 MDV Pipelines routing
|
U#1 GV DV Receivers HP air connections routing
|
U#1 MDV Outlet pipe, penstock welding i/p
|
U#1 Shaft seal panel CW line routing completed
|
U#1 Bypass valve installed and pipeline routing
|
U#1 LAVT and ET positioned at ground level
|
U#5 Stator top and bottom bars brazing
|
Staion air compressors and receivers
|
LP Header routing in turbine floor
|
Staion compressors and receivers positioning
|
U#2 MDV outlet pipe welding i/p
|
U#2 LGB Vapour seal assy in progress
|
U#2 Top bearing instrumentation completed
|
U#1 Brake dust collector flexible piping
|
U#1 Water and air pipelines routing
|
U#1 Turbine bearing CW outlet piping
|
U#1 WDS Air receiver positioning completed
|
U#2 Water air pipelines routing i/p
|
U#1 band drain pipeline routing is completed
|
U#1 Cable trays routing
|
U#1 MDV Outlet pipe penstock welding
|
Dewatering sump-1 pipeline routing in progress
|
U#10 dt liner alignment in progress
|
U#2 DT Drain valves installation in progress
|
U#2 water and air pipelines inside pit
|
U#2 water depression air release pipeline
|
U#1 Water and air pipelines inside pit
|
U#1 MDV Servomotor pipeline routing
|
U#1 Water depression receiver positioning i/p
|
U#1 cyclone seperator drain pipeline
|
U#1 shaft seal cw pipeline
|
U#1 UGB oil filling and filtration
|
U#10 DT Liner radial stays assembly
|
U#6 DT Cone lowering completed
|
U#5 stator top bar laying in progress
|
U#3 Top air guide installation in progress
|
U#3 Shaft seal installation in progress
|
U#2 TGB Housing leak test completed
|
U#1 Water and air pipelines routing
|
U#1 Water depression air release pipeline routing
|
U#1 LGB Instrumentaion works in progress
|
U#1 UGB Instrumentation works in progress
|
D&D sump-1 400nb header pipe routing in progress
|
D&D sump-1 pump pedestals erectioncompleted
|
SFC transformers grouting in progress
|
U#2 turbine bearing housingassy completed
|
U#2 bottom bearing assy in progress
|
U#2 Top bearing assy is in progress
|
U#1 GV Lever stopper positioning and welding
|
U#1 water and air pipeline assy in turbine pit
|
U#1 bearing instrumentation in progress
|
U#1 busduct welding at surface level in progress
|
U#1 motor transformer oil filtration in prorgess
|
U#4 CW system works in progress
|
U#4 Motor shaft coupling nut guard assy is complet
|
U#3 LGB sole plates locking is completed
|
U#2 turbine bearing housingassy in progress
|
U#1 oil manifold pipeline routing is completed
|
U#1 LGB assembly completed
|
U#1 UGB assembly completed
|
U#7 DT segments alignment with unit axis is in pro
|
U#5 GV sevomotor reassembly is completed
|
U#4 Motor shaft coupling nut guard assembly is in
|
U#4 Tubular shaft assembly and alignment is in pro
|
U#3 Installation of shaft seal is in progress
|
U#2 Installation of shaft seal is completed
|
U#1 LGB coolers and pipeline assembly is in progre
|
U#1 Top coolers assembly is in progres
|
SFC Transformer LV Bushing assy completed
|
SFC Transformer hv bushing assy completed
|
U#5 gv servomotor foundation block welding i/p
|
U#5 stator segments positioning in progress
|
U#4 CWS pipeline routing in progress
|
U#3 impeller nutguard assy and welding in progress
|
U#2 mdv servomotor leakage test in progress
|
U#1 Cable tray laying in progress
|
U#2 shaft seal installation in progress
|
U#1 10nb pipeline for servo valve routing in progr
|
U#1 Turbine bearings assy in progress
|
Pkg-8 SFC Transformers 2 sets
|
SFC O/P Transformer HV & LV Bushings assy complete
|
U#5 GV Servomotor dowelling in progress
|
U#4 CWS pump to strainer piping in progress
|
U#4 LGB coolers testing in progress
|
U#3 Motor transformer hv bushings assy completed
|
U#2 MDV inlet pipe welding in progress
|
U#2 Motor Transformer HV Bushing assy completed
|
U#1 Cable tray laying in progress
|
U#1 TGB Housing leak test in progress
|
U#1 GV Servomotor oil pipelines routing i/p
|
U#1 LGB Cooler piping assembly in progress
|
U#1 Top bearing final assembly in progress
|
U#9 spiral casing pedestals casting completed
|
U#4 top gb pads blue matching in progress
|
U#4 CW Strainer skid works completed
|
U#4 Turbine shaft alignment completed
|
U#2 cable tray laying is in progress
|
U#2 turbine bearing sump assy in progress
|
U#1 Cable trays laying is in progress
|
U#1 Motor transformer
|
U#2 MDV and outlet pipe assy completed
|
U#1 Turbine GB Housing assembly in progress
|
U#5 GV servomotor welding is in progress
|
U#4 top gb pads blue matching in progress
|
U#4 CW pump motor skid
|
U#4 motor turbine shafts coupling in progress
|
U#2 oil pipeline routing in progress
|
U#2 MDV lowering completed
|
U#1 LGB coolers assy in progress
|
U#1 Turbine GB Housing assembly in progress
|
U#5 servomotor connecting rod assy in progress
|
U#4 Top bracket lowering completed
|
U#2 MDV inlet & outlet pipe lowered
|
U#2 oil pipeline routing in progress
|
U#1 oil pipeline hydraulic testing in progress
|
U#1 shaft seal installation and testing completed
|
U#2 Cable tray laying
in progress
|
U#1 Cable tray laying in progress
|
U#9 Spiral casing pedestals casting i/p
|
U#4 Motor CW pipeline outside barell routing compl
|
U#2 impeller nut guard cap welding completed
|
U#1 olu installation completed
|
U#4 Top bracket arms assembly completed
|
U#4 Rotor lowering completed
|
U#4 Rotor lowering completed
|
U#2 Spiral edge preparation is in progress
|
U#1 shaft seal installation in progress
|
U#4 Motor CW pipeline outside barell routing i/p
|
U#4 motor cw pipeline routing inside barell comple
|
U#4 Rotor final HV completed
|
U#4 bottom shaft lowering completed
|
U#1 shaft seal wfs shifting in progress
|
U#1 oil pipelines routing in progress
|
U#1 shaft seal installation in progress
|
Dewatering sump 2 pump erection completed
|
U#5 Guide apparatus assembly is in progress
|
U#4 Top bracket arms assembly in progress
|
U#1 water depression pipeline routing is in progre
|
U#2 Brake jack pipeline routing completed
|
U#1 Impeller coupling nutguard joint welding compl
|
U#5 Inner top cover lowering completed
|
U#3 CW 350>300nb pipeline routing completed
|
U#4 Rotor pole mounting completed
|
U#3 Turbine CW piping outside barrel completed
|
U#1 Top vapour piping routing is completed
|
U#2 Cooler support pads welding is in progress
|
U#1 Waterdepression pipeline routing in progress
|
U#5 impeller coupling bolt elongation is completed
|
U#4 rotor rim building is completed
|
U#4 stator cw pipeline routing is in progress
|
U#1 water depression pipeline routing is in progre
|
U#1 Impeller coupling nut guard joint is completed
|
U#1 Top vapour piping routing is completed
|
Dewatering sump-2 pipeline routing in progress
|
U#5 TGB pads blue matching is in progress
|
U#4 Rotor rim building is in progress
|
U#4 bottom shaft cleaning and pad matching in prog
|
U#3 Labyrinth CW pipelines routing is in progress
|
U#2 top oil vapour piping routing is in progress
|
U#2 CW main headers near DT routing is in progress
|
U#2 Bottom vapour seal trial assy is completed
|
U#1 gauge panel positioning is in progress
|
U#1 CW main headers near dt routing completed
|
U#1 top vapour seal trial assy is in progress
|
Dewatering sump-2 pipeline routing in progress
|
U#8 spiral pedestals casting is in progress
|
U#5 TGB pads blue matching is in progress
|
U#5 Guide apparatus assembly is in progress
|
U#5 Impeller lowering completed
|
U#4 Pressure Equalizing lines routing is completed
|
U#4 Installation of turbine platform is in progess
|
U#2 bottom vapour seal trial assy in progress
|
U#2 CW pipeline routing is in progress
|
U#1 CW pipeline routing is in progress
|
U#8 spiral pedestals casting is in progress
|
U#7 Spiral casing pedestals casting is completed
|
U#5 Guide apparatus assembly is in progress
|
U#4 pump pit platform installation in progress
|
U#4 pipeline routing at discharge valve floor i/p
|
U#4 Rotor rim building is in progress
|
U#2 bottom vapour seal trial assy in progress
|
U#1 Motor transformer lv turrets installed
|
U#1 Motor Transformer hv bushing installed
|
Dewatering pump erection is in progress
|
U#8 dt liner concreting is in progress
|
U#7 Spiral casing pedestals casting is in progress
|
U#5 Guide Apparatus trial assy in progress
|
U#4 Rotor rim building is in progress
|
U#4 Installation of turbine platform is in progess
|
U#3 MDV base plates positioning is completed
|
U#3 panels positioning is in progress
|
U#2 Top vapour seal trial assy completed
|
U#1 Transformer HV turrets mounting is in progress
|
U#9 DT elbow liner alignment is in progress
|
U#8 Positioning ofhooks for dt cone is in progress
|
U#7 Spiral casing pedestals casting is in progress
|
U#5 Guide apparatus assembly is in progress
|
U#5 Preparation of inner top cover for lowering
|
U#3 Panels shifting is in progress
|
U#3 MDV base plates positioning is in progress
|
U#2 Panels positioning on motor floor completed
|
U#2 Top vapour pipeline routing in progress
|
U#2 Top vapour seal trial assy in progress
|
U#8 Spiral drain pipeline routing in progress
|
U#7 DT Elbow liner concreting in progress
|
U#6 dt elbow liner concreting completed
|
U#2 Top bearing assy is in progress
|
U#5 Guide vanes lowering is in progress
|
U#4 Shear pins assembly is in progress
|
U#3 MDV base plates positioning is in progress
|
U#2 receivers positioning is in progress
|
U#1 Starter panels positioning in progress
|
U#1 MDV Servomotor positioning completed
|
U#1 Transformer oil conservator&coolers erection
|
U#1 Busduct installation at ground level
|
U#5 Stator sole plates positioning levelling compl
|
U#5 LGB Sole plates positioning and levelling i/p
|
U#5 OTC welding completed lowering in progress
|
U#4 Monorail installation is in progress
|
U#4 GV Servomotors reassembly in progress
|
U#4 Bottom bracket jack post welding is in progres
|
U#5 Stator sole plate positioning in progress
|
U#5 OTC quadrants welding in progress
|
U#4 Monorail installation is in progress
|
U#4 GV Servomotors reassembly in progress
|
U#4 brake jacks positioning completed
|
U#4 brake jacks positioning completed
|
U#4 HS piping inside bottom bracket completed
|
U#1 Governing receivers foundation casting i/p
|
U#1 Transformer oil conservator&coolers erection
|
U#5 stator sole plates hole correction in progress
|
U#7 DT Elbow liner alignment correction in progres
|
U#5 gv cleaning and feather height measurement i/p
|
U#5 OTC quadrants welding in progress
|
U#4 spring plate dowels matching in progress
|
U#4 Stator air coolers installation in progress
|
U#4 GV Servomotor foundation block welding in prog
|
U#3 MDV OPU CW pipeline welding in progress
|
U#2 Bottom air guide final assy completed
|
U#5 Guide Apparatus trial assy in progress
|
U#10 dt liner segments welding is in progress
|
U#5 Stator sole plate positioning in progress
|
U#4 GV Servomotor welding in progress
|
U#4 HS Skid positioning completed piping in progre
|
U#4 LGB Lowering completed
|
U#4 Stator air cooler hydraulic testing in progres
|
U#3 GV OPU CW pipeline routing in progress
|
U#3 MDV OPU CW pipeline routing in progress
|
U#3 Cooling water system at turbine floor
|
U#3 Firefighting panel positioning in progress
|
U#1 GV DV Receivers and panels positioning i/p
|
U#5 Pivot ring quadrants levelling assembly comple
|
U#4 Stator instrumentation completed
|
U#4 LGB Sole plates levelling in progress
|
U#4 GV Servo motors testing is in progress
|
U#3 cyclone seperator outlet piping completed
|
U#3 CW System skids positioned
|
U#10 DT Elbow liner all segments positioning compl
|
U#9 DT Elbow liner
|
U#8 DT Drain box installation in progress
|
U#7 DT ELbow liner
|
U#5 Foundation ring grouting plugs welding in prog
|
U#5 Pivot ring quadrants cleaning in progress
|
U#4 ITC & GV Servomotors lowering completed
|
U#2 MDV OPU CW piping routing completed
|
U#3 CW strainer skid positioning in progress
|
U#3 cyclone seperator outlet piping in progress
|
U#3 CW pump motor skid fabrication in progress
|
U#1 MDV and inlet pipe dismantling gap adjustment
|
U#5 Stay ring spiral grouting completed
|
U#4 LGB Sole plates positioning inprogress
|
U#4 Impeller lowering completed
|
U#3 CW outlet header at pump floor routing complet
|
U#3 Air duct covers installation in progress
|
U#2 fire fighting panel to header piping completed
|
U#3 CW strainer skids fabrication in progress
|
U#3 cyclone seperators installation completed
|
U#2 MDV OPU CW piping in progress
|
U#2 GV OPU CW piping inside progress
|
U#2 Cabling inside brush gear casing i/p.
|
U#1 Cabling inside brush gear casing completed
|
U#5 Staircase concreting outside barrel in progre
|
U#4 LGB sole plates cleaning is in progress
|
U#4 Installation of barell door completed
|
U#4 ITC centering completed dowelling in progress
|
U#4 firefighting header outside barell installed
|
U#3 Motor cw pipeline outside barell routing compl
|
U#3 CW Main o/l header at turbine floor welding i/
|
U#3 Pit air seal final assy completed
|
U#3 Pit air seal final assy completed
|
U#2 Firefighting panel positioned piping in progre
|
U#2 Stator sole plates grouting completed
|
U#2 GV MDV OPU positioning completed
|
U#1 Firefighting panel positioning and piping comp
|
U#1 MDV OPU CW piping completed
|
U#1 GV OPU CW piping completed
|
U#6-10 DT gate wall civil works are in progress
|
U#1-5 Surge pool concreting completed upto gantry
|
U#1 DT Gates installed seal assy in progress
|
U#4 Turbine bearing pads blue matching in progress
|
U#4 Fire fighting header outside barell installati
|
U#4 Guide apparatus final assy in progress
|
U#3 LGB Cooler hydraulic testing completed
|
U#3 CW header at turbine floor routing i/p
|
U#3 Barell door installation completed
|
U#3 Stator and LGB piping outside barell completed
|
U#3 UGB CW piping final assembly is in progress
|
U#3 Fire fighting piping inside stator i/p
|
U#2 MDV & GV OPU Positioning completed
|
U#1 Fire fighting control panel positioning i/p
|
U#1 MDV OPU Cooling water piping is in progress
|
U#1 MDV & GV OPU Positioning completed
|
Control room cable tray work is in progress
|
U#4 gv lever fork and fork pin drilling i/p
|
U#4 guide apparatus trial assy in progress
|
U#4 Turbine bearing pad blue matching in progress
|
U#3 Motor floor plate support beamassy in progress
|
U#3 stator cooler to header connection piping i/p
|
U#3 Stator cw piping outside barell routing comple
|
U#3 Fire fighting header outside barell routingi/p
|
U#2 Stator sole plate grouting is in progress
|
U#1 MDV OPU positioning is in progress
|
U#1 Brake dust collector positioning completed
|
U#4 Guide vanes trial assy completed
|
U#3 Installation of stator air coolers i/p
|
U#3 Pit air seal final assy in progress
|
U#3 UGB CW pipeline inside barell routing i/p
|
U#3 Stator CW pipeline inside barell routing compl
|
U#3 Stator CW pipeline outside barell routing i/p
|
U#1 Installation of motor space heaters in progres
|
U#1 Installation of air duct covers in progress
|
Dewatering sump2 header pipeline routing in progre
|
U#4 guide apparatus trial assy in progress
|
U#3 stator air cooler hydraulic testing in progres
|
U#3 pit air seal rings welding in progress
|
U#2 turbine cooling water piping outside barell
|
U#2 cyclone seperators installation completed
|
U#1 MDV inlet pipe welding is in progress
|
U#4 OTC lowering and tightening is in progress
|
U#3 coupling nut guard installation completed
|
U#2 cooling water outlet header at pump floor
|
U#2 cooling water piping routing and welding i/p.
|
U#2 cyclone seperator inlet and outlet piping i/p
|
U#2 bottom fire fighting piping routing is i/p
|
U#2 Bottom air baffle trial assy in progress
|
Dewatering sump-2 pipeline routing in progress
|
Water depression header routing completed upto ASB
|
U#4 OTC quadrants welding is in progress
|
U#2 CW main inlet header routing and welding i/p
|
U#2 cw main outlet header routing, welding complet
|
U#2 cyclone seperators installation in progress
|
U#1 MDV erection completed
|
U#5 Barrel concreting in progress
|
U#4 OTC Quadrants lowering in progress
|
U#2 cw skids shifted to pump floor
|
U#2 bottom air guide trial assy i/p
|
U#2 cw main outlet header routing and welding i/p
|
U#2 CW main inlet header routing and welding i/p
|
U#2 top oil cooler piping routing and welding i/p
|
U#1 MDV inlet and outlet pipe lowering completed
|
U#5 Barrel concreting in progress
|
U#4 pivot ring quadrants assy completed
|
U#3 turbine platform installation completed
|
U#2 bottom air guide trial assy i/p
|
U#2 strainer assy on skid is in progress
|
U#2 cw pump motor skid positioning i/p
|
U#2 cw header at pump floor routing i/p
|
U#1 water and air pipelines welding i/p.
|
U#1&2 busduct installation at ground level
|
U#1 view inside pump pit
|
U#1 MDV inlet pipe edge preparation in progress
|
U#1 topoilvapour pipingoutside barell is completed
|
Com.aux-Water depression main header routing i/p.
|
U#5 Barrel concreting in progress
|
U#5 Barrel concreting in progress
|
U#4 Pivot ring quadrants assy in progress
|
U#3 slip rings assembly on tubular shaft completed
|
U#2 CW pump motor assembly on skid is in progress
|
U#1 CW main inlet header routing in progress
|
U# bottom bracket oil level indicator installed
|
U#1 Top bracket oil level indicator installed
|
U#1 MDV Erection in progress
|
U#1 Top shaft voltage equalizing brush installed
|
U#5 Barrel concreting in progress
|
U#4 Pivot ring face seal assembly is in progress
|
U#3 Turbine platform installation in progress
|
U#3 Pump motor shaft coupling completed
|
U#3 Tubular shaft assembly completed
|
U#2 Turbine platform installation completed
|
U#1 Water depression pipelines outside barell
|
U#1 Water pipelines inside turbine pit routing i/p
|
U#1 Busduct installation at ground level
|
U#1 cable trays fixing outside barell in progress
|
U#5 stator sole plate sleeves positioning complete
|
U#4 Pivot ring quadrants cleaning in progress
|
U#3 Pump motor shaft coupling is in progress
|
U#3 Top bracket lowering completed
|
U#2 Preparation for MDV Testing is in progress
|
U#1 TGB clearance adjustment in progress
|
U#1 LGB Clearance adjustment in progress
|
U#1 Turbine cw pipeline routing in progress
|
U#1 Water pipelines inside turbine pit routing i/p
|
U#5 Busduct installation in progress
|
U#5 Barrel concreting in progress
|
U#4 Stay ring levelling in progress
|
U#3 Top shaft lowered into barell
|
U#3 Rotor lowered into barell
|
U#2 CW skid works in progress
|
U#2 Cable trays positining inside stator barel i/p
|
U#1 Stator sole plates grouting is in progress
|
U#1 LGB CW pipeline routing is in progress
|
U#1 Cable trays positioned inside stator barell
|
U#1 Bottom bearing clearance setting in progress
|
U#1 Top bearing clearance setting in progress
|
U#1 Turbine cw pipeline routing in progress
|
U#1 Water pipelines inside turbine pit routing i/p
|
PRLIS Stage-III Motor Transformers in position
|
PRLIS Stage-III Control room works in progress
|
U#10 DT Ebow liner segments positioning in progres
|
U#9 DT Elbow liner installation completed
|
U#8 DT Elbow liner installation completed
|
U#7 DT Elbow liner installation completed
|
U#5 Busduct installation in progress
|
U#5 Barrel concreting in progress
|
U#4 Turbine shaft cleaning in progress
|
U#3 Turbine platform installation in progress
|
U#1 Water pipelines inside turbine pit routing i/p
|
U#3 UGB Bracket and arms cleaning in progress
|
U#3 HS Pipeline routing and testing completed
|
U#3 HS Skid positioned in turbine floor
|
U#2 Bottom air guide supports assy in progress
|
U#2 Top air baffle assembly completed
|
U#1 LGB cooler trial assy in progress
|
U#1 LGB cooler supports fixing in progress
|
U#1 UGB oil retainer assembly completed
|
U#2 Top air baffle trial assy
|
U#3 Top shaft bearing pad matching in progress
|
U#5 Barrel concreting in progress
|
U#5 Barrel concreting in progress
|
U#4 Grouting of Stay ring in progress
|
U#3 GV Servomotors final assembly alignment comple
|
U#3 guide apparatus final assy in progress
|
U#2 Turbine bearing housing trial assy
|
U#1 cw main outlet header pipeline routing
|
U#1 Turbine cw pipeline routing in progress
|
U#2 Bottom shaft and spring plate assembled in LGB
|
U#2 busduct to stator connection arrangement
|
U#2 stator cooling water outside barrel routing
|
U#2 view from motor floor
|
U#1 view from motor floor
|
U#1 cyclone separator piping routing completed
|
PRLIS Stage-III Pump house view from s/bay
|
U#1 Shaft current monitor installation completed
|
U#5- Bottom bracket sole plate sleeves positioning
|
U#3- Bottom shaft lowered into barrel
|
U#3- Spring plate assy around bottom shaft
|
U#2- Busduct seal off bushing assembly in progress
|
U#2-Stator cooler inlet and outlet connections
|
U#2- Stator cw pipelines outside barrel
|
U#2- Fire fighting top ring assembly completed
|
U#1- CW outlet main header routing & welding
|
U#1- Cyclone separator pipeline welding in progre
|
U#2- Turbine platform installation in progress
|
U#1- Busduct seal off bushing assembly
|
U#5 Barrel concreting in progress
|
U#5 Busduct installation in progress
|
U#4 Busduct installation in progress
|
U#4 Preparation for Pit liner grouting
|
U#3 Bottom shaft cleaning and bearing pads matchin
|
U#3 Rotor poles mounting completed
|
U#2 MDV base plates erection in progress
|
U#2 GV Servomotors after final assy
|
U#2 Brush gear plates installation complete
|
U#2 Stator cooling water pipeline outside barell
|
U#2 Pit air seal installation completed
|
U#1 Turbine platform assy
|
U#1 Motor flooring completed
|
U#1 cyclone separator erection
|
U#1 Turbine platform trial assy in progress
|
U#1Collector to spider connections comlpeted
|
U#1 Rotor DC Connections assy in progress
|
U#1 cooling water skids assembly
|
U#6 Spiral casing pedestal casting
|
U#3 Water and air piping outside barrell
|
U#5 Busduct installation
|
U#5 second stage embedded sleeves installation
|
U#3LGB Bracket and arms assy
|
U#3 LGB Sole plates leveling completed
|
U#2 pit air seal trial assy
|
U#1 Bottom air baffle trial assy
|
U#1 CW Strainer piping routing
|
U#1 GV lever link assy
|
U#1 brush gear support plates installation
|
U#1 Brush gear casing installation completed
|
U#1 Testing of Discharge valve
|
U#5 Second stage embedments installation i/p.
|
U#3 LGB Sole plates levelling is in progress
|
U#2 slip ring alignment is in progress
|
U#2 stator cooling water header routing in progres
|
U#2 Pump motor shaft nutgaurd assy in progress
|
U#1 CW pump motor assy on skid in progress
|
U#1 GV Servomotor final alignment completed
|
U#1 Bottom fire fighting header routing completed
|
U#1 Bottom shaft keys assy completed
|
U#1 Top air guide final assy in progress
|
U#1 MDV Testing preparation in progress
|
U#1 Outlet pipe and test cone welding completed
|
U#9 DT Segments installation in progress
|
U#8 First stage piping in progress
|
U#7 DT Anchor hooks welding completed
|
U#6 spiral casing pedestals casting completed
|
U#5 pit liner installation completed
|
U#3 rotor rim building is in progress
|
U#3 Motor Transformer positioning completed
|
U#2 LGB Cooling water header routing in progress
|
U#1 Bottom Air Guide Trial assy in progress
|
U-6 spiral casing pedestals casting is in progress
|
U-5 concreting is in progress
|
U-5 pit liner segments assy is in progress
|
U-3 Rotor rim building is in progress
|
U-3 GV Servomotor lowering completed
|
Unit-2
|
U#1 Bottom air guide installation is in progress
|
U#1 Brake jack installation completed
|
U#1 cooling water piping outside barell
|
U#9 dt liner segments installation is in progress
|
U#8 first stage piping is in progress
|
U#6 spiral pedestals casting is in progress
|
U#5 spiral casing foam lining is in progress
|
U#3 pump shaft, itc, regulating ring lowering comp
|
U#2 pump motor shaft coupling is completed
|
U#1 GV Servomotor alignment is in progress
|
U#2 Top shaft and bracket assy completed
|
U#1 Top air guide trial assy is in progress
|
U#9 dt liner segments installation is in progress
|
U#7 first stage pipelines routing completed
|
U#6 spiral pedestals casting is in progress
|
U#5 concreting of barell is in progress
|
U#3 impeller and pump shaft coupling is completed
|
U#2 pump motor shaft coupling is in progress
|
U#1 GV SErvomotors shifted inside turbine pit
|
U#9 dt liner segments installation is in progress
|
U#8 dt liner segments installationcompleted
|
U#7 first stage piping is in progress
|
U#6 dt liner concreting is completed
|
U#5 Spiral concreting is in progress
|
U#4 Stator lowering completed
|
U#3 Guide Apparatus assy in progress
|
U#2 Rotor lowering completed
|
U#1 Motor Floor Plate Trial Assy
|
U#8 dt liner segments installationcompleted
|
U#7 dt liner all segments installation completed
|
U#6 dt liner concreting is in progress
|
U#2
|
U#5
|
U#4 Stator sole plates levelling is in progress
|
U#3 ITC Centering and dowelling completed
|
U#1 Top bracket centering and levelling completed
|
U#2 Rotor poles mounting is in progress
|
U#8 dt liner segments installation is in progress
|
U#7 dt liner all segments installation completed
|
U#6 dt liner concreting is in progress
|
U#3 outer top cover tightening is in progress
|
U#2 bottom shaft lowering completed
|
U#1 cooling water pipeline routing is in progress
|
U#1 positioning of ng cubicle completed
|
U#7 dt liner installation is in progress
|
U#6 elbow liner concreting is in progress
|
U#5 second stage pipeline routing u/p.
|
U#4 busduct installation under progress
|
U#3 OTC lowering and bush housing assembly u/p.
|
U#2 LGB bracket lowering completed
|
U#1 shafts alignment completed
|
U#7 installation of dt liner is in progress
|
U#6 dt elbow liner installation completed
|
U#5 lowering of foundation ring is in progress
|
U#3 guide vane trial assy is in progress
|
U#2 lgb spring plate trial assy is in progress
|
U#1 tubular shaft alignment is in progress
|
PRLIS-8 view from main serice bay
|
U#1 Motor transformer shifting completed
|
U#4 busduct installation under progress
|
U#5 cleaning of foundation ring for assembly
|
U#2 lgb arms assembly completed
|
U#4 barrell concreting completed, cleaning in prog
|
U#3 otc levelling after welding is in progress
|
U#2 rotor rim building is in progress
|
U#2 rotor rim building is in progress
|
U#5 spiral casing hydraulic testing completed
|
U#4 barrell concreting under progress
|
U#3 guide vane height measurement in progress
|
U#2 Inner top cover, bearing housing lowered
|
U#1 top bracket lowered, tubular shaft assembled
|
U#5 spiral segments welding in progress
|
U#4 busduct installation under progress
|
U#4 barrell concreting under progress
|
U#3 otc quadrants assy completed welding isin prog
|
U#2 impeller and pump shaft lowering completed
|
U#1 pump motor shaft coupling is in progress
|
U#1 Water and airpipelines routing is in progress
|
U#3 pivot ring and top cover quadrants assembly
|
U#5 spiral segments welding in progress
|
U#1 Motor Rotor and Top Shaft after lowering
|
U#1 Rotor Lowering into barrel
|
U#5 spiral segments welding in progress
|
U#2 inner top cover centering
|
U#4 barrell concreting under progress
|
U#1 Bottom Bracket arms assembly
|
U#1 Complete Rotor
|
U#4 barrell concreting under progress
|
U#3 busduct installation under progress
|
U#2 Guide apparatus assy in progress
|
U#4 stator bar laying under progress
|
U#5 spiral segments erection under progress
|
U#1 regulating ring lowered
|
U#1 Rotor poles assembly
|
U#5 spiral segments erection under progress
|
U#2 Guide apparatus assy in progress
|
U#3 Stator lowering completed
|
U#1 Runner Lowering completed
|
U#4 Pit liner installation completed
|
U#2 Stator Lowering completed
|
U#1 Busduct erection in progress
|
U#1 Guide Apparatus erection in progress
|
U#2 stator joints brazing completed
|
U#2 Bus duct erection in progress
|
U#1 Rotor Rim building in progress
|
U#1 Stator Lowering completed
|
U#1 Stator Lowering into Motor Barrell
|
U#1 Busduct erection under progress
|
U#1 Positioning of stator sole plates in progress
|
U#4 Pitliner halves welding completed
|
U#5 Draft tube lowering completed
|
U#2 Stator Sole plate sleeves installation
|
U#1 Bus Duct erection started
|
U#4 welding of foundation ring in progress
|
U#3 Barrel Concreting in Progress
|
U#2 Barrel Concreting in Progress
|
U-1 Generator Barrel Readiness
|
Pump House View
|
U#1 Positioning of BusDuct Support Strucutures
|
Assembly of Stator Lifting Frame is in progress
|
Unit 6-10 Civil Work under progress
|
Unit-5 Concreting of Stay Ring Pedestals completed
|
Unit-4 Erection of Foundation Ring completed.
|
Unit-3 Turbine Pit Liner concreting under progress
|
Unit-2 Postioning of Stator Sole Plate Sleeves.
|
Unit-1 Motor Barrell concreting completed.
|
PRLIS Stage-3: View of from Main Service Bay
|
Unit-6 to 10- 1st stage embedment erection in progress
|
Unit-5 Spiral casing pedestal casting
|
Unit-4 Foundation ring assy in progress
|
Unit-3 Generator barrel concreting in progress
|
Unit-2 Stator assy in progress
|
Unit-2 Generator barrel concreting in progress
|
Unit-1 Generator barrel concreting in progress
|