U#4 Impeller nut guard installation
|
U#4 Turbine CW pipeline routing
|
U#3 MDV pipelines routing from PP set to HCP
|
U#3 UGB oil filling completed
|
U#2 MDV Maintenance seal and body drain piping
|
Second set of compressor additional service bay
|
U#4 Pit air seal installation in progress
|
U#3 Top vapor seal installation
|
Compressors installation in additional servicebay
|
U#4 WDS pipeline routing in progress
|
U#3 Brake dust collector installation in progress
|
U#4 MDV cleaning in progres
|
U#4 Motor floor plates installation in progress
|
U#4 Water depression pipeline routing in progress
|
U#3 Water and air pipelines in pit welding in prog
|
U#3 oil manifold pipeline routing in progress
|
U#2 Discharge valve pipelines routing in progress
|
U#2 MDV Servomotor Secondary concreting completed
|
U#1 Discharge valve pipelines routing completed
|
U#4 CW pipeline routing in progress
|
U#3 Water and air pipelines inside turbine pit routing i/p
|
U#3 oil manifold pipeline routing
|
U#3 Impeller band drain valve
|
U#3 Top air baffle installation in progress
|
U#5 Rotor rim building in progress
|
U#3 Turbine CW pipeline routing in progress
|
U#3 Water depression pipeline routing in progress
|
U#2 MDV Servomotor alignment completed
|
U#8 stayring joint welding is completed
|
U#7 stay ring joint welding in progress
|
U#5 Rotor rim building in progress
|
U#2 Bypass valve pipeline assy completed
|
U#3 Turbine CW pipeline welding in progress
|
U#3 GV OPU CW pipeline routing in progress
|
U#1 MDV Servomotor alignment completed
|
U#8 stayring welding in progress
|
U#7 stay ring levelling and alignment in progress
|
U#3 turbine cw pipeline routing in progress
|
U#1 MDV Servomotor alignment in progress
|
U#8 Stay ring halves joining completed
|
U#4 GV MDV Pressure receivers positioning in progr
|
U#2 bypass valve 300nb pipeline routing completed
|
U-4 unit axis alignment in progress
|
U-6 spiral segments positioning in progress
|
U-3 pgb installation in progress
|
U-7 stay ring halves assy in progress
|
D&D sump-1 pump pedestals casting
|
U#6 stay ring welding
|
U#4 rotor poles installation
|
U#2 MDV Push pull bolt rework
|
U#5 Spring plate assy around bottom shaft
|
U#5 DT Elbow liner grouting
|
U#2 MDV outlet pipe and penstock welding in progre
|
U#1 OPU oil filling done for oil flushing
|
400NB Dewatering header pipeline routing
|
U#6 Stay ring halves levelling and joint tightenin
|
U#3 Top air guide trial assembly
|
U#2 Transformer oil leakage rectification works
|
U#2 MDV servomotor lowered to position
|
U#1 MDV rework in prorgess
|
U#1 auxiliary panel cable termination
|
Station transformer ready for charging
|
Station air and WDS System in main service bay
|
U#6 Stay ring halves assembly in progress
|
U#5 LGB bearing pads blue matching completed
|
U#2 MDV installation in prgoress
|
U#1 UAB and starter panels cabling
|
U#1 Auxiliaries cabling in progress
|
U#1 Auxiliaries cabling
|
U#1 Excitation Transformer
|
U#1 MDV Servomotor positioning
|
U#1 Bypass valve pipeline routing
|
24V DC Battery Bank
|
220V UPS System Battery Bank
|
U#1 Gauge panel control wiring
|
U#1 Breaker panels
|
U#1 CW Strainer and sand seperator panels
|
U#1 Busduct CT Wiring
|
U#1 cable laying and termination
|
U#1 Discharge valve pipelines routing in progress
|
Station and WDS Compressors
|
U#1 Field efficiency pipeline routing
|
U#1 DT Water level indicator installed
|
U#1 GV Servo opening closing pipelines routing
|
U#1 CW Main outlet NRV installed
|
U#1 Bypass valve piping works i/p
|
U#1 Cable laying works
|
U#1 UAB Panels positioned
|
U#1 to 5 HP Common header pipeline routing i/p
|
Station air compressors and receivers erection
|
U#2 LGB CW pipeline final assembly
|
U#1 LP Air connections pipeline routing
|
U#1 10NB water pipelines routing
|
U#1 Brake dust collector piping
|
U#1 MDV Outlet pipe penstock welding
|
U#2 DT Drain valves installation in progress
|
U#1 Spiral drain valve installation completed
|
U#1 Ejector pipeline routing completed
|
U#1 DT Drain Valves installation completed
|
U#1 Water air pipelines inside turbine pit
|
U#6 Water Depression air receiver positioned
|
Compressed air pipeline routing in progress
|
HP & LP receivers positioning
|
U#1 Discharge valve pipelines routing in progress
|
U#1 Motor barell door installed
|
U#1 PGB CW O/L pipeline routing
|
U#1 Brake dust collector hopper assembly i/p
|
Installation & algnment of ACEB panels completed
|
U#4,5 WDS air receivers positioning in progress
|
U#3 air guides installation in progress
|
U#2 LGB oil coolers assembly completed
|
U#1 WDS pipeline routing completed
|
U#4 cyclone seperator erection is completed
|
U#3 CWS cyclone seperator and main header piping
|
U#2 10nb pipelines for servo valve routing in prog
|
U#2 Band drain pipeline routing is completed
|
U#2 Top brg and vapour seal assy is completed
|
U#1 water depression pipeline routing is in progre
|
U#1 DTT routing from brg to panel is in progress
|
U#1 Brush gear casing installation is completed
|
U#1 LGB Cooler piping assy is completed
|
U#5 bottom bracket lowering completed
|
U#2 oil manifold pipeline routing in progress
|
U#2 motor transformer dry out completed
|
U#1 band drain pipeline routing is completed
|
U#1 oil manifold pipeline routing is completed
|
U#2 Top bearing instrumentation work
in progress
|
U#1 Water air pipelines routing in progress
|
U#1 Bottom vapour seal assy completed
|
U#1 Bottom oil coolers assy in progress
|
U#1 Top oil coolers assy completed
|
U#1 Top vapour seal assy completed
|
Dewatering sump-2 pipeline routing in progress
|
SFC Transformer hot oil circulation completed
|
U#2 10nb pipelines for servo valve routing in prog
|
U#2 MDV pushpull bolt,spacerflange bush replaced
|
U#2 Motor transformer
|
U#1 Turbine GB Housing assembly in progress
|
U#1 Motor transformer
|
U#4 Rotor rim building is in progress
|
U#2 LGB Bearing final assy in progress
|
U#1 MDV O/L pipe matching with penstock completed
|
U#1 TGB Housing assy
|
U#4 Rotor rim building is in progress
|
U#4 brake jacks assy in progress
|
U#3 top air guide assy in progress
|
U#1 oil pipelines routing in progress
|
U#2 top bearing pads assy completed
|
U#1 Turbine bearing housing assy i/p
|
U#1 Servo operated valves pipeline routing i/p
|
SFC output transformer pressure test carried
|
SFC input transformer oil filling completed
|
U#5 Stator CW pipelines
|
U#4 Rotor rim building in progress
|
U#3 Top air guide installation in progress
|
U#2 LGB assembly in progress
|
U#1 LGB instrumentation in progress
|
U#2 Transformer ready for oil filling
|
U#1 Transformer ready for oil filling
|
D&D sump-2 autocoupling pedestals erection in prog
|
U#4 CWS pump to strainer piping in progress
|
U#3 Cws pipeline works in progress
|
U#2 turbine bearing sump assy in progress
|
SFC Transformer erection is in progress
|
U#4 CWS Strainer skid lowering to turbine floor
|
U#3 CWS cyclone seperator and main header piping
|
U#3 busduct installation at ground level
|
U#1 Busduct installation at ground level
|
U#1 Transformer erection is completed
|
U#1 shaft seal testing is completed
|
U#2 shaft seal testing is completed
|
Panels installation is in progress
|
Panels installation is in progress
|
Panels installation is in progress
|
U#4 CW Strainer skid works are in progress
|
U#4 CW pump motor skid works are in progress
|
U#3 CW system pipeline works are in progress
|
U#3 cyclone seperators installation in progress
|
U#2 shaft seal installation is completed
|
U#2 transformer bushings installation is complete
|
U#1 transformers bushing installation completed
|
U#1 shaft seal installation is completed
|
U#5 View inside turbine pit
|
U#4 Stator CW pipeline outside barell completed
|
U#4 Stator CW pipeline inside barell routing i/p
|
U#4 CW system works in progress
|
U#3 Cooling water system works in progress
|
U#1 water depression pipeline routing is in progre
|
U#1 shaft seal installation in progress
|
U#3 CW pump motor assembly works are in progress
|
U#2 nutguard assembly and welding completed
|
U#1 water depression pipeline routing is in progre
|
U#2 Cyclone seperator pipeline routing and welding
|
U#1 nutguard assembly and welding completed
|
U#5 Installation of Pump platform is completed
|
U#2 Water depression pipeline routing in progress
|
U#5 GV servomotor alignment completed
|
U#2 CW main header near DT routing completed
|
U#1 CW main headers near dt routing completed
|
Water depression receivers positioning in progress
|
U#5 Guide apparatus assembly is in progress
|
U#1 mdv inlet and outlet pipe fitup in progress
|
U#4 Motor CW pipeline outside barell routing i/p
|
U#5 Water and air pipelines outside barell routing
|
U#5 Guide apparatus assembly is in progress
|
U#2 MDV inlet pipe welding is completed
|
U#2 Top oil vapour pipeline routing is completed
|
U#1 Cable routing works are in progress
|
U#1 Starter panels positioning in progress
|
UNIT 1-2 POSITIONING OF PRESSURE RECEIVERS IN PROG
|
UNIT1-2 POSITIONING OF FIRE FIGHTING PANEL COMPD
|
UNIT-3 SAC PIPE LINE WORK IN PROGRESS
|
UNIT-5 FLOOR PLATE SUPPORT FIXING IN PROGRESS.
|
UNIT-2 DC LEAD WOK IN PROGRESS
|
UNIT-3 ALIGHNMENT OF TUBULAR SHAFT AND SLIP RINGS COMPD
|
UNIT-1 TOP BOTTOM VAPOUR PIPING COMPLETED
|
WATAER DEPRESSION PIPE LINE HAEDER AT DV FLOOR
|
UNIT 1 & 2 PP SET CW PIPING WORK IN PROGRESS
|
UNIT-3 POSITIONING OF pp SETS COMPLETED
|
UNIT-5 INSPECTION AND CLEANING OF GUIDE VANES
|
UNIT-4 STATOR AND LOWER BRACKET
|
UNIT-2 CW LINES FOR TOP BOTTOM LABYRINTH
|
UNIT-4 INSTALLATION OF GUIDE APPARATUS COMPLETED
|
UNIT-3 COMBINED ALIGNMENT OF UNIT COMPLETED
|
UNIT-5 WELDING OF OTC IN PROGRESS
|
UNIT-4 GUIDE APPARATUS WORK IN PROGRESS
|
UNIT 1 -2 PRESSURE RECIEVERS POSITIONING IN PROGRS
|
UNIT1-10 WATER SYSTEM HEADER WORK IN PROGRESS
|
UNIT-2 STATOR AND ROTOR
|
UNIT-1 POSITIONING OF PP SETS COMPLETED
|
UNIT-2 LABYRINTH COOLING WATER PIPE LINES
|
UNIT-2 COOLING WATER SYSTEM LINES
|
UNIT-2 COOLIN WATER SYSTEM LINES
|
UNIT-1 COOLING WATER SYSTEM
|
SURGE POOL VIEW FROM TOP
|
UNIT-3 THRUST BEARING ASSEMBLY
|
UNIT-1 TOP,BOTTOM LABYRINTH COOLING WATER LINES
|
UNIT-5 PIVOT RING SEGMENTS
|
UNIT-1 TOP VAPOUR SEAL ASSEMBLY
|
UNIT-5 STATOR HAS BEEN LOWERED ON ITS SOLE PLATES
|
UNIT-3 ROTOR HAS BEEN LOWERED.
|
UNIT-3 LOWERING OF BOTTOM SHAFT
|
UNIT-6 DT CONE LOWERED
|
UNIT-4 IMPELLER/SHAFT LOWERING I
|
BUS DUCT WORK UNIT 3 TO 5 IN PROGRESS
|
CONTROL ROOM BUILDING
|
CONTROL ROOM -LAYING OF CABLE TRAYS IN PROGRESS
|
UNIT-5 GOUTING OF SPIRAL CASING COMPLETED
|
UNIT-7 CONCRETING OF DT LINER COMPLETED.
|
UNI-5 STAOR IS READY FOR LOWERING.
|
UNIT-4 REGULATING RING
|
UNIT-4 INSTALLATION OF GUIDE APPARATUS IN PROGRESS
|
UNIT-2 COOLING WATER PIPE LINE WORK IN PROGRESS
|
UNIT-1 COOLING WATER SYSTEM WORK IN PROGRESS
|
UNIT-1 AND 2 CARBON DUST COLLECTOR
|
UNIT-3 INSTALLATION OF PUMP PIT PLATFORM COMPTD
|
UNIT-2 BOTTOM AIR GUIDE ASSLY COMPLETED.
|
MOTOR FLOOR VIEW
|
UNIT-2 SHAFT CURRENT MONITORING CT
|
UNIT-1 WATER DEPRESSION SYSTEM WORK IN PROGRESS.
|
UNIT-1 WATER AND AIR PIPING WORK IN PROGRESS.
|
UNIT-4 INSTALLATION OF GUIDE APPARATUS IN PROGRESS
|
UNIT-5 BAZING OF STATOR BAR JOINTS COMPD
|
UNIT-5 BARREL CONCRETING IN PROGRESS
|
UNIT-1 ERECTION OF CW SYSTEM IN PROGRESS
|
UNIT-1 ERECTION OF COOLING WATER SYSTEM
|
UNIT1,2,3- BUS DUCT ERECTION IN PROGRESS
|
PANELS ERECTION IN PROGRESS IN CONTROL ROOM
|
UNIT-2 LGB COOLER PIPING WORK IN PROGRESS
|
UNIT-3 INSTALLATION OF PUMP PIT PLATFORM COMP
|
MOTOR FLOOR VIEW
|
UNIT-5 LAYING OF STATOR TOP AND BOTTOM BARS COMPTD
|
UNIT-4 GUIDE APPARATUS WORK IN PROGRESS
|
UNIT-2 BOTTOM AIR GUIDE ASSLY COMPLETED.
|
UNIT-2 INSTALLATION OF PIT AIR SEAL COMPTD
|
UNIT-3 STATOR COOLER PIPING WORK IN PROGRESS
|
UNIT-1 COOLING WATER SYSTEM PIPING WORK IN PROGR
|
UNIT-5 BARREL CONCRETING IN PROGRESS
|
UNIT-1 BUS DUCT( MOTOR FLOOR TO VERTICAL SHAFT)
|
UNIT-10 INSTALLATION OF DRAFT TUBE LINER COMPLETED
|
UNIT-6 STAY RING AND SPIRAL PEDESTALS
|
UNIT-4 STATOR LOWERING
|
UNIT-3 STATOR ON ITS SOLE PLATES
|
UNIT-1 BUS DUCT
|
UNIT-3 ROTOR IS READY FOR LOWERING
|
UNIT-2 LGB COOLER SUPPORT FIXING IN PROGRESS
|
UNIT-5 BUS DUCT
|
UNI-5 BARREL CONCRETING IN PROGRESS
|
UNIT-4 CENTERING OF STATOR COMPLETED
|
UNIT-4 ASSEMBLY OF PIVOT RING SEGMENTS IN PROGRESS
|
UNIT-3 ASSEMBLY OF GUIDE APPARATUS
|
UNIT-1 & 2 BUS DUCT ERECTION IN PROGRESS
|
MOTOR FLOOR VIEW
|
UNIT-3 ROTOR IS READY FOR LOWERING
|
UNIT-2 DISCHARGE VALVE AND OUTLET PIPE
|
UNIT-4 CLEANING AND PAINTING OF PUMP PIT
|
UNIT-4 LOWERING OF STATOR
|
MOTOR FLOOR VIEW
|
UNIT-5 BARREL CONCRETING IN PROGRESS
|
UNIT-2 TOP AIR GUIDE AND BAFFLES ASSEMBLY COMD
|
UNIT-2 PUMP PIT PLATFORM COMPLETED
|
UNIT-4 STATOR LOWERING
|
UNIT-5 INSTALLATION OF BUS DUCT IN PROGRESS
|
UNIT-10 INSTALLATION OF DRAFT TUBELINER COMPLETED
|
UNIT-7 INSTALLATION OF DRAFT TUBE LINER COMPLETED
|
UNIT-6 DRAFT TUBE CONCRETING COMPLETED
|
CONTROL ROOM BUILDING
|
MOTOR FLOOR VIEW
|
UNIT-2 HYDRAULIC TESTING OF DISCHARGE VALVE COMPD
|
UNIT-3 ROTOR FAN MOUNTING IN PROGRESS
|
UNIT-5 BARREL CONCRETING IN PROGRESS
|
UNIT-4 BARREL CONCRETING COMPLETED
|
UNIT-3 GUIDE APPARATUS
|
UNIT-2 FLOOR PLATES SUPPORTS
|
UNIT-2 COMPLITION OF GUIDE APPARATUS SYSTEM
|
UNIT-1 SHAFT CURRENT MONIT0RING SYSTEM
|
UNIT-1 PUMP PIT PLATFORM
|
U-3 STATOR
|
U-2 NUT GUARD ASSEMBLY IN PROGRESS
|
U-3 ROTOR RIM RADIUS CORRECTION IN PROGRESS
|
U-5 POSITIONING OF PIT LINER SLEEVES IN PROGRESS
|
U-4 BARREL CLEANING IN PROGRESS
|
U-3 gV LINK LEVELLING IN PROGRESS
|
U-2 FLOOR PLATES SUPPORT FIXING IN PROGRESS
|
U-1 TOP AIRGUIDE AND BAFFLES
|
motor floor view
|
MOTOR FLOOR VIEW
|
UNIT-1 HYDRAULIC TESTING OF DISCHARGE VALVE
|
UNIT-1 PUMP PIT PLATFORM
|
UNIT-5 CONCRETING OF SPIRAL IN PROGRESS
|
UNIT-4 BARRELL CONCRETING COMPLETED
|
UNIT-3 ALIGNMENT OF SERVO MOTORS COMPLETED
|
UNIT-2 UNIT ALIGNMENT COMPLETED
|
uni-3 rotor rim building completed
|
unit-4 bus duct
|
unit-1 trial assbly of pump pit platform comltd
|
unit-6 concreting of draft tube completed by cstmr
|
unit-3 alignment of GV servomotors in progress
|
motor floor view
|
unit-5 GV mounting plate positioning in progress
|
unit-3 centering and levelling of stator completed
|
unit-1 stator and ugb cooling line
|
unit-4 barrel concreting in final stage
|
unit-2 alignment of gv servo motors completed
|
unit-4 brazing of stator bar joints in progress
|
unit-2 alignment of unit is under progress
|
unit-3 rotor rim building in progress
|
unit-2 rotor has been lowered
|
UNIT-2 HV TEST ON ROTORS POLES COMPLETED
|
UNIT1-3 WATER AND AIR PIPE LINES WORKS IN PROGRESS
|
UNIT-4 STATOR TOP BARS LAYING IN PROGRESS
|
UNIT-4 BARREL CONCRETING IN PROGRESS
|
UNIT-2 THRUST BEARING ASSLY
|
UNIT-3 STATOR AND LGB BRACKET
|
UNIT-5 LOWERING OF BOTTOM SHAFT /THRUST BEARING
|
UNIT-3 ASSEMBLY OF GUIDE APPARATUS IN PROGRESS
|
UNIT-2 ALINGMENT OF gv SERVO MOTORS IN PROGRESS
|
UNIT-1 ALIGNMENT OF SERVO MOTORS COMPLETED
|
UNIT-5
|
UNIT-4 CONCRETING OF BARREL IN PROGRESS
|
UNIT-1 TRIAL ASSEMBLY OF STATOR COOLERS
|
UNIT-3 IMPELLER
|
UNIT-2 POLES MOUNTING COMPLETED
|
UNIT1 ASSEMBLY OF GUIDE APPARATUS IN PROGRESS
|
UNIT-1 BOXUP OF UNIT IS UNDER PROGRESS
|
UNIT-4 BUS DUCT ERECTION IN PROGRESS
|
UNIT-1 ROTOR RIM BUILDING IN PROGRESS
|
MOTOR FLOOR VIEW
|
UNIT -2 BOTTOM BRACKET
|
SPIRAL AND PIT LINER
|
UNIT-4 CONCRETING OF BARREL IN PROGRESS
|
UNIT-3 DOWELLING OF ITC AND OTC
|
UNIT--2 NO WORK DUE TO MATERIAL NOT RECIEVED
|
UNIT-1 ALIGNMENT OF UNIT IN PROGRESS
|
UNISTATOR BAR TO BAR JOINT BRAZING COMPLETEDT-3
|
UNIT-2
|
UNIT-3 ASSEMBLY OF SEAL RETAINERS AND FACE SEALS
|
UNIT-4 BARRELL CONCRETING IS UNDER PROGRESS
|
UNIT-5 UNIT RELEASED FOR CONCRETING
|
UNIT -1 ROTOR LOWERING
|
UNIT-2 STATOR HAS BEEN LOWERED ON SOLE PLATES.
|
UNIT-1 GUIDE APPARATUS WORK IS IN PROGRESS
|
UNIT-5 INSTALLATION OF PIT LINER COMPLETED
|
UNIT-4 BARRELL CONCRETING IN PROGRESS
|
UNIT-3 CENTERING AND LEVELLING OF PIVOT RING/OTC
|
UNIT-1 LOWERING OF BOTTOM SHAFT/ THRUST BEARING
|
UNIT-2 LOWERING OF TOP ITC COMPLETED
|
UNIT-1 LOWERING OF STATOR COMPLETED
|
UNIT-3 JOINING OF STATOR SEGMENTS
|
BUS DUCT UNIT 1,2 AND 3
|
MOTOR FLOOR VIEW
|
UNIT-1 ROTOR
|
UNIT-5 PREPARATION FOR PIT LINER LOWERING
|
UNIT-4 CONCRETING OF MOTOR BARREL IN PROGRESS
|
UNIT-3 PREPARATION FOR PIVOT RING LOWERING
|
UNIT-2 FIXING OF SEAL RETAINERS AND SEALS
|
UNIT-1 impeller with shaft lowered in pit
|
CONTROL ROOM BUILDING
|
SWITCHYARD AREA
|
DELIVERY LINES( PENSTOCK) UNIT 1 TO 5
|
UNIT-3 BUS DUCT ERECTION IN PROGRESS
|
UNIT-5 WELDING OF DT CONE AND FOUNDATION RING I
|
UNIT-4 CONCRETING OF MOTOR BARREL IN PROGRESS
|
UNIT-3 CONCRETING OF BARREL COMPLETED
|
UNIT-1 FINAL VH OF ROTOR POLES COMPLETED
|
UNIT-2 LOWERING OF OTC QUADRANTS IN PROGRESS
|
UNIT-1 ASSEMBLY OF GUIDE APPARATUS IN PROGRESS
|
UNIT-1 ERECTION BUS DUCT IN PROGRESS
|
UNIT-5 ERECTION OF FOUNDATION RING IN PROGRESS
|
UNIT-4 CONCRETING OF BARREL IN PROGRESS
|
UNIT-3 CONCRETING OF BARREL IS UNDER PROGRESS
|
UNIT-2 LOWERING OF PIVOT RING QUADRANTS
|
UNIT-1SOLDERING OF ROTOR POLE CONNECTION
|
UNIT-1 POSITIONING OF GUIDE VANES
|
CONTROL ROOM
|
UNIT1 AND 2 ERECTION OF BUS DUCT IN PROGRESS
|
VIEW OF MOTOR FLOOR UNIT- 1 TO10
|
VIEW OF UNIT 6-10
|
UNIT-6 ERECTION OF DRAFT TUBE IN PROGRESS
|
UNIT-5 POSITIONING OF FOUNDATION RING
|
UNIT-4 CONCRETING OF BARREL IN PROGRESS
|
UNIT-3 POSITIONING OF STATOR SLE PLATE SLEEVES COMPLETED
|
UNIT-2 GROUTING OF STAY RING AREA COMPLETED
|
UNIT-1 POSITIONING OF PIVOT RING COMPLETED
|
UNIT-1 TIGHTEING OF POLE KEYS IN PROGRESS
|
UNIT-5 LEVEL CHECK OF STAY RING AFTER HYDRO TEST
|
MOTOR FLOOR
|
UNIT-5 HYDRAULIC TESTING OF SPIRAL CASING
|
UNIT-4 CONCRETING OF BARREL IS UNDER PROGRESS
|
UNIT-3 CONCRETING OF BARREL IS UNDER PROGRESS
|
UNIT-2 BARREL CASTING COMPLETED
|
UNIT-1 MOUNTIN OF POLE
|
UNIT-1 WELDING OF OTC SEGMENTS IN PROGRESS
|
UNIT-1 MOUNTING OF ROTOR POLES IN PROGRESS
|
UNIT-5 WELDING OF SPIRAL SEG AND MAKE-UP PIECES
|
UNIT-4 CONCRETING OF PIT LINER IN PROGRESS
|
UNIT-3 CONCRETING OF BARREL IS UNDER PROGRESS
|
UNIT-2 MOTOR BARREL CONCRETING IN PROGRESS
|
UNIT-1 LOWERING OF PIVOT RING SEGMENTS
|
Unit- cleaning of pump pit in progress
|
Unit-1 measurement of rotor rim dia in progress
|
Unit-5 erection of spiral make-up pieces
|
Unit-4 concreting of pit liner in progress
|
Unit-3 concreting of barrel is under progress
|
Unit-2 positioning of stator sole plate sleeves
|
Unit-1 top view
|
Unit-1 stator has been lowered on its sole plates
|
Unit-2 bus duct erection in progress
|
Unit-1 torque tightening of rotor rims completed
|
Unit-5 erection of spiral make-up pieces
|
Unit-4 concreting of pit liner in progress
|
Unit-3 concreting of barrel is under progress
|
Unit-2 bus duct erection in progress
|
Unit-1 finishing of motor barrel in progress
|
Unit-1 tightening of rotor rims in progress
|
Unit-5 welding of spiral segments in progress
|
Unit-4 concreting of pit liner in progress
|
Unit-3 positioning of LGB sloe plate sleeves
|
Unit-2 motor barrel concreting in progress
|
Unit-1 cleaning of barrel in progress
|
Unit-5 Welding of spiral segments in progress
|
Unit-3 LGB Sloe plate cut out
|
Unit-2 Stator Sole Plate and air duct cut out
|
Unit-1 Grouting of spiral and foundation ring
|
Unit-1 Rotor rim building completed
|
Unit-5 erection of spiral segments in progress
|
Unit-4 concreting of pit liner in progress
|
Unit-3 motor barrel concreting in progress
|
Unit-2 motor barrel concreting in progress
|
Unit-1 cleaning of motor barrel in progress
|
Unit-1 erection bus duct in progress
|
Unit-1 rotor rim building completed
|
Unit-1 rotor rim building in progress.
|
Unit-5 erection of spiral segments
|
Unit-4 concreting of pit liner in progress
|
Unit-3 LGB sloe plate cut out
|
Unit-2 motor barrel concreting in progress
|
Unit-1 positioning of stator sole plates
|
Unit-1 positioning of stator sole plates
|
Unit-1 Erection bus duct in progress.
|
Unit-5 erection of spiral segments
|
Unit-5 erection of spiral segments
|
Unit-1 rotor rim building in progress
|
Unit-4 concreting of pit liner in progress
|
Unit -3 Laying of barrel reinforcement RODS
|
Unit-2 motor barrel concreting in progress
|
Unit-1 finishing of motor barrel /pump in progress
|
Unit-1 second pressing of rotor rim building
|
Unit-5 erection of spiral segments
|
Unit-4 concreting of spiral casing in progress
|
Unit-2 laying of reinforcement rods in progress
|
Unit-3 motor barrel concreting in progress
|
Unit-1 finishing of motor barrel in progress
|
Unit-1 rotor rim building in progress.
|
Unit-5 alignment of spiral partition plate seg.
|
Unit-4 concreting up to pump centre completed
|
Unit-3 LGB sloe plate cut out
|
Unit-2 motor barrel concreting in progress
|
Unit-1 finishing of motor barrel in progress
|
Unit-1 first pressing of rotor rim building
|
Unit-5 erection of spiral segments
|
Unit-4 concreting up to Pump Centre completed
|
Unit-2 LGB sloe plate cut out
|
Unit-3 Motor barrel concreting in progress
|
Unit-1 motor barrel concreting completed
|
Unit-1 erection bus duct in progress
|
Unit-5 erection of spiral segments
|
Unit-4 positioning of 2nd stage pit liner sleeves
|
Unit-3 positioning of LGB sole plate cut out frame
|
Unit-2 motor barrel concreting in progress
|
Unit-1 concreting of motor barrel completed
|
Unit-5 elevation and centre stay ring
|
Unit-4 positioning of 2nd stage pit liner sleeves
|
Unit-3 motor barrel concreting in progress
|
Unit-2 motor barrel concreting in progress
|
Unit-1 concreting of motor barrel completed
|
Unit-5 welding of stay ring joints in progress
|
Unit-4 positioning of 2nd stage pit liner sleeves
|
Unit-3 LGB sloe plate cut out
|
Unit-2 positioning of LGB sole plate sleeves
|
Unit-1 concreting of motor barrel in progress
|
U#4 Pit liner and Spiral Casing
|
U#3 Barrel Concreting in Progress
|
U#2 Barrel Concreting in Progress
|
UNIT-1 ERECTION OF BUS DUCT IN PROGRESS.
|
Unit-5 welding of Stay Ring Joints in progress
|
Unit-4 Concreting of spiral casing in progress
|
Unit-3 Pit liner concreting in progress
|
Unit-2 Motor Barrel Concreting in progress
|
Unit-1 Concreating of Motor Barrel in progress
|
U-1 Rotor Rim Building
|
U-1 Generator Barrel
|
U1 Generator Barrel
|
Unit-1 motor stator ready for erection
|
Unit-1 preparation for rotor rim building in progress
|
Unit-5 Full Welding of Stay ring joints in progress
|
Unit-4 concreting up to Pump center completed
|
Unit-3 completion of second stage embeddments
|
Unit-2 Motor Barrel Concreting in progress
|
Unit-1 Motor Barrel Concreting in progress
|
Unit-6 to 10- 1st stage embedment erection in prog
|
Unit-5 stay ring leveling & centering in progress
|
Unit-4 pit liner and spiral casing
|
Unit-3 Generator barrel concreting in progress
|
Unit-2 Generator barrel concreting in progress
|
Unit- 6 to 10- Erection of 1st stage embedment in progress
|
Unit-1 Generator barrel concreting in progress
|