EPC SIKKA -3 250 MW


Service building AC plant Chillers room/

Service building AC plant Chillers room/

Unit #3

Unit #3

Unit # 3

Unit # 3

Unit #3 – Boiler A–B side, Hot Air

Unit #3 – Boiler A–B side, Hot Air

Compressor house - Air receiver painting/

Fire Protection system readiness: for UAT, ST

Fire Protection system readiness: for UAT, ST

Unit 3 Vacuum Pump/

LDO HFO UNIT#3

UNIT#3 ESP‐A/

Chimney #3 and #4/

COOLING TOWER#3/

CW Pump House/

Pump house building/

Box Type Under ground Tunnel/

ESP A/

Turbine Floor/

LDO

Cooling Tower/

Box‐pushing type under‐ground tunnel work (ISG Scope)/

Box‐pushing type under‐ground tunnel work/In Progress

Switch yard work for Unit #3

ESP Pass ‐A/

Chimney/

Cooling Tower/In Progress

STATION TRANSFORMER ERECTION/UNDER PROGRESS

CLARIFIED PUMP HOUSE MOTOR ERECTION/UNDER PROGRESS

UAT ST BUSDUCT CONNECTION/UNDER PROGRESS

LEFT SIDE HOT PA AND COLD PA ERECTION/UNDER PROGRESS

BUNKER TO ESP DUCTING INSULATION/In Progress

TG Floor/In Progress

Boiler-LHS Elevation/Coal Mill Erection Under Progress

Boiler-LHS Elevation/Coal Mill Erection Under Progress