Home   

PRLIS Stg-2 Pkg-5


U#4 Impeller nut guard installation

U#4 Turbine CW pipeline routing

U#3 MDV pipelines routing from PP set to HCP

U#3 UGB oil filling completed

U#2 MDV Maintenance seal and body drain piping

Second set of compressor additional service bay

U#4 Pit air seal installation in progress

U#3 Top vapor seal installation

Compressors installation in additional servicebay

U#4 WDS pipeline routing in progress

U#3 Brake dust collector installation in progress

U#4 MDV cleaning in progres

U#4 Motor floor plates installation in progress

U#4 Water depression pipeline routing in progress

U#3 Water and air pipelines in pit welding in prog

U#3 oil manifold pipeline routing in progress

U#2 Discharge valve pipelines routing in progress

U#2 MDV Servomotor Secondary concreting completed

U#1 Discharge valve pipelines routing completed

U#4 CW pipeline routing in progress

U#3 Water and air pipelines inside turbine pit routing i/p

U#3 oil manifold pipeline routing

U#3 Impeller band drain valve

U#3 Top air baffle installation in progress

U#5 Rotor rim building in progress

U#3 Turbine CW pipeline routing in progress

U#3 Water depression pipeline routing in progress

U#2 MDV Servomotor alignment completed

U#8 stayring joint welding is completed

U#7 stay ring joint welding in progress

U#5 Rotor rim building in progress

U#2 Bypass valve pipeline assy completed

U#3 Turbine CW pipeline welding in progress

U#3 GV OPU CW pipeline routing in progress

U#1 MDV Servomotor alignment completed

U#8 stayring welding in progress

U#7 stay ring levelling and alignment in progress

U#3 turbine cw pipeline routing in progress

U#1 MDV Servomotor alignment in progress

U#8 Stay ring halves joining completed

U#4 GV MDV Pressure receivers positioning in progr

U#2 bypass valve 300nb pipeline routing completed

U-4 unit axis alignment in progress

U-6 spiral segments positioning in progress

U-3 pgb installation in progress

U-7 stay ring halves assy in progress

D&D sump-1 pump pedestals casting

U#6 stay ring welding

U#4 rotor poles installation

U#2 MDV Push pull bolt rework

U#5 Spring plate assy around bottom shaft

U#5 DT Elbow liner grouting

U#2 MDV outlet pipe and penstock welding in progre

U#1 OPU oil filling done for oil flushing

400NB Dewatering header pipeline routing

U#6 Stay ring halves levelling and joint tightenin

U#3 Top air guide trial assembly

U#2 Transformer oil leakage rectification works

U#2 MDV servomotor lowered to position

U#1 MDV rework in prorgess

U#1 auxiliary panel cable termination

Station transformer ready for charging

Station air and WDS System in main service bay

U#6 Stay ring halves assembly in progress

U#5 LGB bearing pads blue matching completed

U#2 MDV installation in prgoress

U#1 UAB and starter panels cabling

U#1 Auxiliaries cabling in progress

U#1 Auxiliaries cabling

U#1 Excitation Transformer

U#1 MDV Servomotor positioning

U#1 Bypass valve pipeline routing

24V DC Battery Bank

220V UPS System Battery Bank

U#1 Gauge panel control wiring

U#1 Breaker panels

U#1 CW Strainer and sand seperator panels

U#1 Busduct CT Wiring

U#1 cable laying and termination

U#1 Discharge valve pipelines routing in progress

Station and WDS Compressors

U#1 Field efficiency pipeline routing

U#1 DT Water level indicator installed

U#1 GV Servo opening closing pipelines routing

U#1 CW Main outlet NRV installed

U#1 Bypass valve piping works i/p

U#1 Cable laying works

U#1 UAB Panels positioned

U#1 to 5 HP Common header pipeline routing i/p

Station air compressors and receivers erection

U#2 LGB CW pipeline final assembly

U#1 LP Air connections pipeline routing

U#1 10NB water pipelines routing

U#1 Brake dust collector piping

U#1 MDV Outlet pipe penstock welding

U#2 DT Drain valves installation in progress

U#1 Spiral drain valve installation completed

U#1 Ejector pipeline routing completed

U#1 DT Drain Valves installation completed

U#1 Water air pipelines inside turbine pit

U#6 Water Depression air receiver positioned

Compressed air pipeline routing in progress

HP & LP receivers positioning

U#1 Discharge valve pipelines routing in progress

U#1 Motor barell door installed

U#1 PGB CW O/L pipeline routing

U#1 Brake dust collector hopper assembly i/p

Installation & algnment of ACEB panels completed

U#4,5 WDS air receivers positioning in progress

U#3 air guides installation in progress

U#2 LGB oil coolers assembly completed

U#1 WDS pipeline routing completed

U#4 cyclone seperator erection is completed

U#3 CWS cyclone seperator and main header piping

U#2 10nb pipelines for servo valve routing in prog

U#2 Band drain pipeline routing is completed

U#2 Top brg and vapour seal assy is completed

U#1 water depression pipeline routing is in progre

U#1 DTT routing from brg to panel is in progress

U#1 Brush gear casing installation is completed

U#1 LGB Cooler piping assy is completed

U#5 bottom bracket lowering completed

U#2 oil manifold pipeline routing in progress

U#2 motor transformer dry out completed

U#1 band drain pipeline routing is completed

U#1 oil manifold pipeline routing is completed

U#2 Top bearing instrumentation work in progress

U#1 Water air pipelines routing in progress

U#1 Bottom vapour seal assy completed

U#1 Bottom oil coolers assy in progress

U#1 Top oil coolers assy completed

U#1 Top vapour seal assy completed

Dewatering sump-2 pipeline routing in progress

SFC Transformer hot oil circulation completed

U#2 10nb pipelines for servo valve routing in prog

U#2 MDV pushpull bolt,spacerflange bush replaced

U#2 Motor transformer

U#1 Turbine GB Housing assembly in progress

U#1 Motor transformer

U#4 Rotor rim building is in progress

U#2 LGB Bearing final assy in progress

U#1 MDV O/L pipe matching with penstock completed

U#1 TGB Housing assy

U#4 Rotor rim building is in progress

U#4 brake jacks assy in progress

U#3 top air guide assy in progress

U#1 oil pipelines routing in progress

U#2 top bearing pads assy completed

U#1 Turbine bearing housing assy i/p

U#1 Servo operated valves pipeline routing i/p

SFC output transformer pressure test carried

SFC input transformer oil filling completed

U#5 Stator CW pipelines

U#4 Rotor rim building in progress

U#3 Top air guide installation in progress

U#2 LGB assembly in progress

U#1 LGB instrumentation in progress

U#2 Transformer ready for oil filling

U#1 Transformer ready for oil filling

D&D sump-2 autocoupling pedestals erection in prog

U#4 CWS pump to strainer piping in progress

U#3 Cws pipeline works in progress

U#2 turbine bearing sump assy in progress

SFC Transformer erection is in progress

U#4 CWS Strainer skid lowering to turbine floor

U#3 CWS cyclone seperator and main header piping

U#3 busduct installation at ground level

U#1 Busduct installation at ground level

U#1 Transformer erection is completed

U#1 shaft seal testing is completed

U#2 shaft seal testing is completed

Panels installation is in progress

Panels installation is in progress

Panels installation is in progress

U#4 CW Strainer skid works are in progress

U#4 CW pump motor skid works are in progress

U#3 CW system pipeline works are in progress

U#3 cyclone seperators installation in progress

U#2 shaft seal installation is completed

U#2 transformer bushings installation is complete

U#1 transformers bushing installation completed

U#1 shaft seal installation is completed

U#5 View inside turbine pit

U#4 Stator CW pipeline outside barell completed

U#4 Stator CW pipeline inside barell routing i/p

U#4 CW system works in progress

U#3 Cooling water system works in progress

U#1 water depression pipeline routing is in progre

U#1 shaft seal installation in progress

U#3 CW pump motor assembly works are in progress

U#2 nutguard assembly and welding completed

U#1 water depression pipeline routing is in progre

U#2 Cyclone seperator pipeline routing and welding

U#1 nutguard assembly and welding completed

U#5 Installation of Pump platform is completed

U#2 Water depression pipeline routing in progress

U#5 GV servomotor alignment completed

U#2 CW main header near DT routing completed

U#1 CW main headers near dt routing completed

Water depression receivers positioning in progress

U#5 Guide apparatus assembly is in progress

U#1 mdv inlet and outlet pipe fitup in progress

U#4 Motor CW pipeline outside barell routing i/p

U#5 Water and air pipelines outside barell routing

U#5 Guide apparatus assembly is in progress

U#2 MDV inlet pipe welding is completed

U#2 Top oil vapour pipeline routing is completed

U#1 Cable routing works are in progress

U#1 Starter panels positioning in progress

UNIT 1-2 POSITIONING OF PRESSURE RECEIVERS IN PROG

UNIT1-2 POSITIONING OF FIRE FIGHTING PANEL COMPD

UNIT-3 SAC PIPE LINE WORK IN PROGRESS

UNIT-5 FLOOR PLATE SUPPORT FIXING IN PROGRESS.

UNIT-2 DC LEAD WOK IN PROGRESS

UNIT-3 ALIGHNMENT OF TUBULAR SHAFT AND SLIP RINGS COMPD

UNIT-1 TOP BOTTOM VAPOUR PIPING COMPLETED

WATAER DEPRESSION PIPE LINE HAEDER AT DV FLOOR

UNIT 1 & 2 PP SET CW PIPING WORK IN PROGRESS

UNIT-3 POSITIONING OF pp SETS COMPLETED

UNIT-5 INSPECTION AND CLEANING OF GUIDE VANES

UNIT-4 STATOR AND LOWER BRACKET

UNIT-2 CW LINES FOR TOP BOTTOM LABYRINTH

UNIT-4 INSTALLATION OF GUIDE APPARATUS COMPLETED

UNIT-3 COMBINED ALIGNMENT OF UNIT COMPLETED

UNIT-5 WELDING OF OTC IN PROGRESS

UNIT-4 GUIDE APPARATUS WORK IN PROGRESS

UNIT 1 -2 PRESSURE RECIEVERS POSITIONING IN PROGRS

UNIT1-10 WATER SYSTEM HEADER WORK IN PROGRESS

UNIT-2 STATOR AND ROTOR

UNIT-1 POSITIONING OF PP SETS COMPLETED

UNIT-2 LABYRINTH COOLING WATER PIPE LINES

UNIT-2 COOLING WATER SYSTEM LINES

UNIT-2 COOLIN WATER SYSTEM LINES

UNIT-1 COOLING WATER SYSTEM

SURGE POOL VIEW FROM TOP

UNIT-3 THRUST BEARING ASSEMBLY

UNIT-1 TOP,BOTTOM LABYRINTH COOLING WATER LINES

UNIT-5 PIVOT RING SEGMENTS

UNIT-1 TOP VAPOUR SEAL ASSEMBLY

UNIT-5 STATOR HAS BEEN LOWERED ON ITS SOLE PLATES

UNIT-3 ROTOR HAS BEEN LOWERED.

UNIT-3 LOWERING OF BOTTOM SHAFT

UNIT-6 DT CONE LOWERED

UNIT-4 IMPELLER/SHAFT LOWERING I

BUS DUCT WORK UNIT 3 TO 5 IN PROGRESS

CONTROL ROOM BUILDING

CONTROL ROOM -LAYING OF CABLE TRAYS IN PROGRESS

UNIT-5 GOUTING OF SPIRAL CASING COMPLETED

UNIT-7 CONCRETING OF DT LINER COMPLETED.

UNI-5 STAOR IS READY FOR LOWERING.

UNIT-4 REGULATING RING

UNIT-4 INSTALLATION OF GUIDE APPARATUS IN PROGRESS

UNIT-2 COOLING WATER PIPE LINE WORK IN PROGRESS

UNIT-1 COOLING WATER SYSTEM WORK IN PROGRESS

UNIT-1 AND 2 CARBON DUST COLLECTOR

UNIT-3 INSTALLATION OF PUMP PIT PLATFORM COMPTD

UNIT-2 BOTTOM AIR GUIDE ASSLY COMPLETED.

MOTOR FLOOR VIEW

UNIT-2 SHAFT CURRENT MONITORING CT

UNIT-1 WATER DEPRESSION SYSTEM WORK IN PROGRESS.

UNIT-1 WATER AND AIR PIPING WORK IN PROGRESS.

UNIT-4 INSTALLATION OF GUIDE APPARATUS IN PROGRESS

UNIT-5 BAZING OF STATOR BAR JOINTS COMPD

UNIT-5 BARREL CONCRETING IN PROGRESS

UNIT-1 ERECTION OF CW SYSTEM IN PROGRESS

UNIT-1 ERECTION OF COOLING WATER SYSTEM

UNIT1,2,3- BUS DUCT ERECTION IN PROGRESS

PANELS ERECTION IN PROGRESS IN CONTROL ROOM

UNIT-2 LGB COOLER PIPING WORK IN PROGRESS

UNIT-3 INSTALLATION OF PUMP PIT PLATFORM COMP

MOTOR FLOOR VIEW

UNIT-5 LAYING OF STATOR TOP AND BOTTOM BARS COMPTD

UNIT-4 GUIDE APPARATUS WORK IN PROGRESS

UNIT-2 BOTTOM AIR GUIDE ASSLY COMPLETED.

UNIT-2 INSTALLATION OF PIT AIR SEAL COMPTD

UNIT-3 STATOR COOLER PIPING WORK IN PROGRESS

UNIT-1 COOLING WATER SYSTEM PIPING WORK IN PROGR

UNIT-5 BARREL CONCRETING IN PROGRESS

UNIT-1 BUS DUCT( MOTOR FLOOR TO VERTICAL SHAFT)

UNIT-10 INSTALLATION OF DRAFT TUBE LINER COMPLETED

UNIT-6 STAY RING AND SPIRAL PEDESTALS

UNIT-4 STATOR LOWERING

UNIT-3 STATOR ON ITS SOLE PLATES

UNIT-1 BUS DUCT

UNIT-3 ROTOR IS READY FOR LOWERING

UNIT-2 LGB COOLER SUPPORT FIXING IN PROGRESS

UNIT-5 BUS DUCT

UNI-5 BARREL CONCRETING IN PROGRESS

UNIT-4 CENTERING OF STATOR COMPLETED

UNIT-4 ASSEMBLY OF PIVOT RING SEGMENTS IN PROGRESS

UNIT-3 ASSEMBLY OF GUIDE APPARATUS

UNIT-1 & 2 BUS DUCT ERECTION IN PROGRESS

MOTOR FLOOR VIEW

UNIT-3 ROTOR IS READY FOR LOWERING

UNIT-2 DISCHARGE VALVE AND OUTLET PIPE

UNIT-4 CLEANING AND PAINTING OF PUMP PIT

UNIT-4 LOWERING OF STATOR

MOTOR FLOOR VIEW

UNIT-5 BARREL CONCRETING IN PROGRESS

UNIT-2 TOP AIR GUIDE AND BAFFLES ASSEMBLY COMD

UNIT-2 PUMP PIT PLATFORM COMPLETED

UNIT-4 STATOR LOWERING

UNIT-5 INSTALLATION OF BUS DUCT IN PROGRESS

UNIT-10 INSTALLATION OF DRAFT TUBELINER COMPLETED

UNIT-7 INSTALLATION OF DRAFT TUBE LINER COMPLETED

UNIT-6 DRAFT TUBE CONCRETING COMPLETED

CONTROL ROOM BUILDING

MOTOR FLOOR VIEW

UNIT-2 HYDRAULIC TESTING OF DISCHARGE VALVE COMPD

UNIT-3 ROTOR FAN MOUNTING IN PROGRESS

UNIT-5 BARREL CONCRETING IN PROGRESS

UNIT-4 BARREL CONCRETING COMPLETED

UNIT-3 GUIDE APPARATUS

UNIT-2 FLOOR PLATES SUPPORTS

UNIT-2 COMPLITION OF GUIDE APPARATUS SYSTEM

UNIT-1 SHAFT CURRENT MONIT0RING SYSTEM

UNIT-1 PUMP PIT PLATFORM

U-3 STATOR

U-2 NUT GUARD ASSEMBLY IN PROGRESS

U-3 ROTOR RIM RADIUS CORRECTION IN PROGRESS

U-5 POSITIONING OF PIT LINER SLEEVES IN PROGRESS

U-4 BARREL CLEANING IN PROGRESS

U-3 gV LINK LEVELLING IN PROGRESS

U-2 FLOOR PLATES SUPPORT FIXING IN PROGRESS

U-1 TOP AIRGUIDE AND BAFFLES

motor floor view

MOTOR FLOOR VIEW

UNIT-1 HYDRAULIC TESTING OF DISCHARGE VALVE

UNIT-1 PUMP PIT PLATFORM

UNIT-5 CONCRETING OF SPIRAL IN PROGRESS

UNIT-4 BARRELL CONCRETING COMPLETED

UNIT-3 ALIGNMENT OF SERVO MOTORS COMPLETED

UNIT-2 UNIT ALIGNMENT COMPLETED

uni-3 rotor rim building completed

unit-4 bus duct

unit-1 trial assbly of pump pit platform comltd

unit-6 concreting of draft tube completed by cstmr

unit-3 alignment of GV servomotors in progress

motor floor view

unit-5 GV mounting plate positioning in progress

unit-3 centering and levelling of stator completed

unit-1 stator and ugb cooling line

unit-4 barrel concreting in final stage

unit-2 alignment of gv servo motors completed

unit-4 brazing of stator bar joints in progress

unit-2 alignment of unit is under progress

unit-3 rotor rim building in progress

unit-2 rotor has been lowered

UNIT-2 HV TEST ON ROTORS POLES COMPLETED

UNIT1-3 WATER AND AIR PIPE LINES WORKS IN PROGRESS

UNIT-4 STATOR TOP BARS LAYING IN PROGRESS

UNIT-4 BARREL CONCRETING IN PROGRESS

UNIT-2 THRUST BEARING ASSLY

UNIT-3 STATOR AND LGB BRACKET

UNIT-5 LOWERING OF BOTTOM SHAFT /THRUST BEARING

UNIT-3 ASSEMBLY OF GUIDE APPARATUS IN PROGRESS

UNIT-2 ALINGMENT OF gv SERVO MOTORS IN PROGRESS

UNIT-1 ALIGNMENT OF SERVO MOTORS COMPLETED

UNIT-5

UNIT-4 CONCRETING OF BARREL IN PROGRESS

UNIT-1 TRIAL ASSEMBLY OF STATOR COOLERS

UNIT-3 IMPELLER

UNIT-2 POLES MOUNTING COMPLETED

UNIT1 ASSEMBLY OF GUIDE APPARATUS IN PROGRESS

UNIT-1 BOXUP OF UNIT IS UNDER PROGRESS

UNIT-4 BUS DUCT ERECTION IN PROGRESS

UNIT-1 ROTOR RIM BUILDING IN PROGRESS

MOTOR FLOOR VIEW

UNIT -2 BOTTOM BRACKET

SPIRAL AND PIT LINER

UNIT-4 CONCRETING OF BARREL IN PROGRESS

UNIT-3 DOWELLING OF ITC AND OTC

UNIT--2 NO WORK DUE TO MATERIAL NOT RECIEVED

UNIT-1 ALIGNMENT OF UNIT IN PROGRESS

UNISTATOR BAR TO BAR JOINT BRAZING COMPLETEDT-3

UNIT-2

UNIT-3 ASSEMBLY OF SEAL RETAINERS AND FACE SEALS

UNIT-4 BARRELL CONCRETING IS UNDER PROGRESS

UNIT-5 UNIT RELEASED FOR CONCRETING

UNIT -1 ROTOR LOWERING

UNIT-2 STATOR HAS BEEN LOWERED ON SOLE PLATES.

UNIT-1 GUIDE APPARATUS WORK IS IN PROGRESS

UNIT-5 INSTALLATION OF PIT LINER COMPLETED

UNIT-4 BARRELL CONCRETING IN PROGRESS

UNIT-3 CENTERING AND LEVELLING OF PIVOT RING/OTC

UNIT-1 LOWERING OF BOTTOM SHAFT/ THRUST BEARING

UNIT-2 LOWERING OF TOP ITC COMPLETED

UNIT-1 LOWERING OF STATOR COMPLETED

UNIT-3 JOINING OF STATOR SEGMENTS

BUS DUCT UNIT 1,2 AND 3

MOTOR FLOOR VIEW

UNIT-1 ROTOR

UNIT-5 PREPARATION FOR PIT LINER LOWERING

UNIT-4 CONCRETING OF MOTOR BARREL IN PROGRESS

UNIT-3 PREPARATION FOR PIVOT RING LOWERING

UNIT-2 FIXING OF SEAL RETAINERS AND SEALS

UNIT-1 impeller with shaft lowered in pit

CONTROL ROOM BUILDING

SWITCHYARD AREA

DELIVERY LINES( PENSTOCK) UNIT 1 TO 5

UNIT-3 BUS DUCT ERECTION IN PROGRESS

UNIT-5 WELDING OF DT CONE AND FOUNDATION RING I

UNIT-4 CONCRETING OF MOTOR BARREL IN PROGRESS

UNIT-3 CONCRETING OF BARREL COMPLETED

UNIT-1 FINAL VH OF ROTOR POLES COMPLETED

UNIT-2 LOWERING OF OTC QUADRANTS IN PROGRESS

UNIT-1 ASSEMBLY OF GUIDE APPARATUS IN PROGRESS

UNIT-1 ERECTION BUS DUCT IN PROGRESS

UNIT-5 ERECTION OF FOUNDATION RING IN PROGRESS

UNIT-4 CONCRETING OF BARREL IN PROGRESS

UNIT-3 CONCRETING OF BARREL IS UNDER PROGRESS

UNIT-2 LOWERING OF PIVOT RING QUADRANTS

UNIT-1SOLDERING OF ROTOR POLE CONNECTION

UNIT-1 POSITIONING OF GUIDE VANES

CONTROL ROOM

UNIT1 AND 2 ERECTION OF BUS DUCT IN PROGRESS

VIEW OF MOTOR FLOOR UNIT- 1 TO10

VIEW OF UNIT 6-10

UNIT-6 ERECTION OF DRAFT TUBE IN PROGRESS

UNIT-5 POSITIONING OF FOUNDATION RING

UNIT-4 CONCRETING OF BARREL IN PROGRESS

UNIT-3 POSITIONING OF STATOR SLE PLATE SLEEVES COMPLETED

UNIT-2 GROUTING OF STAY RING AREA COMPLETED

UNIT-1 POSITIONING OF PIVOT RING COMPLETED

UNIT-1 TIGHTEING OF POLE KEYS IN PROGRESS

UNIT-5 LEVEL CHECK OF STAY RING AFTER HYDRO TEST

MOTOR FLOOR

UNIT-5 HYDRAULIC TESTING OF SPIRAL CASING

UNIT-4 CONCRETING OF BARREL IS UNDER PROGRESS

UNIT-3 CONCRETING OF BARREL IS UNDER PROGRESS

UNIT-2 BARREL CASTING COMPLETED

UNIT-1 MOUNTIN OF POLE

UNIT-1 WELDING OF OTC SEGMENTS IN PROGRESS

UNIT-1 MOUNTING OF ROTOR POLES IN PROGRESS

UNIT-5 WELDING OF SPIRAL SEG AND MAKE-UP PIECES

UNIT-4 CONCRETING OF PIT LINER IN PROGRESS

UNIT-3 CONCRETING OF BARREL IS UNDER PROGRESS

UNIT-2 MOTOR BARREL CONCRETING IN PROGRESS

UNIT-1 LOWERING OF PIVOT RING SEGMENTS

Unit- cleaning of pump pit in progress

Unit-1 measurement of rotor rim dia in progress

Unit-5 erection of spiral make-up pieces

Unit-4 concreting of pit liner in progress

Unit-3 concreting of barrel is under progress

Unit-2 positioning of stator sole plate sleeves

Unit-1 top view

Unit-1 stator has been lowered on its sole plates

Unit-2 bus duct erection in progress

Unit-1 torque tightening of rotor rims completed

Unit-5 erection of spiral make-up pieces

Unit-4 concreting of pit liner in progress

Unit-3 concreting of barrel is under progress

Unit-2 bus duct erection in progress

Unit-1 finishing of motor barrel in progress

Unit-1 tightening of rotor rims in progress

Unit-5 welding of spiral segments in progress

Unit-4 concreting of pit liner in progress

Unit-3 positioning of LGB sloe plate sleeves

Unit-2 motor barrel concreting in progress

Unit-1 cleaning of barrel in progress

Unit-5 Welding of spiral segments in progress

Unit-3 LGB Sloe plate cut out

Unit-2 Stator Sole Plate and air duct cut out

Unit-1 Grouting of spiral and foundation ring

Unit-1 Rotor rim building completed

Unit-5 erection of spiral segments in progress

Unit-4 concreting of pit liner in progress

Unit-3 motor barrel concreting in progress

Unit-2 motor barrel concreting in progress

Unit-1 cleaning of motor barrel in progress

Unit-1 erection bus duct in progress

Unit-1 rotor rim building completed

Unit-1 rotor rim building in progress.

Unit-5 erection of spiral segments

Unit-4 concreting of pit liner in progress

Unit-3 LGB sloe plate cut out

Unit-2 motor barrel concreting in progress

Unit-1 positioning of stator sole plates

Unit-1 positioning of stator sole plates

Unit-1 Erection bus duct in progress.

Unit-5 erection of spiral segments

Unit-5 erection of spiral segments

Unit-1 rotor rim building in progress

Unit-4 concreting of pit liner in progress

Unit -3 Laying of barrel reinforcement RODS

Unit-2 motor barrel concreting in progress

Unit-1 finishing of motor barrel /pump in progress

Unit-1 second pressing of rotor rim building

Unit-5 erection of spiral segments

Unit-4 concreting of spiral casing in progress

Unit-2 laying of reinforcement rods in progress

Unit-3 motor barrel concreting in progress

Unit-1 finishing of motor barrel in progress

Unit-1 rotor rim building in progress.

Unit-5 alignment of spiral partition plate seg.

Unit-4 concreting up to pump centre completed

Unit-3 LGB sloe plate cut out

Unit-2 motor barrel concreting in progress

Unit-1 finishing of motor barrel in progress

Unit-1 first pressing of rotor rim building

Unit-5 erection of spiral segments

Unit-4 concreting up to Pump Centre completed

Unit-2 LGB sloe plate cut out

Unit-3 Motor barrel concreting in progress

Unit-1 motor barrel concreting completed

Unit-1 erection bus duct in progress

Unit-5 erection of spiral segments

Unit-4 positioning of 2nd stage pit liner sleeves

Unit-3 positioning of LGB sole plate cut out frame

Unit-2 motor barrel concreting in progress

Unit-1 concreting of motor barrel completed

Unit-5 elevation and centre stay ring

Unit-4 positioning of 2nd stage pit liner sleeves

Unit-3 motor barrel concreting in progress

Unit-2 motor barrel concreting in progress

Unit-1 concreting of motor barrel completed

Unit-5 welding of stay ring joints in progress

Unit-4 positioning of 2nd stage pit liner sleeves

Unit-3 LGB sloe plate cut out

Unit-2 positioning of LGB sole plate sleeves

Unit-1 concreting of motor barrel in progress

U#4 Pit liner and Spiral Casing

U#3 Barrel Concreting in Progress

U#2 Barrel Concreting in Progress

UNIT-1 ERECTION OF BUS DUCT IN PROGRESS.

Unit-5 welding of Stay Ring Joints in progress

Unit-4 Concreting of spiral casing in progress

Unit-3 Pit liner concreting in progress

Unit-2 Motor Barrel Concreting in progress

Unit-1 Concreating of Motor Barrel in progress

U-1 Rotor Rim Building

U-1 Generator Barrel

U1 Generator Barrel

Unit-1 motor stator ready for erection

Unit-1 preparation for rotor rim building in progress

Unit-5 Full Welding of Stay ring joints in progress

Unit-4 concreting up to Pump center completed

Unit-3 completion of second stage embeddments

Unit-2 Motor Barrel Concreting in progress

Unit-1 Motor Barrel Concreting in progress

Unit-6 to 10- 1st stage embedment erection in prog

Unit-5 stay ring leveling & centering in progress

Unit-4 pit liner and spiral casing

Unit-3 Generator barrel concreting in progress

Unit-2 Generator barrel concreting in progress

Unit- 6 to 10- Erection of 1st stage embedment in progress

Unit-1 Generator barrel concreting in progress