/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
HRSG insulation and filling works/
|
LP and IP line to STG erection /
|
Condensate line from WPH outlet to De Aerator piping /
|
Deaerator and UCFT filling, Water wash skid piping /
|
DM Tank 2 fabrication /
|
CT works under progress/
|
SW piping under progress/
|
ACW pump 2 and CW pump 1 /erection and alignment
|
De-aerator piping works /
|
CW line connection with Condenser /
|
STG rotor placed for centering/
|
HRSG insulation and filling works under progress/
|
LP and IP line to STG erection /
|
Condensate line from WPH outlet to De Aerator piping/
|
Deaerator, UCFT filling, CCW expansion tank, Water wash skid piping/
|
DM Tank 2 fabrication under progress/
|
LP and IP piping suction and discharge hydro-test completed/
|
SW piping under progress/
|
CT works under progress/
|
ACW pump 2 erection and alignment under progress/
|
De aerator piping works in progress/
|
CW line connection with Condenser under progress/
|
STG rotor placed for centering/
|
Clarified Water Pipeline TP 01 Connection with Customer Terminal/
|
DM Pump Foundation, MCC Room /
|
Clarified Water Pump House/Grade Slab, All Columns Completed
|
Clarified Water Pump House/Pump Foundation and Roof Slab Under Progress
|
CT Make Up Line Valve Station Erection /
|
ACW Pump1 Erection/
|
CT Fills Erection /
|
De-Aerator Erection, Alignment, Welding /
|
HP BFP 1, 2 and 3 Suction Line Hydro Test/
|
CW Line to Condenser Erection /
|
STG Lube Oil Flushing /
|
Generator Air Cooler Installed/CCW Line Connected To STG Cooler
|
Casing Centering and Leveling / for Rotor Placement
|
STG Rotor Cleaning/
|
HP BFP 1 and 3 oil flushing/
|
Clarified water pipeline TP 01 connection with customer terminal/
|
HRSG HP line hydrotest /Insulation
|
DM tank water filling completed/Observation under progress
|
CT make up line erection and alignment /
|
CW discharge pipeline erection/ACW pump 1 blue matching
|
STG bottom casing erection completed/
|
STG Lube oil flushing started/
|
HRSG painting/Insulation
|
HP Feed station welding /
|
DM water storage tank/fabrication and erection
|
HP BFP 1 oil flushing /
|
ST exhaust bottom casing/placed
|
STG oil pipeline /erection
|
CW pipeline/erection
|
Clarified water pipe line /erection and alignment
|
Clarified water pipeline connection with customer terminal /erection and alignment
|
STG Expansion bellow erection and fit up /
|
Feed water piping welding /
|
Preparation for erection of de aerator/
|
Clarified water valve station erection /
|
Clarified water pipeline erection /
|
HRSG painting works and Insulation/
|
HP Feed station erection /
|
Clarified water reservoir /inlet Valve station erection
|
Horizontal and Vertical baffle plate erection /Painting and Insulation
|
BFP 1 and 3 lube oil cooler piping/motor, hydraulic coupling
|
CEP discharge and CEP suction/Piping erection
|
Condenser dome erection and alignment /completed
|
LP auxiliary steam piping and DM fill piping/erection in progress
|
HP BFP Discharge Line and HRSG fill Piping Erection/in progress
|
Front and rear bearing pedestal blue matching/
|
HP FW line erection /
|
Condenser tubing and flaring /
|
52in CW, 38in CW and 20in ACW pipe erection near CWPH /
|
Steam jet ejector and Gland steam condenser piping/
|
Steam turbine generator erection done/
|
Top vertical and bottom baffle, HP vent piping /in progress
|
IP, LP, HP FW line and HP BFP alignment /in progress
|
Condenser tubing erection/
|
34inch CW pipe erection /
|
56inch CW pipe erection towards CT /
|
52inch CW and 20inch ACW pipe erection /near CWPH
|
HRSG fill pump, regeneration pump, DM pump alignment done/Ready for grouting
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
DM Plant /Work in Progress
|
Excavation for Clarified Water Pipeline/
|
Cooling Tower/Work in Progress
|
CW Line/Work in Progress
|
CW Line/
|
STG Bldg./
|
Cooling Tower/
|
CW Piping Work/Under Progress
|
Clarified Water Pump House/Foundation completed
|
STG Building /Condenser Erection
|
CW LINE /
|
DM PLANT /
|
STG BUILDING /
|
BFP Building/FST Erected , CCW piping progress
|
Road/Last Layer WBM work under progress
|
CW Line/piping work under progress
|
BFP Building /work under progress
|
STG/work under progress
|
GBC 2 /piping work under progress
|
Cooling Tower/Casting of RCC columns, beams, wind wall under progress
|
GBC/GBC 2 Piping and Painting Under Progress
|
HRSG/Roof Sheeting and HP PP fit up progress
|
HRSG/LP HT complete, Roof Sheeting under progress
|
GBC/GBC 2 under Progress
|
IAPA/2 Air Compressor, 1 ADU, 1 Nitrogen Plant
|
Namrup/Transformaer
|
Namrup/GT
|
Namrup/HRSG
|
STG building B-C Bay 4.5 Mtr floor/ In progress
|
IA
|
GTG Building Area/ In progress
|
GCB
|
CCW Area/In Progress
|
Transformers Yard/In Progress
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
/
|
Drain Works/In Progress
|
Road Works/In Progress
|
Transformer Yard/In Progress
|
SWAS Analyser Building/In Progress
|
GTG Building/In Progress
|
AC Plant Room/In Progress
|
STG Foundation/In Progress
|
BFP Foundation/In Progress
|
Cooling Tower/In Progress
|
Cooling Water Pump House/In Progress
|
Clarified Water Reservior/In Progress
|
DM Plant- Piling Work/In Progress
|
Bypass Stack and STG Building/In Progress
|
Grit Blasted and Primer Coated Bracings/
|
Batching Plant/In Progress
|
Construction of Drain New Switchyard/In Progress
|
Grading of earth for auxilary foundation/In Progress
|
SFC Building Columns/In Progress
|
Firewall columns of Station Auxilary transformer/In Progress
|
Structural works /In Progress
|
Firewall of GT Transformer/
|
Cleaning and Chipping of STG Column/ In progress
|
NAMRUP/Progress
|
NAMRUP/Progress
|
NAMRUP/Progress
|
Clarfied water tank-PH/Progress
|
De-aerator-BFP/Progress
|
Bypass stack-HRSG-Chimney/Progress
|
Cooling Tower/Progress
|
GT Hall/Progress
|
STG-Control bldg/Progress
|