TUIRIAL HEP [NEEPCO] (2 X 30 MW)


Both Unit in Running Condition/

Rotor 2 Erection in Pit/

Unit 1 and 2/

Unit 2 Upper Bracket/

Unit 2/

Stator Unit 2/

Rotor Unit 2/

Sync of Unit 1/

Rotor 2/

Stator 2/

Lower Bracket 2/

Unit 2/

Unit 2 Stator/

Unit 2 Rotor/

Unit 1/

Unit 2 Job/

Unit 1 Panel/

Unit 1 and 2/

Unit 1 and 2/Top View

Unit 2/Stator

Unit 2/Rotor

Unit 2 / Rotor

Unit 1 and 2 / Top View

Generator Barrel/Unit 2

Stator Joining of Segment/Unit 2

OPU System at 29m EL Floor/

Bus Duct and Cabling Work/

Transformer Yard/

Valve Pit/Fixing of valves completed

Drainage Sump/

Dewatering Sump/

HSS Lubrication/Unit 1

MIV and Inlet pipe erected/Unit 1

Fixing fans and interconnections of pole/Unit 1

Stator in Position/Unit 1

Generator Barrel Concreting /Unit 2

Turbine Pit/Unit 1

Fixing of Pole and Key /Rotor Unit 1

Generator Shaft/Unit 1

Generator Barrel/Unit 1

Generator Barrel/Unit 1

Unit 2/Transformer Shifting

Unit 2/Spiral Casing HT done

Unit 1 MIV (Main Inlet Valve)/Foundation Plate Fixed

Unit 1 Turbine/Pivot Ring Fixed

Unit 1 Rotor/Final Pressing, Pole Fixing done

Unit 1 Stator/Final HV test, Painting, finishing done

Spiral 2 with Pit Liner/

Rotor 1/

Stator 1/

Top Cover/

Guide Vane 1/

Stator of Unit-1/

Stator of Unit-1/

Rotor of Unit 1/

Pivot Ring Job of Unit-1/

Pivot Ring Job of Unit-1/

Pit Liner of Unit-2/

Pit Liner of Unit-2/

Duplex Filter/

Unit 2 Spiral Casing/

Transformer Bay/

Stator/

Rotor/

Gen Barrel/

Top bar fixing under progress at Stator/

Ruuner removal Trolley/

Transformer Bay/

Shifting of panels at Floor/

DSL of EOT crane/

generator barrel of unit 1/

/

/

/

/

Stator Job at Service Floor/Unit 1

Rotor Rim Punching Job/Unit 1

Stay Ring Alignment/Unit 2

Drainage Dewatering /Piping Job

Barrel Concreting at 33.5 m/Unit 1

Cable Tray Job/

Spiral Shifting/Unit 2

Barrel Concreting/Unit 1

Unit 2/

Transformer Bay/

Stator Job/

Rotor Job/

HV Test Kit/

Front Side of PH/

D Line Side Job/

B Line Side Job/

Unit 2/Stay Ring

Unit 1/Barrel Casting Job

Unit 1/Progress

EOT Beam/

Cable Tray Erection/

Cable Tray fixing at EL33.5M and EL38M/under progress

Cable Tray fixing at EL33.5M and EL38M/under progress

/under progress

Second Pressing of Rotor Rim Plate /Completed

Four segment of Stator alignment /under progress

TUIRIAL HEP/Progress

TUIRIAL HEP/Progress

TUIRIAL HEP/Progress

TUIRIAL HEP/Progress

TUIRIAL HEP/Progress

TUIRIAL HEP/Progress